Consider the proposal. Should SCF accept or reject ACL’s request? If you were the project manager, which option would you select? What risks are involved with your choice and with ACL’s request?
Shell Case Fabricators
BACKGROUND
Shell Case Fabricators (SCF) designs and builds shell casings that enclose
electronic products such as calculators, cell phones, modems. Typically the cases
are plastic or plastic compounds. SCF has six different production lines that cover
different types of product. For example, the largest high volume production line
for modems can produce three different colors and two models (vertical and flat).
Air Connection Links (ACL) is the biggest customer that buys product from this
line. This high output line now runs at full capacity on an eight-hour shift. The
other five lines run smaller quantities and tend to meet the needs of other specialty
products manufactured by different smaller firms.
Ninety-five percent of SCF’s product casings line is designed by the original
hardware manufacturer. Getting a casing to the production stage requires a great
deal of collaboration and interaction between the original hardware and case design
manufacturer (e.g., ACL) and SCF’s shell design engineers and production
department. The latest new product of ACL is a modem designed to be used for
monitoring water activity in bays, e.g., ship traffic, pollution, floating debris. Because
of the product’s high functionality and low cost, potential demand for the
new product is out of sight. It seems every country with small bays used for shipping
wants enough underwater modems to cover their respective bays.
THE UNDERWATER MODEM PROJECT
At SCF each new product is assigned a project manager to coordinate and manage
the shell design, budgets, and manufacturing startup. Songsee is SCF’s star project
manager and is the project manager of the shell for the new short-range,
underwater acoustical modem. The shell casing for the underwater modem
required special design, materials, custom equipment, and a seal to withstand
pressure to 50 meters. Air Connection Links, the product owner, needs sixty
thousand modems in 91 days (next January 15) for the Estuary Control Institute
meeting in Hong Kong.
CLIENT CHANGE REQUEST
Songsee has felt the project was moving along smoothly, with the exception of
being two weeks behind schedule. She feels she can “lean on” the design department
to put the project on top priority and make up the two weeks. Yesterday,
ACL’s project manager, Sabin, came in with a “simple change.” Change the outer
shell shape from rectangular to dome shape; it will improve performance 2 percent.
Songsee couldn’t believe Sabin. He knows better. He knows the engineering
implications, and it is NOT simple! Yet Sabin tells Songsee, “It shouldn’t cost
much.” Songsee imagined a sharp retort, but she counted to five and aborted. At
this late stage of the game, changes and schedule compression cost big money!
Songsee said she would get together with her team and start on a new time and
cost estimate today. She told Sabin he would have to give her a written change request
of the new requirements by tomorrow. Sabin appeared disappointed. “Why
don’t we just add €100,000 to the price and get on with it? We have been doing
business with SCF for six years. With expected demand out of sight, SCF will
break even quickly and have a great profit on the production side.” Songsee
sighed. “Let’s proceed with the change order process. I will bring your request to
the change order governance committee.”
Songsee’s meeting with her team about the change went about as expected.
Every department moaned about changing at this late date. The guesstimate cost
and time estimates were over triple Sabin’s idea of €100,000. For example,
designing a new seal for a dome style modem will require a new custom water
sealing approach, possibly an untested different sealant, and new molds. Has ACL
frozen the design of the new style modem? Songsee asked the team to come in
with a more detailed estimate by tomorrow afternoon, before her meeting with the
change order governance committee.
THE NEXT DAY (FRIDAY)
Sabin called from ACL at midmorning the next day. “Our senior management is
upset that we have to be so formal for such a small change. They just want to get
on with the project and meet the time to market launch date. €100,000 seems
like a fair price. They believe you need to talk to your management. They want a
response by Monday.”
The team estimates came close to yesterday’s guesstimate (€391,000). Not good
news. Songsee knew the answer of the change committee would be to hold for the
full amount. She was right. The change committee believed the costs are there and
need to be covered to meet the launch date. The committee was also concerned
that priorities and resource scheduling would have to change for SCF’s design and
production departments. In three hours she would meet with senior management
to decide to accept the client’s request at their price or come up with an alternate
plan. Songsee realized she should have several options for senior management to
consider, along with a recommendation.
The truth of the matter is that both ACL and SCF have a valid case. ACL is a key customer which that SCF would benefit from their business transactions. However, whichever the choice that will be settled upon, it will have some implications for either party. At this time of the project, SCF stands on a higher ground of losing as compared with the customer (ACL). The request for change is coming at a stage when the firm is seeking to complete the units within a specified period. Therefore, it is not viable or realistically possible to make the changes as ACL demanded. This calls for the rejection of the proposal at this time and may only be considered in future. The initial option, therefore, remains as it was earlier planned.
The first risk that SCF is facing is a failure to meet the demand within the limited time that is available for them. It is quite difficult to any firm that is confronted with a crunch of time to change its designs when there is no time left. This approach would lead to a huge loss for the firm. A change of product designs is a factor that needs to be planned and executed beforehand and cannot be rushed through in the last minute as it will create unnecessary pressures on the company’s resources.
Secondly, the firm is faced with the loss that would occur due to possible errors arising as a result of the rush development of designs. This one of the greatest threat the firm must face even when making its decisions. A rush on the decisions to be made is not the best in this case, and thus SCF should consider it to be one of the factors of consideration. Since there is limited time, errors in product design would lead to high percentages of obsolete products.
Finally, the cost of operation will be higher. The firm will have to incur a huge cost in engineering processes. Developing new designs could cost the company so much money, and since the firm has established to be approximately €391,000, then this is a cost that cannot be invested instantly. Making instant purchases is costly too.
Consider the proposal. Should SCF accept or reject ACL’s request? If you were the project manager,...
Project management Zeus Project-A You are Donald Tuck, the project manager in charge of the Zeus project. Zeus was the code name given to the development of a virtual electronic medical reference guide. Zeus would be designed for emergency medical technicians and paramedics who need a quick reference guide to use in emergency situations, even in offline mode. Donald and his project team were developing a project plan aimed at producing 30 working models in time for InterMedCON 2018, the...
You have been selected as the project manager for the Global Treps project. You helped to run a local shark tank like event at your college last year as part of a class project, so you have a general idea of what is involved. The schedule goal is six months, and the budget is $120,000. Your favorite professor, Dr. K., and a few of her associates have agreed to fund the project. Your strengths are your organizational and leadership skills....
(Use the case of “Global Treps”) You have been selected as the project manager for the Global Treps project. You helped to run a local shark tank like event at your college last year as part of a class project, so you have a general idea of what is involved. The schedule goal is six months, and the budget is $120,000. Your favorite professor, Dr. K., and a few of her associates have agreed to fund the project. Your strengths...
Hi, Kindly assist with my project management assignment below using the attached case study Question 1 Update the project charter for the remainder of the project in response to Adams’ memo (lines 241 through 246). Question 2 Prepare a plan for the remainder of the project in response to Adams’ memo (lines 241 through 246). Your answers to the above will be assessed in terms of the level of communication displayed, the insights and inferences drawn, and your ability to...
Please help writing a well structured document using the below Agile Runbook - Our Overall Delivery Process How do we initiate a Project? Any project is a response to a pain point or desire expressed by either customers, internal stakeholders, employees, or regulatory authorities. In short, a project is a time bound and specific goal oriented task-system that is born out of an ask from any stakeholder. Project initiation is laying down a new project by defining its goals, objectives,...
How can we assess whether a project is a success or a failure? This case presents two phases of a large business transformation project involving the implementation of an ERP system with the aim of creating an integrated company. The case illustrates some of the challenges associated with integration. It also presents the obstacles facing companies that undertake projects involving large information technology projects. Bombardier and Its Environment Joseph-Armand Bombardier was 15 years old when he built his first snowmobile...
Who do you think are top 3 stakeholder groups Now that you are familiar with the project, what are some areas that are more likely to change? What are ways to monitor the effectiveness of stakeholder engagement? CASE STUDY VIII. Integration Management About Global Information Store Introduction In the relaunch of the ERP system, now with Ms. Adriana Holmes as the new CPO, the project team reexamined and refreshed the business case. After a detailed analysis, the team agreed to...
QUESTION 1: Why must project manager should have good technical skills but also good management skills? QUESTION 2: **Communication and Communicator are related" This quote from the text suppose that the communication process is lead by the spokeperson. Do you think is it a gift" to be a good communicator or a skill to improve ( use example of your knowledge to answer)? QUESTION 3: Look at the text paragraph yellow highlighted, and do you think that in today's world...
Kyle Ritter, Manager of the Strategic Sourcing Group (SSG) at Velocity Oil & Gas Company, sat at his desk and ran through his briefing points for his meeting later in the day. Kyle was the manager of the first-ever SSG at Velocity. A year ago, he had left a promising career as a purchasing manager with a consumer-packaged goods firm back in the mid-west for a complete change of scenery, geography (Denver), and profession (oil and gas exploration and production,...
Case Study 12: Hong Kong Police’s Project Management B Chuah Background In the 1990’s, Hong Kong Police (HKP) was responsible for the public safety and internal security of Hong Kong. She came under the umbrella of the Security Bureau of the Government of Hong Kong. It had more than 34,000 employees, of these, over 26,000 were disciplinary staff. This was the largest department within the hierarchy of the Government of Hong Kong. The organization structure of HKP was rather complicated....