Question

3. The client of a project has requested the project team to crash 8 hours of time. The table below provides the necessary in
0 0
Add a comment Improve this question Transcribed image text
Answer #1
Activity Normal Duration Normal cost Crash duration Crash cost Slope
(Crash cost- Normal cost)/(Normal time- crash time)
A 2 10 2 0                                                                       -  
B 3 15 2 23                                                                   8.00
C 5 25 4 30                                                                   5.00
D 3 20 1 24                                                                   2.00
E 6 30 4 45                                                                   7.50
F 1 5 1 0 -
G 7 35 6 50                                                                15.00
H 10 50 7 80                                                                10.00

H А B с D E F

Path path length
ABCDH 23
ABCEFGH 34

ABCEFGH IS THE longest path and the critical chain

(a)The critical activities have to be crashed in order of increasing slope

To save 8 days, we have to crash C, E,B, H,G by 1, 2,1,3,1 days respectively

Accordingly, the crash cost is

Slope X Days crashed = 1* 5 + 2* 7.5 + 1*8 + 3*10 + 1*15 = 73

Hence $73 is the crashing cost

(b) No, $20 is not enough to crash by 4 days.

Minimum amount required to crash by 4 days is by crashing B,C,E and the amount is 1*8+ 1*5 + 2*7.5 = $28

Add a comment
Know the answer?
Add Answer to:
3. The client of a project has requested the project team to crash 8 hours of...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 3. The client of a project has requested the project team to crash 8 hours of...

    3. The client of a project has requested the project team to crash 8 hours of time. The table below provides the necessary information about the possible project crashing. (a) What is the crash cost for 8 hours of time-savings? (b) Assume the team calls the client and asks for a project extension, reducing the amount of time they need to crash. The project team has a $20 crash budget. Is the budget sufficient to crash 4 hours of time?...

  • The client of a project has requested the project team to crash 8 hours of time....

    The client of a project has requested the project team to crash 8 hours of time. The table below provides the necessary information about the possible project crashing. (a) What is the crash cost for 8 hours of time-savings? (b) Assume the team calls the client and asks for a project extension, reducing the amount of time they need to crash. The project team has a $20 crash budget. Is the budget sufficient to crash 4 hours of time? Activity...

  • The client of a project has requested the project team to crash 8 hours of time....

    The client of a project has requested the project team to crash 8 hours of time. The table below provides the necessary information about the possible project crashing. (a) What is the crash cost for 8 hours of time-savings? (b) Assume the team calls the client and asks for a project extension, reducing the amount of time they need to crash. The project team has a $20 crash budget. Is the budget sufficient to crash 4 hours of time? Activity...

  • Pirmin's Bike Shop is behind on a custom bike and needs to crash 8 hours of time from the 8-step project. Given the...

    Pirmin's Bike Shop is behind on a custom bike and needs to crash 8 hours of time from the 8-step project. Given the project table below calculate the crash cost for 8 hours of time-savings. Suppose Pirmin calls the customer and asks for a project extension, reducing the amount of time he needs to crash Crash Duration Normal Duration Immediate Crash Cost ($) Normal Cost ($) Activity (hours) (hours) Predecessors 10 0 15 23 3 30 25 4 20 24...

  • Normal Time Crash Time Normal with Activity (weeks) (weeks) Cost Crashing Immediate Predecessor(s) $1,400 A 3...

    Normal Time Crash Time Normal with Activity (weeks) (weeks) Cost Crashing Immediate Predecessor(s) $1,400 A 3 2 $2,050 $2,800 B 2 1 $2,100 1 1 $350 $350 7 $1,400 $1,700 A 6 3 $900 $1,200 $5,000 $2,000 F 2 $4,000 $1,500 C 4 G 2 D, E weeks a) Based on the given information regarding the activities for the project, the project completion date b) To reduce the duration of the project to 10 weeks at the least cost, the...

  • Lecture Exercise #13 Project Crashing Activity Predecessor(s) Time (weeks) Normal Crash 3 2 A None None...

    Lecture Exercise #13 Project Crashing Activity Predecessor(s) Time (weeks) Normal Crash 3 2 A None None None B Cost Normal Crash 1000 1600 2000 2700 300 300 1300 1600 2 1 С 1 1 D A 7 3 E 6 3 B с 1000 5000 F 2 850 4000 1500 NA G D. E 4 2000 What's the normal project completion time? Identify the critical path If you'd like to shorten the project by one week, which activity should you...

  • TYPE: A CRAMOCerat Managmenti Sume 20t9 2 JCh. 3. Project Management] Jacksonville Bike Shop is behind...

    TYPE: A CRAMOCerat Managmenti Sume 20t9 2 JCh. 3. Project Management] Jacksonville Bike Shop is behind on a custom bike and needs to crash 1 day of time from the 6-step project. Given the project table below answer the following questions. Suppose this shop calls the customer and asks for a project extension, reducing the amount of time she/he nceds to crash. [Note: The project can be speeded up (or "crashed") by spending For example, activity A currently takes 10...

  • Lecture Exercise #13 Project Crashing Time (weeks) Cost Activity Predecessori s) Normal Crash Normal Crash A...

    Lecture Exercise #13 Project Crashing Time (weeks) Cost Activity Predecessori s) Normal Crash Normal Crash A None 3 2 1000 1600 B None 2 1 2000 2700 C None 1 1 300 300 D A 7 3 1300 1600 E B 6 3 850 1000 F с 2 1 4000 5000 D, E 2000 G 4 2 1500 What's the normal project completion time? Identify the critical path If you'd like to shorten the project by one week, which activity...

  • what is the normal cost of this project? what is the cost of the project after...

    what is the normal cost of this project? what is the cost of the project after 2 days shortening? what is the crashing cost per day for avtivity G? Given the following data and network, find answer the questions 18-20 if you're asked to finish this project 2 days earlier than its normal duration. Indirect cost (overhead) is $200 per day. 9.12 E 1.8 اليا 12.19 10.13 B 7 H 7 1.8 13, 20 0.1 1.7 8.15 20,25 15, 20...

  • 2. A student has developed a project and is interested in accelerating the schedule. Below network diagram (Activity on...

    2. A student has developed a project and is interested in accelerating the schedule. Below network diagram (Activity on Arrow) and table show all information needed. Partial crashing is available. Show your work for crashing. Accelerated Duration Cost Present Duration Cost $100 4 $50 5 $250 2 $200 3 a h 3 $100 $350 C d 3 $100 cannot accelerate 6 $100 $150 e f 7 $300 5 $600 a) Without any crashing (acceleration), how long is the project expected...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT