Question

Calculate the fully loaded cost of labor for your project team members. (20 points) Write only the total fully loaded labor c

0 0
Add a comment Improve this question Transcribed image text
Answer #1

calculate the fully loaded cost Of labor (FORMULA= hours needed* rate per hour* overhead rate)

project team member name hours needed rate per hour overhead rate total cost

tommy A=10 20 1.70

C=10 20 1.70

E= 10 20 1.70

TOTAL COST 1020

KELLIE A=5 15 1.35

B= 10 15 1.35   

TOTAL COST 303.75

DREW B=10 15 1.70

D=10 15 1.70

F= 20 15 1.70

TOTAL COST 1020

BLAKE C=10 25 1.50

E=10 25 1.50

F=5 25 1.50

TOTAL COST 937.5

JESSE E=5 25 1.70

F=5 25 1.70

TOTAL COST 425

ARTHURD D=10 20 1.35 270

COST OF EACH ACTIVITY PER WEEK

task week1 week2 week3 week 4 week 5 week 6

A 10*20*1.70   

5*15*1.35

B 10*15*1.35

10*15*1.70

C 10*20*1.70

10*25*1.50

D 10*15*1.35

10*20*1.35

E 10*20*1.70

10*25*1.50

5*25*1.70

F 20*15*1.70

5*25*1.50

5*25*1.70

planned budget 441.25 457.50 715 472.5 927.5 910

cummulative 3923.75

budget

Add a comment
Know the answer?
Add Answer to:
Calculate the fully loaded cost of labor for your project team members. (20 points) Write only th...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The client of a project has requested the project team to crash 8 hours of time....

    The client of a project has requested the project team to crash 8 hours of time. The table below provides the necessary information about the possible project crashing. (a) What is the crash cost for 8 hours of time-savings? (b) Assume the team calls the client and asks for a project extension, reducing the amount of time they need to crash. The project team has a $20 crash budget. Is the budget sufficient to crash 4 hours of time? Activity...

  • The client of a project has requested the project team to crash 8 hours of time....

    The client of a project has requested the project team to crash 8 hours of time. The table below provides the necessary information about the possible project crashing. (a) What is the crash cost for 8 hours of time-savings? (b) Assume the team calls the client and asks for a project extension, reducing the amount of time they need to crash. The project team has a $20 crash budget. Is the budget sufficient to crash 4 hours of time? Activity...

  • 3. The client of a project has requested the project team to crash 8 hours of...

    3. The client of a project has requested the project team to crash 8 hours of time. The table below provides the necessary information about the possible project crashing. (a) What is the crash cost for 8 hours of time-savings? (b) Assume the team calls the client and asks for a project extension, reducing the amount of time they need to crash. The project team has a $20 crash budget. Is the budget sufficient to crash 4 hours of time?...

  • 3. The client of a project has requested the project team to crash 8 hours of...

    3. The client of a project has requested the project team to crash 8 hours of time. The table below provides the necessary information about the possible project crashing. (a) What is the crash cost for 8 hours of time-savings? (b) Assume the team calls the client and asks for a project extension, reducing the amount of time they need to crash. The project team has a $20 crash budget. Is the budget sufficient to crash 4 hours of time?...

  • QUESTION 1 3.8 points Save Ans The cost management plan has all of the following characteristics EXCEPT It may specify variance thresholds for monitoring cost performance to indicate an...

    QUESTION 1 3.8 points Save Ans The cost management plan has all of the following characteristics EXCEPT It may specify variance thresholds for monitoring cost performance to indicate an agreed-upon amount of variation to be allowed before some action needs to be taken. It describes how the project costs will be planned, structured, and controlled. It is based on project cost estimates and is separate from the project management plan. It may specify the level of precision, which is the...

  • In the Week 1 Lesson Video, you were introduced to the team at Getta Byte Software. Your assignment this week is to discuss the billing project charter and submit a one- to two-page paper. Consider wh...

    In the Week 1 Lesson Video, you were introduced to the team at Getta Byte Software. Your assignment this week is to discuss the billing project charter and submit a one- to two-page paper. Consider what additional risks, assumptions, or requirements Getta Byte should include in this charter. Getta Byte Software—The Project Scope We need a new billing system. Why? The one we have works fine. It's manual, time-consuming, and inaccurate. There is that... So, it has to be automated,...

  • Gigabyte, Inc. manufactures three products for the computer industry: Gismos (product G): annual sales, 8,000 units...

    Gigabyte, Inc. manufactures three products for the computer industry: Gismos (product G): annual sales, 8,000 units Thingamajigs (product T): annual sales, 15,000 units Whatchamacallits (product W): annual sales, 4,000 units The company uses a traditional, volume-based product-costing system with manufacturing overhead applied on the basis of direct- labor dollars. The product costs have been computed as follows: Raw material Direct labor Manufacturing overhead* Total product cost Product G $ 35.00 16.00 (.8 hr. at $20) 140.00 $191.00 Product T $...

  • Problem 20-4A Manufacturing: Preparation of a complete master budget LO P1, P2, P3 The management of Zigby M...

    Problem 20-4A Manufacturing: Preparation of a complete master budget LO P1, P2, P3 The management of Zigby Manufacturing prepared the following estimated balance sheet for March 2017: 00 points Skipped eBook Print ZIGBY MANUFACTURING Estimated Balance Sheet March 31, 2017 Assets Cash 43,000 Accounts receivable 432,900 Raw materials inventory 86, 198 Finished goods inventory 387,168 Total current assets 949, 266 Equipment, gross 606,000 Accumulated depreciation (153,000) Equipment, net 453,000 Total assets $1,402,266 Liabilities and Equity Accounts payable $ 194,798 Short-term...

  • The highlighted sections are the ones i need figured out MGMT 640 GROUP PROJECT to your...

    The highlighted sections are the ones i need figured out MGMT 640 GROUP PROJECT to your team has been hired to provide financial analysis for a start-up company, Bobble in Style, n produces customized bobble heads. The bobble heads are made out of less rigid materials and are more true to life more true to life than those of competitors. The company inventors, Mr. and Mrs. Lee, are going to pitch trieir idea to Shark Tank in a few months,...

  • High-End Lifts uses a volume-based, plant-wide approach to allocating overhead. They use direct-labor hours as the...

    High-End Lifts uses a volume-based, plant-wide approach to allocating overhead. They use direct-labor hours as the cost driver for determining the budgeted rate. You will need to derive the predetermined overhead rate for them. First few images are information for the actual problems. Please help!! Challenge 2: Job-Order Costing for Customized Work Based on your advice, High-End Lifts has moved forward and set up the production process to build all of its residential elevators in- house. In the past, High-End...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT