Question

The client of a project has requested the project team to crash 8 hours of time....

The client of a project has requested the project team to crash 8 hours of time. The table below provides the necessary information about the possible project crashing.
(a) What is the crash cost for 8 hours of time-savings?
(b) Assume the team calls the client and asks for a project extension, reducing the amount of time they need to crash. The project team has a $20 crash budget. Is the budget sufficient to crash 4 hours of time?
Activity
Normal
Duration (hours)
Normal
Cost ($)
Crash
Duration (hours)
Crash
Cost (S)
Immediate
Predecessors
A
2
10
2
0
None
B
3
15
2
23
A
C
5
25
4
30
B
D
3
20
1
24
C
E
6
30
4
45
C
F
1
5
1
0
E
G
7
35
6
50
F
H
10
50
7
80
D, G
0 0
Add a comment Improve this question Transcribed image text
Answer #1
Activity

Normal

Normal

Crash

Crash

Immediate

Duration (hours)

Cost ($)

Duration (hours)

Cost (S)

Predecessors

A

2

10

2

0

None

B

3

15

2

23

A

C

5

25

4

30

B

D

3

20

1

24

C

E

6

30

4

45

C

F

1

5

1

0

E

G

7

35

6

50

F

H

10

50

7

80

D, G

(a)

Initial codition (normal time estimates) D 3 A B с H 2 x 3 5 10 目一母母 Duration Project paths A-B-C-D-H A-B-C-E-F-G-H 23 34 Pro

Activity

Normal

Normal

Crash

Crash

Slope

Duration (hours)

Cost ($)

Duration (hours)

Cost ($)

$ / hr

A

2

10

2

0

-

B

3

15

2

23

8

C

5

25

4

30

5

D

3

20

1

24

2

E

6

30

4

45

7.5

F

1

5

1

0

-

G

7

35

6

50

15

H

10

50

7

80

10

Step-1: Crash 'C' by 1 hour. Total cost = $5

D 3 A H B 3 C 4X 2 x 10 E 6 G 7 Project paths |A-B-CD-H | A-B-C-E-F-G-H Duration 22 33 Project duration 33

Step-2: Crash 'E' by 2 hours. Total cost = 2 * $7.5 = $15

D 3 A B C H 2 x 3 4 x 10 E F G 中由电 = 4JX 1 X 7 Project paths | A-B-C-D-H | A-B-CE-F-G-H Duration 22 31 Project duration 31

Step-3: Crash 'B' by 1 hour. Total cost = $8

D 3 A H 一回一回 2|X 2 |x AIR 10 E F G 4TX 1 x Duration Project paths | A-B-C-D-H A-B-C-E-F-G-H 21 30 Project duration 30

Step-4: Crash 'H' by 2 hours. Total cost = 2 * $10 = $20

D 3 A H B 2 x 21X 4 x 8 E F G 4 x 11 7 Duration Project paths |A-B-C-D-H | A-B-C-E-F-G-H 19 28 Project duration 28

Note that the target of 8 hours reduction is achieved now (from 34 hrs initially to 28 hrs now). The total minimum cost of crashing = 5+15+8+20 = $48

(b)

A 4-hour reduction means the end of step-3 where the duration became 30 hours.

At this point, the total cost was 5+15+8 = $28. So, with only $20 in hand, it is not possible to achieve this target.

Add a comment
Know the answer?
Add Answer to:
The client of a project has requested the project team to crash 8 hours of time....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The client of a project has requested the project team to crash 8 hours of time....

    The client of a project has requested the project team to crash 8 hours of time. The table below provides the necessary information about the possible project crashing. (a) What is the crash cost for 8 hours of time-savings? (b) Assume the team calls the client and asks for a project extension, reducing the amount of time they need to crash. The project team has a $20 crash budget. Is the budget sufficient to crash 4 hours of time? Activity...

  • 3. The client of a project has requested the project team to crash 8 hours of...

    3. The client of a project has requested the project team to crash 8 hours of time. The table below provides the necessary information about the possible project crashing. (a) What is the crash cost for 8 hours of time-savings? (b) Assume the team calls the client and asks for a project extension, reducing the amount of time they need to crash. The project team has a $20 crash budget. Is the budget sufficient to crash 4 hours of time?...

  • 3. The client of a project has requested the project team to crash 8 hours of...

    3. The client of a project has requested the project team to crash 8 hours of time. The table below provides the necessary information about the possible project crashing. (a) What is the crash cost for 8 hours of time-savings? (b) Assume the team calls the client and asks for a project extension, reducing the amount of time they need to crash. The project team has a $20 crash budget. Is the budget sufficient to crash 4 hours of time?...

  • Pirmin's Bike Shop is behind on a custom bike and needs to crash 8 hours of time from the 8-step project. Given the...

    Pirmin's Bike Shop is behind on a custom bike and needs to crash 8 hours of time from the 8-step project. Given the project table below calculate the crash cost for 8 hours of time-savings. Suppose Pirmin calls the customer and asks for a project extension, reducing the amount of time he needs to crash Crash Duration Normal Duration Immediate Crash Cost ($) Normal Cost ($) Activity (hours) (hours) Predecessors 10 0 15 23 3 30 25 4 20 24...

  • Normal Time Crash Time Normal with Activity (weeks) (weeks) Cost Crashing Immediate Predecessor(s) $1,400 A 3...

    Normal Time Crash Time Normal with Activity (weeks) (weeks) Cost Crashing Immediate Predecessor(s) $1,400 A 3 2 $2,050 $2,800 B 2 1 $2,100 1 1 $350 $350 7 $1,400 $1,700 A 6 3 $900 $1,200 $5,000 $2,000 F 2 $4,000 $1,500 C 4 G 2 D, E weeks a) Based on the given information regarding the activities for the project, the project completion date b) To reduce the duration of the project to 10 weeks at the least cost, the...

  • TYPE: A CRAMOCerat Managmenti Sume 20t9 2 JCh. 3. Project Management] Jacksonville Bike Shop is behind...

    TYPE: A CRAMOCerat Managmenti Sume 20t9 2 JCh. 3. Project Management] Jacksonville Bike Shop is behind on a custom bike and needs to crash 1 day of time from the 6-step project. Given the project table below answer the following questions. Suppose this shop calls the customer and asks for a project extension, reducing the amount of time she/he nceds to crash. [Note: The project can be speeded up (or "crashed") by spending For example, activity A currently takes 10...

  • Development of Version 2.0 of a particular accounting software product is being considered by Jose Noquera's...

    Development of Version 2.0 of a particular accounting software product is being considered by Jose Noquera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table: To Cost Normal Time (weeks) Crash Time Normal with Activity (weeks) Cost Crashing Immediate Predecessor(s) $2.700 A $2,000 7 $2,300 S3,100 3 $500 $500 S2,300 $2,580 A E 5900 $1.275 F F $3.400 2 S4,800 C G $1,500 $2.100 D, E a) Based on...

  • Lecture Exercise #13 Project Crashing Time (weeks) Cost Activity Predecessori s) Normal Crash Normal Crash A...

    Lecture Exercise #13 Project Crashing Time (weeks) Cost Activity Predecessori s) Normal Crash Normal Crash A None 3 2 1000 1600 B None 2 1 2000 2700 C None 1 1 300 300 D A 7 3 1300 1600 E B 6 3 850 1000 F с 2 1 4000 5000 D, E 2000 G 4 2 1500 What's the normal project completion time? Identify the critical path If you'd like to shorten the project by one week, which activity...

  • Given below is the crashing data for a project along with other data. The project completion...

    Given below is the crashing data for a project along with other data. The project completion time is 20 davs. Determine: (a) the crash slope (i.e crash cost/day) for all activities, (b) the normal total project cost, (c) prioritized the list of activities for crashing from best to worst, (d) the best activity to crash if the project has to be completed in 19 days and alternative critical paths, if any, (e) the earliest time the project can be completed,...

  • 2. A student has developed a project and is interested in accelerating the schedule. Below network diagram (Activity on...

    2. A student has developed a project and is interested in accelerating the schedule. Below network diagram (Activity on Arrow) and table show all information needed. Partial crashing is available. Show your work for crashing. Accelerated Duration Cost Present Duration Cost $100 4 $50 5 $250 2 $200 3 a h 3 $100 $350 C d 3 $100 cannot accelerate 6 $100 $150 e f 7 $300 5 $600 a) Without any crashing (acceleration), how long is the project expected...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT