Question

Q1: Use the network below to answer the following questions: D 7 G 8 E 5 C H 10 F 3 B 3 i. ii. Assume the duration is given i
0 0
Add a comment Improve this question Transcribed image text
Answer #1

The given problem is

Activity Activity Duration (in weeks)
1-2 A 8
1-3 B 10
2-3 C 3
2-4 D 7
3-4 E 6
3-5 F 7
4-6 G 5
5-6 H 3

Edge and it's preceded and succeeded node

Edge Node1 → Node2
A 1→2
B 1→3
C 2→3
D 2→4
E 3→4
F 3→5
G 4→6
H 5→6

Forward Pass Method
E1=0

E2=E1+t1,2 [t1,2=A=8]=0+8=8

E3=Max{Ei+ti,3}[i=1,2]

=Max{E1+t1,3;E2+t2,3}

=Max{0+10;8+3}

=Max{10;11}

=11

E4=Max{Ei+ti,4}[i=2,3]

=Max{E2+t2,4;E3+t3,4}

=Max{8+7;11+6}

=Max{15;17}

=17

E5=E3+t3,5 [t3,5=F=7]=11+7=18

E6=Max{Ei+ti,6}[i=4,5]

=Max{E4+t4,6;E5+t5,6}

=Max{17+5;18+3}

=Max{22;21}

=22

Backward Pass Method
L6=E6=22

L5=L6-t5,6 [t5,6=H=3]=22-3=19

L4=L6-t4,6 [t4,6=G=5]=22-5=17

L3=Min{Lj-t3,j}[j=5,4]

=Min{L5-t3,5;L4-t3,4}

=Min{19-7;17-6}

=Min{12;11}

=11

L2=Min{Lj-t2,j}[j=4,3]

=Min{L4-t2,4;L3-t2,3}

=Min{17-7;11-3}

=Min{10;8}

=8

L1=Min{Lj-t1,j}[j=3,2]

=Min{L3-t1,3;L2-t1,2}

=Min{11-10;8-8}

=Min{1;0}

=0

The critical path in the network diagram has been shown. This has been done by double lines by joining all those events where E-values and L-values are equal.
The critical path of the project is: 1-2-3-4-6 and critical activities are A, C, E, G

The total project time taken ti finish is 22 weeks.
The network diagram for the project, along with E-values and L-values, is

E2=8 L2=8 D(7) 2 4 G(5) A(8) E4=17 L4=17 C(3) E1=0 L1=0 1 E(6) 6 H(3) E6=22 L6=22 B(10) F(7) 3 5 E3=11 L3=11 E5=18 L5=18

For each non-critical activity, the total float, free float and independent float calculations are shown in Table


Activity
(i,j)
(1)

Duration
(tij)
(2)
Earliest time
Start
(Ei)
(3)


(Ej)
(4)


(Li)
(5)
Latest time
Finish
(Lj)
(6)
Earliest time
Finish
(Ei+tij)
(7)=(3)+(2)
Latest time
Start
(Lj-tij)
(8)=(6)-(2)

Total Float
(Lj-tij)-Ei
(9)=(8)-(3)

Free Float
(Ej-Ei)-tij
(10)=((4)-(3))-(2)

Independent Float
(Ej-Li)-tij
(11)=((4)-(5))-(2)
1-3 10 0 11 0 11 10 1 1 1 1
2-4 7 8 17 8 17 15 10 2 2 2
3-5 7 11 18 11 19 18 12 1 0 0
5-6 3 18 22 19 22 21 19 1 1 0
Add a comment
Know the answer?
Add Answer to:
Q1: Use the network below to answer the following questions: D 7 G 8 E 5...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Consider the following project network and activity times (in weeks): Start Finish Activity | A B C D E F G H Time 5 37...

    Consider the following project network and activity times (in weeks): Start Finish Activity | A B C D E F G H Time 5 37 6 7 310 8 a. Identify the critical path. b. How much time will be needed to complete this project? c. Can activity D be delayed without delaying the entire project? If so, by how many weeks? d. Can activity C be delayed without delaying the entire project? If so, by how many weeks? What...

  • A=8 B=6 E=5 G=4 C=7 F=9 D=7 The following activities are part of a project to...

    A=8 B=6 E=5 G=4 C=7 F=9 D=7 The following activities are part of a project to be scheduled using CPM. Determine the critical Path. How many weeks will it take to complete the project? Suppose F could be shortened by two weeks and B by one week. How would this affect the completion date? OBJECTIVE QUESTION 14 The following activities are part of a project to be scheduled using CPM. B-6 A-8 G-4 D-7 E-5 F-9 a. Determine the critical...

  • Q1.      (10 marks) Construct an activity on arrow network based on the activity descriptions below. Show...

    Q1.      (10 marks) Construct an activity on arrow network based on the activity descriptions below. Show all your work. Label activities in the network by their activity letters and node numbers. Remove any redundant dependencies and label dummy activities DUMMY1, DUMMY2, etc. • Activities H, R2, T1 start the project. • Activity T2 can start when Activities H, E1 and S are completed. • Activity E1 also depends on Activity R2. • Activity X follows Activity H and precedes Activity...

  • Q4 The network diagram of a project is shown below E.4 B.3 G.5 D.5 A.7 F.2 C.4 (a) Use two-pass method to determine the...

    Q4 The network diagram of a project is shown below E.4 B.3 G.5 D.5 A.7 F.2 C.4 (a) Use two-pass method to determine the critical path. (3 points) (b) What is the project duration? ( points) (c) What is the slack time of activity F? ( points) Q4 The network diagram of a project is shown below E.4 B.3 G.5 D.5 A.7 F.2 C.4 (a) Use two-pass method to determine the critical path. (3 points) (b) What is the project...

  • .8-6. A project consists of 12 activities, represented by the project network below, where number by each arc repres...

    .8-6. A project consists of 12 activities, represented by the project network below, where number by each arc represents the duration (in days) of the associated activity 4 12 4 12 10 a) Find the earliest time, latest time, and slack for each event as well as the slack for each activity. Also identify the critical path. (b) The project has been scheduled to be completed in the minimum possible time.If all previous activities have begun as early as possible...

  • Consider a project having the following six activities:                                  

    Consider a project having the following six activities:                                                      Immediate                                                  Max        Crash cost             Activity                           Predecessors           Time (weeks)             Crash*    per week                   A                                none                                    6                          6                N/A                   B                                none                                    5                          2               $500                   C                                A                                       3                          2             $1000                   D                                A, B                                    4                          2             $2000                   E                                 C, D                                    5                          2             $1250                   F                                D                                       6                          2             $1000                                                                                                 *Shortest possible time for the task 1. Draw the project network and list...

  • Consider the project network information in Table 1 of Case Study A on Page 3 below....

    Consider the project network information in Table 1 of Case Study A on Page 3 below. Assuming the project starts at time zero and all activity connections are finish-to-start, draw an Activity on the Node (AON) network diagram of the project, determine the expected project completion time, state the critical activities and critical path(s). Crash the project by 1 week and state the total crash cost. (b) (18 narl Case Study A Table 1 below contains activities associated with a...

  • Consider the project network information in Table 1 of Case Study A on Page 3 below....

    Consider the project network information in Table 1 of Case Study A on Page 3 below. Assuming the project starts at time zero and all activity connections are finish-to-start, draw an Activity on the Node (AON) network diagram of the project, determine the expected project completion time, state the critical activities and critical path(s). Crash the project by 1 week and state the total crash cost. (b) (18 nar Case Study A Table 1 below contains activities associated with a...

  • Problem 5-14 (Static) Here is a CPM network with activity times in weeks: a. Determine the...

    Problem 5-14 (Static) Here is a CPM network with activity times in weeks: a. Determine the critical path. a. A-E-F-D b. A-E-G-C-D c. A-B-C-D b. How many weeks will the project take to complete? c. Suppose F could be shortened by two weeks and B by one week. By how many weeks would this reduce the project duration? B(5) E(4) F(8)

  • : A network consists of the following list. Times are given in weeks. Activity Preceding Duration...

    : A network consists of the following list. Times are given in weeks. Activity Preceding Duration A -- 9 B A 2 C A 12 D A 5 E B 6 F B 8 G C, F 3 H D 2 I H 8 J G, I 6 K E, J 2 Draw the network diagram. Find ES, EF, LS, LF, and the slack times for each of the activities. Which activities are critical? Determine the critical path(s). What is...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT