Question

Q1.      (10 marks) Construct an activity on arrow network based on the activity descriptions below. Show...

Q1.      (10 marks)

Construct an activity on arrow network based on the activity descriptions below. Show all your work. Label activities in the network by their activity letters and node numbers. Remove any redundant dependencies and label dummy activities DUMMY1, DUMMY2, etc.

• Activities H, R2, T1 start the project.

• Activity T2 can start when Activities H, E1 and S are completed.

• Activity E1 also depends on Activity R2.

• Activity X follows Activity H and precedes Activity L.

• Activity E is preceded by Activities T2 and P1.

• The predecessors to Activity G are Activities L, T2 and P1.

• The successors to Activity T1 are Activities E1, S, W and D2.

• Activity P1 cannot begin until Activity W is finished.

• Activity P2 and F follow Activities W and D2, and precede Activities E and R1.

• Activity O2 depends on T2 and P1 , and precedes Activity L.

Q2.      (5 marks)

Compare and contrast the project evaluation and review technique (PERT) with the critical path method (CPM).

Q3. (5 marks)

Using the information in the table below, assuming that the project team will work a standard working week (5 working days in a week) and that all tasks will start as soon as possible:

Task

Description

Duration (Working days)

Predecessor/s

A

Requirement Analysis

5

B

Systems Design

15

A

C

Programming

25

B

D

telecoms

15

B

E

Hardware installation

30

B

F

Integration

10

C, D

G

System Testing

10

E, F

H

Training/Support

5

G

I

Handover and Go-Live

5

H

Determine the critical path of the project.

Calculate the planned duration of the project in weeks

Q4. (10 marks)

Explain in detail Eliyahu Goldratt’s Theory of Constraints with a brief note on its application in Project Management.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Q1. The activity on Arrow (AOA) network diagram as per given precedence relationship is following

Dummy2 Dummy3 02 R2 E1 T2 .Dummy5 Start 2 12 Finish Dummy1 Dummy6 P1 R1 T1 P2 10 Dummy4 Dummy7 D2

Add a comment
Know the answer?
Add Answer to:
Q1.      (10 marks) Construct an activity on arrow network based on the activity descriptions below. Show...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Problem 5: For the given activity network, if there are 35 days required to complete the...

    Problem 5: For the given activity network, if there are 35 days required to complete the project, find the following Complete the network by filling in ES, LS, EF and LF Earliest start for activities D, E, F, H, G, L, M ill. Earliest finish for activities D, E, F, H,G,L,M Latest start for activities D, E, F, H, G, LM V. Latest finish activities D, E, F.H.GLM vi. Slack/Float time for each activities D, E, F, H, G, LM...

  • Activity on arrow construction

    QUESTION 1 The following table provides information about a particular project:ActivityDuration (Days)PrecedingActivityA5_B6_C4AD3AE1AF4EG14D,EH12B,CI2G,H (a)   Represent the project by means of a simple network diagram.        (b)   Prepare in tabular form, an activity schedule showing the following details: Earliest-start, earliest-finish, latest-start, latest-finish and slack times.         (c)   Identify the critical path.                                                               ...

  • 2. Using the information in Table 1, assuming that the project team will work a standard...

    2. Using the information in Table 1, assuming that the project team will work a standard working week (5 working days in 1 week) and that all tasks will start as soon as possible: Table 1: Project description Task Description Predecessor/s Duration (working days) 5 15 25 15 A B A B с D E F G H Requirement Analysis Systems Design Programming Telecoms Hardware Installation Integration System Testing Training/Support Handover and Go-Live B B 30 CD E, F 10...

  • QUESTION 2: (20 marks) 2. Critical Path Method (CPM) is a network diagramming technique used to...

    QUESTION 2: (20 marks) 2. Critical Path Method (CPM) is a network diagramming technique used to predict total project duration and to determine the critical path. a) Based on the table provided, create the CPM network diagram. Analyse and show the Early Start (ES), Early Finish (EF), Late Start (LS), Late Finish (LF) and the Float/Slack duration. (14 marks) b) Analyse the diagram, state and circle the Critical Path clearly. (6 Marks) Activity Predecessor Duration A 6 B A 7...

  • QUESTION 2: (20 marks) 2. Critical Path Method (CPM) is a network diagramming technique used to...

    QUESTION 2: (20 marks) 2. Critical Path Method (CPM) is a network diagramming technique used to predict total project duration and to determine the critical path. a) Based on the table provided, create the CPM network diagram. Analyse and show the Early Start (ES), Early Finish (EF), Late Start (LS), Late Finish (LF) and the Float/Slack duration (14 marks) b) Analyse the diagram, state and circle the Critical Path clearly. (6 Marks) Activity Predecessor Duration A 6 B А 7...

  • Q1: Use the network below to answer the following questions: D 7 G 8 E 5...

    Q1: Use the network below to answer the following questions: D 7 G 8 E 5 C H 10 F 3 B 3 i. ii. Assume the duration is given in weeks(numbers shown above), how long will it take to finish this project? Show your work. (4 marks) Determine the critical path. (1 mark) List the activities that could be delayed without affecting the submission of the project and determine the duration of this delay ( 1 Marks) iii.

  • Draw an activity on the arrow network for the activities of a project as shown in...

    Draw an activity on the arrow network for the activities of a project as shown in table, indicate the critical path and calculate the total float Activity description immediate predecessor Expected time (Weeks) A - 5 B - 4 C A 7 D B 7 E B 8 F B 5 G C,D 8 H E,I 11 I F 2 J F 12 K H,I 11 2.convert the above into activity on the node

  • Construct an Activity-on-branch network from the precedence relationships of activities shown Activity Predecessors Duration 6 7...

    Construct an Activity-on-branch network from the precedence relationships of activities shown Activity Predecessors Duration 6 7 A A A B с D E F 1 14 5 8 9 3 5 3 B C D C, D D H F E, J F GI G, I L, N H I J K L M 12 6

  • Consider the network described in the table below. Activity Immediate Predecessor(s) Pessimistic Probable Optimistic J --...

    Consider the network described in the table below. Activity Immediate Predecessor(s) Pessimistic Probable Optimistic J -- 15 10 8 K -- 9 8 7 L J 10 6 5 M J 3 3 3 N K, M 9 5 1 O K, M 10 7 4 P L, N 10 8 3 Draw the network diagram and answer the following questions. (a) Calculate the expected duration of each activity. (b) Calculate the expected duration and variance of the critical path....

  • Please use the information below to draw and solve the network on a piece of paper...

    Please use the information below to draw and solve the network on a piece of paper by: • Complete the forward and backward pass • Identify the critical path Fill in the requested information (Example: ESA - Early Start of Activity A; LFA - Late Finish of Activity A, etc) Duration 3 Predecessor Relationship N 2 - Activity Activity ID Contract sign A Survey Target market C Data collection Presentation Analyze results Demographics G Closing H FS Lag 3 N...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT