Question

Project UMUC is to produce 200 widgets and is scheduled to take five weeks. Each unit...

  1. Project UMUC is to produce 200 widgets and is scheduled to take five weeks. Each unit is planned to cost $90. The project is severely cost constrained. Performance data for the project at the end of week three is presented below:
  • 120 total units were planned to be produced
  • 130 units have actually been produced
  • The financial manager reported that the business had actually spent $13,000 on the project by the end of week three.

Answer the following questions; show all work:

  1. What is the forecast of project cost at completion assuming current cost performance efficiency remains the same? How much budget variance is expected at completion?
  2. What is the forecast of funding needed to complete the project (from this point forward)?
  3. What cost performance efficiency would be required for the remainder of the project to complete the project within the original budget?
  4. As the project financial manager, what recommendations would you make?
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Please rate the earlier solution where first four parts were answered.

What is the forecast of project cost at completion assuming current cost performance efficiency remains the same? How much budget variance is expected at completion?

Forecast of project cost at completion = Actual cost / Actual number of units x total number of units = (13,000 / 130) x 200 = $ 20,000

Budget variance expected at completion = Forecast of project cost at completion - budget cost = 20,000 - 200 x 90 = $ 2,000

What is the forecast of funding needed to complete the project (from this point forward)?

forecast of funding needed to complete the project (from this point forward) = Forecast of project cost at completion - cost incurred so far = 20,000 - 13,000 = 7,000

What cost performance efficiency would be required for the remainder of the project to complete the project within the original budget?

Balance budget cost = (Budget cost - cost incurred so far) =(200 x 90 - 13,000) = 5,000

Balance number of units = (200 - 130) = 70

Cost performance efficiency = Earned Value on balance units / Balance budget cost = 70 x 90 / 5,000 = 126.0%

As the project financial manager, what recommendations would you make?

Recommendations:

  • Cost control: The budget has exceed so far and is likely to remain exceeded unless cost is controlled. hence, focus on cost control.
  • Arrange for external funding, the budget is likely to be exceeded. In order to prevent time overrun, look for funding right now.
Add a comment
Know the answer?
Add Answer to:
Project UMUC is to produce 200 widgets and is scheduled to take five weeks. Each unit...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 2. You are 4.5 months into a 6-month, $12,000 project with a planned linear spend rate....

    2. You are 4.5 months into a 6-month, $12,000 project with a planned linear spend rate. You have an earned value of $8,500 and you have spent $10,000. What is your EAC? (2 points) 3. The earned value on your project is $15,000, the planned value is $20,000, and the actual cost is $18,000. What is your current schedule variance (in $)? (1 point) 5. You are working on a large project and have determined that your cost variance is...

  • 16. Jane is a project manager for a company that produces two special widgets each year...

    16. Jane is a project manager for a company that produces two special widgets each year for suppliers around the world. Jane receives a project schedule of 10 months and a budget with estimates of what it will cost to produce both widgets (shown below). The project requires 200 widgets to be produced per month for Widget A, and 100 widgets to be produced per month for Widget B. Activity Widget A Widget B Total Start Jan 1 Mar 1...

  • At week 10 of a project below to improve distance learning platform, assume that the planned...

    At week 10 of a project below to improve distance learning platform, assume that the planned values (PV) are based on time proportionality but the “% Complete” values for earned values (EV) are from the workers actually doing the tasks. ACTIVITY PRE- DECESSORS DURATION (WEEKS) BUDGET ($) ACTUAL COST ($) % COMPLETE A - 5 500 640 100 B A 3 300 400 100 C B 4 320 310 80 D B 6 600 250 60 E C,D 3 300...

  • #1. A project in its 26th week has an actual cost of $270,000. It was scheduled...

    #1. A project in its 26th week has an actual cost of $270,000. It was scheduled to have spent $261,000. For the work performed to date, the budgeted value is $272,000. What are the cost and schedule variances for the project? What are the SPI and CPI? What is your assessment of the project from a cost and schedule perspective? #2. A project has just completed the 87th item in its plan. It was scheduled to have spent $168,000 at...

  • A road resurfacing and barrier protection project, planned to take 30 weeks to complete, is underway....

    A road resurfacing and barrier protection project, planned to take 30 weeks to complete, is underway. Week 35 of the project has just ended. You are to use the Earned Value Analysis technique with the data provided in Table A1, to monitor the project's progress and answer the following question: a) Assuming nothing changes, work out the new total estimated cost at completion and the new to estimated time at completion (to 1 decimal place). D) What does your answer...

  • 2. Can the project be completed before construction can begin, which is scheduled 40 weeks later?...

    2. Can the project be completed before construction can begin, which is scheduled 40 weeks later? a. Yes, because the project duration time is 39 weeks. b. No, because the project duration time is 41 weeks. c. No, because the project duration time is 42 weeks. d. Yes, because the project duration time is 40 weeks. 3. Which activities can be delayed without delaying the projection completion time? a. B, D and F b. B, D and G c. A,...

  • Question 1: The following data and table illustrate a small project: Activity A was completed on...

    Question 1: The following data and table illustrate a small project: Activity A was completed on schedule • Activity B started as planned but it is expected to take four weeks more Activity C started as planned but finished one week later • %age of completion of activity D is 60% ACWP at the end of week 10 = SR 90400 Activity Original Planned Start Time Original Planned Finish Time Wage Complete Amount Completed BCWP Amount Scheduled BCWS Amount Spent...

  • Use the following project status information to calculate each of the requested EVM numbers below. The...

    Use the following project status information to calculate each of the requested EVM numbers below. The project status is reported at the end of week 13. 5. Cost performance index: 6. Schedule performance index 7. Budget at completion 8. Estimate to complete 9. Estimate at completion Task Budget Cost Budget Duration Status as of Week 13 A $5,000 2 weeks 100 percent com- plete, $5,000 B $8,500 3 weeks 100 percent com- plete, $9,000 с $15,000 4 weeks 75 percent...

  • Complete the following exercises and submit them in a word document (10 points). Project ABC Scope...

    Complete the following exercises and submit them in a word document (10 points). Project ABC Scope = 10 chairs @ $10.00 = $100.00 PV = Timeframe = 10 days At the End of the 5th day 4 chairs were EV = Completed at a cost of $11.00 each CPLE SV = SPIE To install a 10,000 feet fence at a cost of $10.00/per foot. It is estimated that 500 feet of fence can be installed per week for a total...

  • Project ABC Scope = 10 chairs @ $10.00 = $100.00 PV = Timeframe = 10 days...

    Project ABC Scope = 10 chairs @ $10.00 = $100.00 PV = Timeframe = 10 days AC = At the End of the 5th day 4 chairs were EV = Completed at a cost of $11.00 each CV = CPI= SV = SPI= CR = To install a 10,000 feet fence at a cost of $10.00/per foot. It is estimated that 500 feet of fence can be installed per week for a total of 20 weeks. After 12 weeks and...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT