2.
Can the project be completed before construction can begin, which is scheduled 40 weeks later?
a. |
Yes, because the project duration time is 39 weeks. |
|
b. |
No, because the project duration time is 41 weeks. |
|
c. |
No, because the project duration time is 42 weeks. |
|
d. |
Yes, because the project duration time is 40 weeks. |
3.
Which activities can be delayed without delaying the projection completion time?
a. |
B, D and F |
|
b. |
B, D and G |
|
c. |
A, D and G |
|
d. |
A, D and F |
4.
To meet the 40-week construction deadline, what activities the manager should crash if necessary? What is the cost?
a. |
Crash E and G by 1 week respectively at a total cost of $3000. |
|
b. |
There is no need to crash because it is meeting the deadline. |
|
c. |
Crash E by 2 weeks at a cost of $4000. |
|
d. |
Crash F by 1 week and G by 2 weeks respectively at a total cost of $2800. |
|
e. |
Crash F by 1 week at a cost of $800. |
The precedence diagram as follows :
A |
B |
|
C |
||
D |
E |
|
F |
G |
|
H |
||
The possible paths and their corresponding durations as follows :
A-C-D-F-H = 8 + 12 + 3 + 7 + 8 = 38
B-C-D-F-H = 6 + 12 + 3 + 7 + 8 = 36
A-C-E-F-H = 8 +12+6 +7+8 = 41
B-C-E-F-H = 39
A-C-E-G-H = 42
B-C—E-G-H = 40
Out of above. A-C-E-G-H has the longest duration and hence forms the critical path.
ANSWER : d) A-C-E-G-H |
Answer to Question 2 :
Answer : c) No, because project duration time is 42 weeks
Answer to question 3 :
Those activities which don’t fall on critical path can be delayed without delaying overall duration of the project
Such activities are , B ,D,F
ANSWER : a) B,D,F |
Answer to question C :
One /or more of the activities on the critical path should be crashed by a total of 2 weeks to meet the project deadline of 40 weeks
From the given data , it can be E.F,G which can be crashed. However , we rule out F since it does not fall on the critical path.
So , we are left with choices E or G
So , we crash E and G (both of which lie on critical path) at a cost of $2000 + $1000 = $3000
2. Can the project be completed before construction can begin, which is scheduled 40 weeks later?...
Suppose that Rafay is only given 7 weeks (instead of 10) to complete the project . By how many weeks should each activity be crashed in order to meet the deadline? Assume that you can crash an activity down to 0 weeks duration. Activity Each Activity Should be Reduced BY (weeks) A (weeks)- ? B (weeks)- ? C (weeks)- ? D (weeks)- ? E (weeks)- ? F (weeks)- ? What is the total crashing cost ? The following is a...
The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations, what activities each must precede and the crash cost to reduce duration per week: Activity Duration (weeks) Precedes Crash Cost/Week A (start) 2 B, C $ 370 B 2 E $ 130 C 4 F $ 200 E 1 F $ 150 F (end) 2 — $ 420 Suppose that Rafay is only given 5 weeks (instead of 8) to...
QUESTION 9 Consider the following project; for which activities is it possible that the slack can be greater than zero? Activity Immediate Predecessors B, E a. Only activities B or E could have slack, but they could not both have slack. Ob. Only activities B or C could have slack, but they could not both have slack. Oc. It is possible for any or all activities in this project to have slack. Od. It is possible for either all three...
Use a PERT network to establish the expected duration for the project described in the table below: (SHOW the PERT NETWORK) Activity Predecessors Duration a m b Exp. Duration Var. Crash Week 1 Crash Week 2 A - 3 6 9 700 100 B A 6 7 14 600 200 C A 4 6 14 400 600 D B, C 4 6 8 200 600 E B, C 6 9 12 400 300 F C 4 6 14...
The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations, what activities each must precede and the crash cost to reduce duration per week: Duration (weeks) Activity A (start) Precedes B, C Crash Cost/Week $400 $100 $200 $300 $400 F F (end) 2 Suppose that Rafay is only given 5 weeks (instead of 7) to complete the project. By how many weeks should each activity be crashed in order to...
Normal Time Crash Time Normal with Activity (weeks) (weeks) Cost Crashing Immediate Predecessor(s) $1,400 A 3 2 $2,050 $2,800 B 2 1 $2,100 1 1 $350 $350 7 $1,400 $1,700 A 6 3 $900 $1,200 $5,000 $2,000 F 2 $4,000 $1,500 C 4 G 2 D, E weeks a) Based on the given information regarding the activities for the project, the project completion date b) To reduce the duration of the project to 10 weeks at the least cost, the...
Megah Holding Sdn. Bhd is in progress to start their housing project. The list of activity and scheduled of the project is proposed as in Table 1. If the indirect costs for each duration is as follows, compute the direct and total cost for each duration. What is the optimum cost-time schedule? Indirect cost 27 weeks – RM 350 26 weeks – RM 270 25 weeks – RM 160 24 weeks – RM 100 12 weeks – RM 70 (12...
Consider a project having the following six activities: Immediate Max Crash cost Activity Predecessors Time (weeks) Crash* per week A none 6 6 N/A B none 5 2 $500 C A 3 2 $1000 D A, B 4 2 $2000 E C, D 5 2 $1250 F D 6 2 $1000 *Shortest possible time for the task 1. Draw the project network and list...
I ONLY need help on letters G and I. According to the answers I've tried for these, it is NOT Activity G for the letter G and not $2,120 for letter I. M5_A5. A computer installation project is being reviewed. Assume the project has to be completed in 16 weeks. Crash the project as necessary (crashing one week at a time). The relevant information is in the table below. CRASH STANDARD STANDARD CRASH IMMEDIATE ACTIVITY TIME TIME COST PREDECESSORS COST...
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 3 B A 9 C A 5 D C 2 E B D 7 F D 6 G E F 4 b. What is the critical path? A-B-D-F-G A-B-E-G A-C-D-F-G A-C-D-E-G c. How many weeks will it take to complete the project? Number of weeks d. How much slack does activity B have? Slack of activity B week(s)