Project management Zeus Project-A You are Donald Tuck, the project manager in charge of the Zeus...
You work for a company that makes cell phones and have been made the project manager for the design of a new cell phone. Your supervisors have already scoped the project, so you have a list showing the work breakdown structure, and this includes major project activities. You must plan the project schedule and calculate project duration. Your boss wants the schedule on his desk tomorrow morning! You have been given the information in Table-1 below. It includes all the...
Analytics Exercise 4-2 You work for Microsoft in their global cell phone group. You have been made project manager for the design of a new cell phone. Your supervisors have already scoped the project so you have a list showing the work breakdown structure and this includes major project activities. You must plan the project schedule and calculate project duration. Your boss wants the schedule on his desk tomorrow morning! You have been given the information in Exhibit 5.13. It...
2. Using the information in Table 1, assuming that the project team will work a standard working week (5 working days in 1 week) and that all tasks will start as soon as possible: Table 1: Project description Task Description Predecessor/s Duration (working days) 5 15 25 15 A B A B с D E F G H Requirement Analysis Systems Design Programming Telecoms Hardware Installation Integration System Testing Training/Support Handover and Go-Live B B 30 CD E, F 10...
4. Design and plot a critical ratio for a computer installation project that had planned constant, linear progress from 0 to an earned value of 200 over a 100-day duration. In fact, progress for the first 20 days has been: 2, 3, 4, 6,7, 9, 12, 14, 15, 17, 20. 21, 21, 22, 24, 26, 27, 29, 31,33. What can you conclude about this project?
Your Assignment is to Create a Project Schedule in MS Project. You are to Create a Project Schedule using the durations, including Predecessors and Names on each activity Amir’s Sheds is a successful franchise in the home building industry. Amir’s Sheds build specific purpose sheds for home gardens, farms and industrial storage facilities. The project starts on Monday, June 3, 2019 WBS for Building a Shed Task ID Task Description Predecessor Time Resources (people and materials required to complete the...
QUESTION 1 Your company is planning to implement a construction project in a nearby town. You have identified ten (10) activities and their relationship to be carried out in order to complete the project. Table 1 and Figure 1 below show the relationship and the critical path diagram for the project. The duration to complete each activity (days) is stated below the activity. The relationship between activities is 'finish-start with no lag except for the following activities. Table 1: Relationship...
1 According to the project plan, a contractor is scheduled to deliver some software components today afternoon. A regular payment is due to be made to this contractor tomorrow. You and your project team received a note this morning informing you that the software delivery will be delayed by 2 weeks. What should you do right now? a You should delay the payment for two weeks b You must immediately find a different contractor c You should conduct a meeting...
A senior manager has finished reviewing the latest draft of an upcoming project. the following table provides information about the project including the normal time for each activity, activity sequence and information about costs to shorten some of the activities and therefore the project duration. As he prepares ro review rhe proposal with the owners he is concerned about the project duration and expects the owners will want the project shortened. Activity Precedes Normal Time. (week) Crashing Costs ($000) 1st...
2. Can the project be completed before construction can begin, which is scheduled 40 weeks later? a. Yes, because the project duration time is 39 weeks. b. No, because the project duration time is 41 weeks. c. No, because the project duration time is 42 weeks. d. Yes, because the project duration time is 40 weeks. 3. Which activities can be delayed without delaying the projection completion time? a. B, D and F b. B, D and G c. A,...
Gail is the project manager tasked to install a nursing documentation application. She is planning on bringing all of the team members together for an introduction. The other members of the team include: 1) One medical/surgical unit nurse manager who is the head of the team 2) Two nursing unit clerical support staff members 3) The hospital medical records supervisor 4) One case manager 5) A daytime hospitalist, 6) An emergency department nurse 7) The chief hospital cook from the...