Part 1.C&A Fast Food has four activities in serving a customer: greet customer, take order, process...

Part 1.C&A Fast Food has four activities in serving a customer: greet customer, take order, process order, and deliver order. Each activity is staffed by one employee (for a total of four employees). The processing time for each activity is given as follows:

ActivityProcessing time per customer

Greet customer 2 seconds

Take order 30 seconds

Process order 60 seconds

Deliver order 5 seconds.

a. What is the average labor utilization?

b.Assume demand is unlimited. If one additional employee is added to the bottleneck activity, what will be the percentage change in process capacity?

Part 2.Which of the following statements about takt time and cycle time is TRUE ?

A) If takt time is longer than cycle time, target manpower will be lower than current staff level.

B) Supply matches demand when takt time is shorter than cycle time.

C) If takt time is longer than cycle time, target manpower will be higher than current staff level.

D) Supply is less than demand when takt time is equal to cycle time.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Part 1

a.In this case the bottleneck is the step “Process order” with a capacity of 1 customer per minute. This will reduce the overall capacity of the system. At this rate the system capacity is 1 customer per minute. This also results in the usage of the following times = 2 + 30 + 60 + 5 = 97 seconds. However, the total available time is 4*60 = 240 seconds. This means the utilization is 97/240 = 0.4041 or 40.41%

b.If we add another employee to “Process order” the capacity of the step will double. This means step capacity will be 2 customer per minute. This is also the same as “Take order” step. Overall process capacity will now be 2 customers per minute. This is a 100% increase over the previous stage.

Part 2

If takt time is longer than cycle time, target manpower will be lower than current staff level.

Takt time represents the time the company should take to make a product. Cycle time represents the time company takes to make a product. This means if the cycle time is less or takt time is high, the company can meet the demand and also have some idle time. This translates into the fact that the current manpower is more than target manpower.

Add a comment
Know the answer?
Add Answer to:
Part 1.C&A Fast Food has four activities in serving a customer: greet customer, take order, process...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Four employees at a fast-food restaurant each perform one of the four activities in serving a...

    Four employees at a fast-food restaurant each perform one of the four activities in serving a customer: greet customer, take order, process order, and deliver order. The processing time for each activity is given as follows:   Activity Processing time per customer Greet customer 2 seconds Take order 30 seconds Process order 60 seconds Deliver order 5 seconds 60 seconds 35.75 seconds 143 seconds 97 seconds Assume demand is unlimited. What is the total idle time?

  • 13. Automating some activities at a nonbottleneck resource simply increases the amount of idle time for...

    13. Automating some activities at a nonbottleneck resource simply increases the amount of idle time for that resource without making the process more efficient. True or False? 14. Specialization reduces processing times by making it easier to balance the line. True or False ? 15. C&A Fast Food has four activities in serving a customer: greet customer, take order, process order, and deliver order. Each activity is staffed by one employee (for a total of four employees). The processing time...

  • PART I: Multiple Choice Write all answers to the following questions. No partial credit available. Consumption...

    PART I: Multiple Choice Write all answers to the following questions. No partial credit available. Consumption utility is composed of price and convenience. True or False? A firm reduces inefficiencies by making trade-offs. True or False? A firm can increase its profitability by: A. increasing costs and reducing price. B. moving away from the efficient frontier. C. increasing inefficiencies. D. reducing inefficiencies. Operations comes from the Latin word "opus," which means: A. activity. B. helping people. C. improvement. D. work....

  • One employee is in charge of the following activities at a refreshment stand: Activity Activity Time...

    One employee is in charge of the following activities at a refreshment stand: Activity Activity Time per Customer Greet customer 5 seconds Take order 25 seconds Process order 1.5 minutes Print receipt 30 seconds If demand rate is 20 customers per hour and the process is not constrained by input raw materials, what are the flow rate (in customers per hour), utilization, and cycle time (in minutes per customer)? Note: Here "cycle time" is the reciprocal of the Flow Rate....

  • 56) One employee is in charge of the following activities at a refreshment stand: Activity Greet...

    56) One employee is in charge of the following activities at a refreshment stand: Activity Greet customer Take order Process order Print receipt Activity Time per Customer 5 seconds 25 seconds 1.5 minutes 30 seconds If demand rate is 20 customers per hour, what are the flow rate (in customers per hour), utilization, and cycle time (in minutes per customer)? A) 20, 0.83, 0.05 B) 24, 1, 0.04 c)20,0.83, 3 D) 24, 1,25 57) Patients are arriving at a clinic...

  • A customer who wants a coffee moves sequentially to 2 stations staffed by 4 employees in...

    A customer who wants a coffee moves sequentially to 2 stations staffed by 4 employees in a Starbucks: The customer first moves to one of the two cash registers where Alex and Bob are working. One of them places the order and accepts payment. There is one extra cash register where no one is working. One of Charlotte and David makes the coffee using a coffee machine. Both Charlotte and David have their own coffee machines. There is one extra...

  • Problem 4 (16 points) Consider a typical patient's stay in the emergency department (ED). On average,...

    Problem 4 (16 points) Consider a typical patient's stay in the emergency department (ED). On average, 10 patients arrive to the ED per hour. Triage: Once a patient arrives, he/she is first triaged at the triage station which is staffed with one triage nurse. The triage process takes 5 minutes on average. Initial Consultation: After triage, the patient goes through initial consultation with a nurse who takes information on the patient's demographics, medical history, allergies, etc. On average, initial consultation...

  • Question: The whole process before administering blood can be broken down into the following nine activities:...

    Question: The whole process before administering blood can be broken down into the following nine activities: A. Register B. Consult and take tests C. Sample blood D. Deliver blood sample to lab E. Deliver blood to bank (CBS) F. Deliver test blood to lab (CBS) G. Cross-match H. Retrieve blood from bank I. Deliver blood to the clinic (Note: Administering blood is a pure medical activity. This activity will be excluded since your the analysis will not help to reduce...

  • QUESTION 1 Customers arrive at a hair salon according to a Poisson process with an average of 1...

    QUESTION 1 Customers arrive at a hair salon according to a Poisson process with an average of 16 customers per hour. Which of the following is most likely true, based on this information: a. The hair salon serves customers on a walk-in basis (rather than by appointment times) b. If 10 customers arrive in the first hour, it is likely that 22 customers will arrive in the next hour. c. If the salon can serve an average of 20 customers...

  • Sandra has been the clinical manager in critical care for 10 years. She has noticed that...

    Sandra has been the clinical manager in critical care for 10 years. She has noticed that there has been an increasing level of changes in technology and clinical practice in the past 5 years. This new technology has created a different way of treating patients and has called clinical providers to adjust the way in which they deliver care for those patients. Because of the new technology, patients who are more seriously ill are now receiving higher levels of complex...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT