Question

Assignment for week 5 Given the following information, draw the project network

Assignment for week 5
Given the following information, draw the project network. Compute the early, late and slack times for the project network. which activities are on the critical path have only the start or finish of the activity on the critical path?
ID duration finish to start finish to start additional lag lag
predecessor lag Relationship
A 2 none 0 none 0
B 4 A 0 none 0
C 6 A 0 finish-finish C to F 7
D 8 A 0 none 0
E 18 B 0 finish-finish E & G 9
C 10
F 2 D 0 none
G 5 F 0 Start-start G to H 10
H 5 None 0 none
I 14 E 0 Finish-finish I to J 5
J 15 G,H 0 none 0
0 0
Add a comment Improve this question Transcribed image text
✔ Recommended Answer
Answer #1
What kind of HELP do you need? You need to be specific when asking questions here.

If all you do is post your entire assignment, with no evidence of thinking on your part, nothing will happen since no one here will do your work for you. But if you are specific about what you don't understand about the assignment or exactly what help you need, someone might be able to assist you.
answered by: Lynda Smith
Add a comment
Know the answer?
Add Answer to:
Assignment for week 5 Given the following information, draw the project network
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT