Question

3. The client of a project has requested the project team to crash 8 hours of time. The table below provides the necessary in

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Network Diagram:

3 jo ng 2 5 3 A B C STAA it 79

Possible Paths:

Start-A-B-C-D-H-End = 23 hours

Start-A-B-C-E-F-G-H-End = 34 hours ......... Critical Path (longest duration path

Start-A-B-C-F-G-H-End = 28 hours

For reducing the project duration, the least incremental crash cost activities on Critical Path should be crashed.

Incremental Crash Cost = (Crash Cost - Normal Cost) / (Normal Duration - Crash Duration)

Activity Normal Time Crash Time Normal Cost Crash Cost Incremental Crash Cost
A 2 2 10 0 NA
B 3 2 15 23 8
C 5 4 25 30 5
D 3 1 20 24 2
E 6 4 30 45 7.5
F 1 1 5 0 NA
G 7 6 35 50 15
H 10 7 50 62 4

Crashing Schedule to reduce the project duration by 8 hours i.e 34 - 8 = 26 hours

Crashed Activity No Crashing H C E B G
No. of days Crashed 0 3 1 2 1 1
Crashing Cost 0 12 5 15 8 15
Total Crashing Cost 0 12 17 32 40 55
Critical Path A-B-C-E-F-G-H A-B-C-E-F-G-H A-B-C-E-F-G-H A-B-C-E-F-G-H A-B-C-E-F-G-H A-B-C-E-F-G-H
TPT 34 31 30 28 27 26

a) From the above table, crash cost for 8 hours of time-saving is $55

b) From the above table, 20$ budget is sufficient to crash 4 hours of time, as it will only require $17

PLEASE HELP ME BY LIKING THIS ANSWER. THANK YOU VERY MUCH FOR THE LIKE!

Add a comment
Know the answer?
Add Answer to:
3. The client of a project has requested the project team to crash 8 hours of...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 3. The client of a project has requested the project team to crash 8 hours of...

    3. The client of a project has requested the project team to crash 8 hours of time. The table below provides the necessary information about the possible project crashing. (a) What is the crash cost for 8 hours of time-savings? (b) Assume the team calls the client and asks for a project extension, reducing the amount of time they need to crash. The project team has a $20 crash budget. Is the budget sufficient to crash 4 hours of time?...

  • The client of a project has requested the project team to crash 8 hours of time....

    The client of a project has requested the project team to crash 8 hours of time. The table below provides the necessary information about the possible project crashing. (a) What is the crash cost for 8 hours of time-savings? (b) Assume the team calls the client and asks for a project extension, reducing the amount of time they need to crash. The project team has a $20 crash budget. Is the budget sufficient to crash 4 hours of time? Activity...

  • The client of a project has requested the project team to crash 8 hours of time....

    The client of a project has requested the project team to crash 8 hours of time. The table below provides the necessary information about the possible project crashing. (a) What is the crash cost for 8 hours of time-savings? (b) Assume the team calls the client and asks for a project extension, reducing the amount of time they need to crash. The project team has a $20 crash budget. Is the budget sufficient to crash 4 hours of time? Activity...

  • Pirmin's Bike Shop is behind on a custom bike and needs to crash 8 hours of time from the 8-step project. Given the...

    Pirmin's Bike Shop is behind on a custom bike and needs to crash 8 hours of time from the 8-step project. Given the project table below calculate the crash cost for 8 hours of time-savings. Suppose Pirmin calls the customer and asks for a project extension, reducing the amount of time he needs to crash Crash Duration Normal Duration Immediate Crash Cost ($) Normal Cost ($) Activity (hours) (hours) Predecessors 10 0 15 23 3 30 25 4 20 24...

  • Normal Time Crash Time Normal with Activity (weeks) (weeks) Cost Crashing Immediate Predecessor(s) $1,400 A 3...

    Normal Time Crash Time Normal with Activity (weeks) (weeks) Cost Crashing Immediate Predecessor(s) $1,400 A 3 2 $2,050 $2,800 B 2 1 $2,100 1 1 $350 $350 7 $1,400 $1,700 A 6 3 $900 $1,200 $5,000 $2,000 F 2 $4,000 $1,500 C 4 G 2 D, E weeks a) Based on the given information regarding the activities for the project, the project completion date b) To reduce the duration of the project to 10 weeks at the least cost, the...

  • TYPE: A CRAMOCerat Managmenti Sume 20t9 2 JCh. 3. Project Management] Jacksonville Bike Shop is behind...

    TYPE: A CRAMOCerat Managmenti Sume 20t9 2 JCh. 3. Project Management] Jacksonville Bike Shop is behind on a custom bike and needs to crash 1 day of time from the 6-step project. Given the project table below answer the following questions. Suppose this shop calls the customer and asks for a project extension, reducing the amount of time she/he nceds to crash. [Note: The project can be speeded up (or "crashed") by spending For example, activity A currently takes 10...

  • Lecture Exercise #13 Project Crashing Activity Predecessor(s) Time (weeks) Normal Crash 3 2 A None None...

    Lecture Exercise #13 Project Crashing Activity Predecessor(s) Time (weeks) Normal Crash 3 2 A None None None B Cost Normal Crash 1000 1600 2000 2700 300 300 1300 1600 2 1 С 1 1 D A 7 3 E 6 3 B с 1000 5000 F 2 850 4000 1500 NA G D. E 4 2000 What's the normal project completion time? Identify the critical path If you'd like to shorten the project by one week, which activity should you...

  • 1) Based on the given information regarding the activities for the project, the project length= ___...

    1) Based on the given information regarding the activities for the project, the project length= ___ weeks. 2) The total cost required for completing this project on normal time= $____ 3) For reducing the duration of the project by one week, the activity that should be crashed first is activity ___. 4) The cost of the project based on the first activity selected for crashing will increase by $___. 5) The maximum weeks by which the project can be reduced...

  • Lecture Exercise #13 Project Crashing Time (weeks) Cost Activity Predecessori s) Normal Crash Normal Crash A...

    Lecture Exercise #13 Project Crashing Time (weeks) Cost Activity Predecessori s) Normal Crash Normal Crash A None 3 2 1000 1600 B None 2 1 2000 2700 C None 1 1 300 300 D A 7 3 1300 1600 E B 6 3 850 1000 F с 2 1 4000 5000 D, E 2000 G 4 2 1500 What's the normal project completion time? Identify the critical path If you'd like to shorten the project by one week, which activity...

  • what is the normal cost of this project? what is the cost of the project after...

    what is the normal cost of this project? what is the cost of the project after 2 days shortening? what is the crashing cost per day for avtivity G? Given the following data and network, find answer the questions 18-20 if you're asked to finish this project 2 days earlier than its normal duration. Indirect cost (overhead) is $200 per day. 9.12 E 1.8 اليا 12.19 10.13 B 7 H 7 1.8 13, 20 0.1 1.7 8.15 20,25 15, 20...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT