Zeus Project-A You are Donald Tuck, the project manager in charge of the Zeus project. Zeus was the code name given to the de
21 20 days 20 days 20 days 15 days Lab test prototypes Field test prototypes 22 19,22 23 23 Adjust design Order stock parts 2
Zeus Project-A You are Donald Tuck, the project manager in charge of the Zeus project. Zeus was the code name given to the development of a virtual electronic medical reference guide. Zeus would be designed for emergency medical technicians and paramedics who need a quick reference guide to use in emergency situations, even in offline mode. Donald and his project team were developing a project plan aimed at producing 30 working models in time for InterMedCON 2018, the biggest medical equipment trade show which will be held at the KLCCC Convention Centre on 9 November. Meeting the InterMedCON deadline was critical to success. All the major medical equipment manufacturers demonstrated and took orders of new products at InterMedCON. Donald had also heard rumors that competitors were considering developing a similar product, and he knew that being first to market would have a significant sales advantage. Besides, top management made funding contingent upon developing a workable plan for meeting the InterMedCON deadline. The project team spent the morning working on the schedule for Zeus. They started with the WBS and developed the information for a network, adding activities when needed. Then the team added the time estimates they had collected for each activity. Following is the preliminary information for activities with duration time and predecessors: Predecessor Duration Description Architectural decisions Activity 10 days 1 1 20 days 18 days 15 days 15 days Internal specifications External specifications Feature specifications Voice recognition 1 4 2,3 5 2,3 2,3 4 days Case 6 2 days 2 days 2 days 40 days Screen 7 Speaker output jacks Tape mechanism 2,3 2,3 9 4 Database 10 Microphone/soundcard Pager 5 days 11 4 4 days 12 3 days 4 days 5 days 10 days 4 Barcode reader 13 4 Alarm clock 14 Computer 1/O Review design 4 15 5,6,7,8,9,10,11,12,13,14,15 5,6,7,8,9,10,11,12,13,14,15 16 5 days 15 days 35 days Price components 17 16,17 Integration Document design 18 16 19 20 days 18 Procure prototype components 20 Assemble prototypes 10 days 20 21
21 20 days 20 days 20 days 15 days Lab test prototypes Field test prototypes 22 19,22 23 23 Adjust design Order stock parts 24 24 25 24 2 days Order custom parts 26 25, FS 8 days 26, FS 13 days 10 days Assemble first production unit 27 27 10 days 15 days 10 days Test unit 28 28 Produce 30 units 29 Train sales representatives 30 Use Microsoft Project to develop the schedule of activities (see Case Appendix for further instructions) - noting late and early times, the critical path, and estimated completion for the project. Prepare a short memo to the Vice President, Dr Sergei White, which addresses the following questions: 1. What is the project duration? 2. When will the project finished? 3. What activities lie on the critical path? 29
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Solution )Consider the fotlowing given data 1otal duration of project : total time taken to Complete the Crih cal path days D

Add a comment
Know the answer?
Add Answer to:
Project management Zeus Project-A You are Donald Tuck, the project manager in charge of the Zeus...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • You work for a company that makes cell phones and have been made the project manager...

    You work for a company that makes cell phones and have been made the project manager for the design of a new cell phone. Your supervisors have already scoped the project, so you have a list showing the work breakdown structure, and this includes major project activities. You must plan the project schedule and calculate project duration. Your boss wants the schedule on his desk tomorrow morning! You have been given the information in Table-1 below. It includes all the...

  • Analytics Exercise 4-2 You work for Microsoft in their global cell phone group. You have been made project manager for the design of a new cell phone. Your supervisors have already scoped the project...

    Analytics Exercise 4-2 You work for Microsoft in their global cell phone group. You have been made project manager for the design of a new cell phone. Your supervisors have already scoped the project so you have a list showing the work breakdown structure and this includes major project activities. You must plan the project schedule and calculate project duration. Your boss wants the schedule on his desk tomorrow morning! You have been given the information in Exhibit 5.13. It...

  • 2. Using the information in Table 1, assuming that the project team will work a standard...

    2. Using the information in Table 1, assuming that the project team will work a standard working week (5 working days in 1 week) and that all tasks will start as soon as possible: Table 1: Project description Task Description Predecessor/s Duration (working days) 5 15 25 15 A B A B с D E F G H Requirement Analysis Systems Design Programming Telecoms Hardware Installation Integration System Testing Training/Support Handover and Go-Live B B 30 CD E, F 10...

  • 4. Design and plot a critical ratio for a computer installation project that had planned constant,...

    4. Design and plot a critical ratio for a computer installation project that had planned constant, linear progress from 0 to an earned value of 200 over a 100-day duration. In fact, progress for the first 20 days has been: 2, 3, 4, 6,7, 9, 12, 14, 15, 17, 20. 21, 21, 22, 24, 26, 27, 29, 31,33. What can you conclude about this project?

  • Your Assignment is to Create a Project Schedule in MS Project. You are to Create a...

    Your Assignment is to Create a Project Schedule in MS Project. You are to Create a Project Schedule using the durations, including Predecessors and Names on each activity Amir’s Sheds is a successful franchise in the home building industry. Amir’s Sheds build specific purpose sheds for home gardens, farms and industrial storage facilities. The project starts on Monday, June 3, 2019 WBS for Building a Shed Task ID Task Description Predecessor Time Resources (people and materials required to complete the...

  • QUESTION 1 Your company is planning to implement a construction project in a nearby town. You...

    QUESTION 1 Your company is planning to implement a construction project in a nearby town. You have identified ten (10) activities and their relationship to be carried out in order to complete the project. Table 1 and Figure 1 below show the relationship and the critical path diagram for the project. The duration to complete each activity (days) is stated below the activity. The relationship between activities is 'finish-start with no lag except for the following activities. Table 1: Relationship...

  • 1 According to the project plan, a contractor is scheduled to deliver some software components today...

    1 According to the project plan, a contractor is scheduled to deliver some software components today afternoon. A regular payment is due to be made to this contractor tomorrow. You and your project team received a note this morning informing you that the software delivery will be delayed by 2 weeks. What should you do right now? a You should delay the payment for two weeks b You must immediately find a different contractor c You should conduct a meeting...

  • A senior manager has finished reviewing the latest draft of an upcoming project. the following table...

    A senior manager has finished reviewing the latest draft of an upcoming project. the following table provides information about the project including the normal time for each activity, activity sequence and information about costs to shorten some of the activities and therefore the project duration. As he prepares ro review rhe proposal with the owners he is concerned about the project duration and expects the owners will want the project shortened. Activity Precedes Normal Time. (week) Crashing Costs ($000) 1st...

  • 2. Can the project be completed before construction can begin, which is scheduled 40 weeks later?...

    2. Can the project be completed before construction can begin, which is scheduled 40 weeks later? a. Yes, because the project duration time is 39 weeks. b. No, because the project duration time is 41 weeks. c. No, because the project duration time is 42 weeks. d. Yes, because the project duration time is 40 weeks. 3. Which activities can be delayed without delaying the projection completion time? a. B, D and F b. B, D and G c. A,...

  • Gail is the project manager tasked to install a nursing documentation application. She is planning on...

    Gail is the project manager tasked to install a nursing documentation application. She is planning on bringing all of the team members together for an introduction. The other members of the team include: 1) One medical/surgical unit nurse manager who is the head of the team 2) Two nursing unit clerical support staff members 3) The hospital medical records supervisor 4) One case manager 5) A daytime hospitalist, 6) An emergency department nurse 7) The chief hospital cook from the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT