Question

You are appointed as a site engineer representing a consulting firm to supervise a construction project. The project will sta
0 0
Add a comment Improve this question Transcribed image text
Answer #1

(a) Here in this table work and cost is written down and based on commutative cost and time graph is drawn which is of blue Colour.

Time Work Cost Comulative Cost
01-Jan Piling 100000 100000
01-Feb Sub Structure 3,00,000 4,00,000
15-Feb Beams 3,00,000 7,00,000
15-Apr Slab-Deck 80,000 7,80,000
01-Jul Earthwork 50,000 8,30,000
01-Sep Road Work 1,00,000 9,30,000

(b)Here in the given data weightage of each work is given. to match this graph to financial graph , we multiply this weightage to 1,00,000 . And than commutative progress of work is calculated. Based on this Comulative progress of work and Tim graph is located which is of orange colour.

Time Work Weightage Physical work done Comulative
01-Jan Piling 0.1 100000 100000
01-Feb Sub Structure 0.25 250000 350000
15-Feb Beams 0.2 200000 550000
15-Apr Slab-Deck 0.15 150000 700000
01-Jul Earthwork 0.1 100000 800000
01-Sep Road Work 0.2 200000 1000000

Blue Colour - Financial S curve

Orange Colour - Physical Progress S curve.

S Curve 26-Sep 07-Aug 18-Jun 29-Apr 10-Mar 20-Jan 01-Dec 0 200000 400000 600000 800000 1000000 1200000

(C) As per given data:

At the end of June work complete by (30th June) is 60%

And Actual total cost up to this time is RM 7,00,000.

While from the graph and given data we can observe that from the 1st July earth work will start and before earthwork 70% work is completed. While here on the 30th June only 60% work is completed thus our work is behind the schedule.

15th April to 1st July work of slab deck is running whose weightage is 15% and cost is 80,000.

but we have completed only 60% work that means we have done only 5% work of slab deck.

thus cost of slab deck = (0.5*80,0000)/0.15 = 26,667 RM

so total cost up to end of the June = cumulative up to 15th April +26,667 = 7,00,000+26,667 = 7,26,667 RM.

7,26,667 RM is estimated cost of work up to 30th June. But our actual cost is 7,00,000 Rm

thus Project is UnderRun.

Toatl cost of project is commulative cost of each and every work =  9,30,000 RM.

Add a comment
Know the answer?
Add Answer to:
You are appointed as a site engineer representing a consulting firm to supervise a construction project....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT