Question

QUESTION 1 Your company is planning to implement a construction project in a nearby town. You have identified ten (10) activi

0 0
Add a comment Improve this question Transcribed image text
Answer #1

O A 24 0 24 24 24 8 28 sslo 5.34C 38. 46 4 50 9 60 50 24, 9 52 28,52 60, 38 GOLF 88 124 D152 (24/28/52 52 E 60 528160 602888

Go through network diagram, during forward pass: we take maximum value.

& during backward pass: we take minimum value.

The activities which requires full attention are: A,D,E,F,J,K.

Completion time for projection is 122 days.

Any doubts are welcome.

Add a comment
Know the answer?
Add Answer to:
QUESTION 1 Your company is planning to implement a construction project in a nearby town. You...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • A construction company has a project proposal, which takes 10 activities as follows: Activity Predecessors Activity...

    A construction company has a project proposal, which takes 10 activities as follows: Activity Predecessors Activity Duration Time (In DAYS ) Early Start (ES) (In DAYS ) Early Finish (EF) (In DAYS ) Late Start (LS) (In DAYS ) Late Finish (LF) (In DAYS ) SLACK (In DAYS ) A - 14 B - 13 C A 11 D A 15 E B 14 F B 11 G D, E 13 H F 15 J C 12 K G,H 11...

  • Assignment for week 5 Given the following information, draw the project network

    Assignment for week 5Given the following information, draw the project network. Compute the early, late and slack times for the project network. which activities are on the critical path have only the start or finish of the activity on the critical path?ID duration finish to start finish to start additional lag lag predecessor lag Relationship A 2 none 0 none 0B 4 A 0 none 0C 6 A 0 finish-finish C to F 7D 8 A 0 none 0E 18...

  • 1. The activities needed for a new project your company is undertaking are listed in the...

    1. The activities needed for a new project your company is undertaking are listed in the following table. ACTIVITY IMMEDIATE PREDECESSOR(S) A ---- B ---- C A D A, B E B F C, D, E G D, E H F I F, G J G The activity times were determined for the project, and were as below. ACTIVITY ACTIVITY TIME (days) A 11 B 9 C 7 D 12 E 8 F 9 G 10 H 6 I 7...

  • 3. Using the project information below, draw the AON diagram, complete forward and backward pass, and...

    3. Using the project information below, draw the AON diagram, complete forward and backward pass, and identify the critical path. (10 points) Activity Duration Network relationships A-D Finish to Start A C Finish to Start A - B Start to Start - Lag 2 time units D E Start to Start - Lag S time units D-E Finish to Finish - Lag 1 time unit B E Finish to Start C-F Finish to Start - Lag 5 time units E...

  • 1. Sid Orland is involved in planning a scientific research project. The activities are displayed in the following...

    1. Sid Orland is involved in planning a scientific research project. The activities are displayed in the following diagram. Optimistic, most likely, and pessimistic time estimates are displayed in the following table. Figure for Problem 1. r e 14 16 E 4 H 4 7 11 7 11 16 20 G 5 0 33 611 16 11 16 D 3 Most Likely Pessimistic Activity Optimistic 4 4 (a) Determine the expected times and variances for each activity along the critical...

  • Show all Calculations Question 1 (50 points). You were recently assigned to manage a project for...

    Show all Calculations Question 1 (50 points). You were recently assigned to manage a project for your company. You have constructed a network diagram (depicting the various activities in the project, see figure below). In addition, you have asked your team to estimate the amount of time (in days) that they would expect each of the activities to take. Their responses are shown in the table below: Start Finish Table 1 - Estimates Data Time Estimates (Days) Activity OptimisticMost Likely...

  • Activity on arrow construction

    QUESTION 1 The following table provides information about a particular project:ActivityDuration (Days)PrecedingActivityA5_B6_C4AD3AE1AF4EG14D,EH12B,CI2G,H (a)   Represent the project by means of a simple network diagram.        (b)   Prepare in tabular form, an activity schedule showing the following details: Earliest-start, earliest-finish, latest-start, latest-finish and slack times.         (c)   Identify the critical path.                                                               ...

  • Consider the project network information in Table 1 of Case Study A on Page 3 below....

    Consider the project network information in Table 1 of Case Study A on Page 3 below. Assuming the project starts at time zero and all activity connections are finish-to-start, draw an Activity on the Node (AON) network diagram of the project, determine the expected project completion time, state the critical activities and critical path(s). Crash the project by 1 week and state the total crash cost. (b) (18 narl Case Study A Table 1 below contains activities associated with a...

  • Consider the project network information in Table 1 of Case Study A on Page 3 below....

    Consider the project network information in Table 1 of Case Study A on Page 3 below. Assuming the project starts at time zero and all activity connections are finish-to-start, draw an Activity on the Node (AON) network diagram of the project, determine the expected project completion time, state the critical activities and critical path(s). Crash the project by 1 week and state the total crash cost. (b) (18 nar Case Study A Table 1 below contains activities associated with a...

  • Construction methods Do 4-3 5. Answer the following two questions, 5-1 and S-2 5-1) Draw the...

    Construction methods Do 4-3 5. Answer the following two questions, 5-1 and S-2 5-1) Draw the "node" network diagram and perform the CPM calculations based on the end-of-day convention to complete the table entries. (20 points) (Note: use very simple node design for the network diagram: for example, box or circle.) Activity! Duration | Predecessors | EST E-LS 1 LF- B. BFF/2 | 구 | 11 | 15 | 19 E, F SS12 5 13 it is assumed that the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT