Question

Activity on arrow construction

QUESTION 1

 

The following table provides information about a particular project:

Activity

Duration (Days)

Preceding



Activity

A

5

_

B

6

_

C

4

A

D

3

A

E

1

A

F

4

E

G

14

D,E

H

12

B,C

I

2

G,H

 

(a)   Represent the project by means of a simple network diagram.        

(b)   Prepare in tabular form, an activity schedule showing the following details: Earliest-start, earliest-finish, latest-start, latest-finish and slack times.         

(c)   Identify the critical path.                                                                            


0 0
Add a comment Improve this question Transcribed image text
✔ Recommended Answer
Answer #1

Activity

Duration (D)

Earliest Starting Time(E)

Earliest Finish Time (E+D)

Latest Finish Time (L)

Latest Starting Time (L-D)

Slack Time

(L-D)-E

1-2

5

0

5

5

0

0

1-3

6

0

6

10

4

4

2-3

4

5

9

10

6

1

2-4

3

5

8

8

5

0

2-5

1

5

6

20

19

14

3-6

12

9

21

22

10

1

4-6

14

8

22

22

8

0

5-7

4

6

10

24

20

14

6-7

2

22

24

24

22

0

The slack time for 1-2, 2-4, 4-6, 6-7 is zero

So the critical path is 1-2-4-6-7.

> Can i have the activity on arrow diagram please

Izno Mon, Jul 5, 2021 2:09 AM

Add a comment
Know the answer?
Add Answer to:
Activity on arrow construction
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
  • Problem 5: For the given activity network, if there are 35 days required to complete the...

    Problem 5: For the given activity network, if there are 35 days required to complete the project, find the following Complete the network by filling in ES, LS, EF and LF Earliest start for activities D, E, F, H, G, L, M ill. Earliest finish for activities D, E, F, H,G,L,M Latest start for activities D, E, F, H, G, LM V. Latest finish activities D, E, F.H.GLM vi. Slack/Float time for each activities D, E, F, H, G, LM...

  • Activity Duration Precedence Problem# 3 For the project information given below (wecks) information a) Draw the...

    Activity Duration Precedence Problem# 3 For the project information given below (wecks) information a) Draw the network diagram to accurately B must be after C represent the information given C must be after A 10 15 b) Determine the earliest start, earliest D must be after B E must be after C F must be after D and E G must be after F H must be after G 1 must be after F finished, latest start, latest finish for...

  • Provide step by step please thank you, no exce Assume you have a project with ten...

    Provide step by step please thank you, no exce Assume you have a project with ten activities labeled A-J, as shown. Derive the earliest completion time (or early finish-EF), latest completion time (or late finish-LF), and slack for each of the following tasks (begin at time 0) the critical path on your network diagram. . Which tasks are on the critical path? Highligh Preceding Expected Critical Path? Activity Event Duration EF LF Slack A, D C,E D, E F, G...

  • Activity Duration (days) Preceding activity A 3 - B 5 - C 2 B D 1...

    Activity Duration (days) Preceding activity A 3 - B 5 - C 2 B D 1 A E 6 A F 3 D G 3 C,E a. Construct a network diagram showing the critical path. b. Identify the earliest time the campaign can start. c. Identify the activities where there is float/slack time in the project, and calculate how much float/slack time there is. ** You should show all of your workings and state, clearly, any assumptions made.                                              

  • A project manager discovers that his team has neglected tocomplete the network diagram for the...

    A project manager discovers that his team has neglected to complete the network diagram for the project. the network diagram is shown below. however the project manager has some information available, specifically that each activity a-g, has a different duration between one and seven weeks. also the slack time for each of the activity is known as shown belowDuration (weeks): 1,2,3,4,5,6,7 Slack time (weeks): 0,0,0,1,1,3,7 A D E G B FINISH START C F Using the clues provided below, determine...

  • Consider a project having the following six activities:                                  

    Consider a project having the following six activities:                                                      Immediate                                                  Max        Crash cost             Activity                           Predecessors           Time (weeks)             Crash*    per week                   A                                none                                    6                          6                N/A                   B                                none                                    5                          2               $500                   C                                A                                       3                          2             $1000                   D                                A, B                                    4                          2             $2000                   E                                 C, D                                    5                          2             $1250                   F                                D                                       6                          2             $1000                                                                                                 *Shortest possible time for the task 1. Draw the project network and list...

  • also needs daves latest start and latest finish: Dave Fletcher was able to determine the activity...

    also needs daves latest start and latest finish: Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for e activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s) C, E D, F Dave's earliest start (ES) and earliest finish (EF) are: Activity ES...

  • The activities for a breakfast are shown in the table below. Activity Description Duration (in minute)...

    The activities for a breakfast are shown in the table below. Activity Description Duration (in minute) Preceding Activity A Get up 15 - B Make tea 3 D, E C Fill kettle 1 A D Fetch milk 1 A E Boil water 5 C F Milk on cereal 1 D G Make toast 4 H H Cut bread 2 A I Eat 8 B, F, G (a) Use the activity network construction algorithm to number the vertices and to draw...

  • 1. Consider the following project. Activity Duration (weeks)5 Immediate Predecessor(s) Cost (S) 1000 | 400 I 20...

    1. Consider the following project. Activity Duration (weeks)5 Immediate Predecessor(s) Cost (S) 1000 | 400 I 200 | 1200 | 500 | 700 | 1200 | 800 | 1800 | 1500 | 400 (a) Construct the activity-on-node (AoN) network for the relations among the activities in the (b) Using the activity-on-node (Ao) network developed in part (a), determine the critical path and the minimum time required to complete the project. Develop the earliest start and finish times, the latest finish...

  • Please solve the following problems related to Chapter 17: Project Management: 1. Based on the following...

    Please solve the following problems related to Chapter 17: Project Management: 1. Based on the following AOA diagram, please answer the following question: (1) Determine the critical path and the expected project duration (2) Determine the following quantities for each activity: the earliest start time, the latest start time, the earliest finish time and the latest finish time and the slack time. C17) F (5) 1 (61 A(4) D (11) G (3) H(101 B (10) E (12)

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT