Question

2. Using the information in Table 1, assuming that the project team will work a standard working week (5 working days in 1 we

0 0
Add a comment Improve this question Transcribed image text
Answer #1

10 15 10 5 CH I B) D 30

ES for first Activity = 0

ES = Maximum (EF of all the predecessors)

EF = ES + Duration

LF for last activity = EF of last activity

LF = Minimum (LS of all the successors)

LS = LF - Duration

Slack = LF - EF = LS - ES

If Slack = 0, Critical.....Else, Not critical

Activity Duration ES EF LS LF Slack Critical
A 5 0 5 0 5 0 Yes
B 15 5 20 5 20 0 Yes
C 25 20 45 20 45 0 Yes
D 15 20 35 30 45 10 No
E 30 20 50 25 55 5 No
F 10 45 55 45 55 0 Yes
G 10 55 65 55 65 0 Yes
H 5 65 70 65 70 0 Yes
I 5 70 75 70 75 0 Yes


(i)

Critical Path of the project --->

A - B - C - F - G - H - I

(ii)

Planned duration = Time taken by the critical path = 5 + 15 + 25 + 10 + 10 + 5 + 5 = 75 days = 75 / 5 = 15 weeks

(iii) Non critical activities with total slack are listeb below:

Non critical activities Total Slack  

D 10

E 5

Add a comment
Know the answer?
Add Answer to:
2. Using the information in Table 1, assuming that the project team will work a standard...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Q1.      (10 marks) Construct an activity on arrow network based on the activity descriptions below. Show...

    Q1.      (10 marks) Construct an activity on arrow network based on the activity descriptions below. Show all your work. Label activities in the network by their activity letters and node numbers. Remove any redundant dependencies and label dummy activities DUMMY1, DUMMY2, etc. • Activities H, R2, T1 start the project. • Activity T2 can start when Activities H, E1 and S are completed. • Activity E1 also depends on Activity R2. • Activity X follows Activity H and precedes Activity...

  • The following information is provided for the tasks on a project. Times are in days. Task...

    The following information is provided for the tasks on a project. Times are in days. Task Time Predecessor A 12 B 21 B, C F 15 G 5 F, G H 17 [Select ] The critical path is [Select ] The time to complete this project will be The slack for task G is Select ] If the duration on task A increases by three days, how long will the project take to complete? I Select ]

  • QUESTION 2 Given the following information, you are to determine the following Project network. Early, late...

    QUESTION 2 Given the following information, you are to determine the following Project network. Early, late and slack activity times. Project duration. Critical path Task Predecessor Duration A None 8 B A 5 C A 10 D A 15 E A 10 F B 12 G C, D 12 H E, 7 I G, H 7 J F,G,I 10 K J 12

  • The following info is available for drawing a PERT network using AOA. *(More than one answer...

    The following info is available for drawing a PERT network using AOA. *(More than one answer may be selected)* Activity Immediate Predecessors Activity Duration (days) A -- 10 B -- 13 C A 12 D B 15 E A 13 F C 16 G D,E 10 H G,F 5 a. the critical path includes: B, D, G, and H. b. the slack on activity G is not 11 days. c. there is one critical path. d. the total duration to...

  • 9. Given the following information in the table, construct an activity on the node diagram. Label the critical path as well as the early and late start/finish times and the slack for each activit...

    9. Given the following information in the table, construct an activity on the node diagram. Label the critical path as well as the early and late start/finish times and the slack for each activity. (20 points) Predecessor Duration (Days) Activity A, B C, D F,G 9. Given the following information in the table, construct an activity on the node diagram. Label the critical path as well as the early and late start/finish times and the slack for each activity. (20...

  • Assignment for week 5 Given the following information, draw the project network

    Assignment for week 5Given the following information, draw the project network. Compute the early, late and slack times for the project network. which activities are on the critical path have only the start or finish of the activity on the critical path?ID duration finish to start finish to start additional lag lag predecessor lag Relationship A 2 none 0 none 0B 4 A 0 none 0C 6 A 0 finish-finish C to F 7D 8 A 0 none 0E 18...

  • I need help Software Project Management question Q1. For the following table of information:        a)...

    I need help Software Project Management question Q1. For the following table of information:        a) Draw a network diagram (Activity on Arrow)        b) List down all the network paths        c) Determine the critical path(s) Activity Predecessor Duration A Start 5 days B A 2 days C A 3 days D B 4 days E C 6 days F C 3 days G D, E 4 days H F 2 days I G 3 days J H 1...

  • Question 2 (50%): The project information is presented in Table 1. It is known that the...

    Question 2 (50%): The project information is presented in Table 1. It is known that the critical path of the given project is A - D + G - J. 1) Please fill out the Table 2. (1% * 10-10%) 2) The duration of the project is days (10%) Note: Calculation processes for 1) and 2) are not required. 3) What is the probability of finishing the project in 18 days? (15%) 4) What is the probability of finishing the...

  • B. Determine the project’s critical path and duration.(this is number b wuestion) please answer t...

    b. Determine the project’s critical path and duration.(this is number b wuestion) please answer this two b and c questions Reliable Garage is completing production of the J2000 kit car. The following data are available for the project Activity Activity Time (days) Immediate Predecessor(s 10 D, E,G A-B-C-D-H 4 4 A-B-C-F-G-H b. Determine the pr A-B-C-E-H The critical path isand the project duration is I duration. day(s). (Enter your response as a whole number.) c. Calculate the slack for each...

  • The table below shows a number of tasks required for the successful completion of a project....

    The table below shows a number of tasks required for the successful completion of a project. Activity Days Immediate Predecessor(s) A 4 B 2 A C 5 A D 7 A E 2 B F 5 B,C G 6 D,E,F Draw the network diagram for this project highlighting Early Start, Early Finish, Late Start and Late Finish and slack. Please show your answer by using the format shown below.                                                                                                                                  Table template: Activity A B C D E F G Early...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT