A customer who wants a coffee moves sequentially to 2 stations staffed by 4 employees in...

A customer who wants a coffee moves sequentially to 2 stations staffed by 4 employees in a Starbucks: The customer first moves to one of the two cash registers where Alex and Bob are working. One of them places the order and accepts payment. There is one extra cash register where no one is working. One of Charlotte and David makes the coffee using a coffee machine. Both Charlotte and David have their own coffee machines. There is one extra coffee machine which is not used by anyone.

The task time of placing an order and accepting payment is 45 seconds. The task time of making a coffee is 60 seconds.

Tasks Task time Place an order & accept payment 45 seconds Make a coffee 60 seconds

Note: Alex & Bob take the same amount of time to do their tasks. Charlotte & David take the same amount of time to do their tasks.

(a) Draw the process flow diagram.

(b) What is the process capacity and what is (are) the bottleneck(s) of the process?

(c) What is the cycle time of the process?

(d) What is the flow time of the process?

(e) The Starbucks recruits a new staff Elena. It takes Elena 45 seconds to place an order & accept payment and 60 seconds to make a coffee. To improve the process capacity, which task should Elena be assigned to? What is the new process capacity?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

inconich Gustones Stase outgoing Custorurs Ted

Output of the first station = 60x60/45x2= 160 per hour

Output of the second station = 60x60/60 x2 =120 per hour

Process capacity is equal to the slowest station ( station 2)which is 120 per hour.

station 2 is bottleneck with  capacity of 120

cycle time= 60/120 =0.5 min = 30 sec.

flow time for a unit = 45+60 =105 sec.

If a new resource is assigned to the process, it should be assigned to the slower process hich is stage 2 ( coffee making) The new capacityof stage 2 would be

3x60x60/60 =180

New capacity would be now 160, which is eual to the capacity of slower station which is now 1, with capacity of 160.

Add a comment
Know the answer?
Add Answer to:
A customer who wants a coffee moves sequentially to 2 stations staffed by 4 employees in...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 1) Customers at a coffee shop ask for hot, say Xn 0, or cold, say X 1, beverages according to a Bernoulli process with parameter p. Let N denote the first time that a customer wants the same kind...

    1) Customers at a coffee shop ask for hot, say Xn 0, or cold, say X 1, beverages according to a Bernoulli process with parameter p. Let N denote the first time that a customer wants the same kind as their predecessor. (a) Find the pmf of N. (b) What is the probability that XN+ 1? (c) If cold drinks take 30 seconds to prepare and hot drinks take 60 seconds. What is the expected time taken to serve the...

  • Marketing Planning Helps Dunkin’ Donuts Score Big in Coffee Customer Loyalty A key goal for a...

    Marketing Planning Helps Dunkin’ Donuts Score Big in Coffee Customer Loyalty A key goal for a marketing manager is to make sure that the company’s brand stays relevant. Successfully realizing this goal requires a marketing planning process that is both thorough and grounded in best practices, and also flexible enough to allow the firm to react to (and hopefully stay ahead of) changing customer preferences and shifts in values. Over its 67 years in business, Dunkin’ Donuts has shown that...

  • please show work so i can understand the work 10. Grounded Coffee Products manufactures coffee tables....

    please show work so i can understand the work 10. Grounded Coffee Products manufactures coffee tables. Grounded Coffee Products has a policy of adding a 10% markup to full costs and currently has excess capacity. The following information pertains to the company's normal operations per month: Output units Machine-hours Direct manufacturing labor-hours Direct materials per unit Direct manufacturing labor per hour Variable manufacturing overhead costs Fixed manufacturing overhead costs Product and process design costs Marketing and distribution costs 20,000 tables...

  • Exercise 1. Customers at a coffee shop ask for hot, denote it X 0, or cold, denote it Xn 1, beverages according to a Bernoulli process with parameter p. Let N denote the first time that a customer wa...

    Exercise 1. Customers at a coffee shop ask for hot, denote it X 0, or cold, denote it Xn 1, beverages according to a Bernoulli process with parameter p. Let N denote the first time that a customer wants the same kind as their predecessor. (1) Find the PMF of N (2) What is the probability that XN+1-1? (3) Cold drinks take 30 seconds to prepare and hot drinks take 60 seconds. What is the expected time taken to serve...

  • Marketing Planning Helps Dunkin’ Donuts Score Big in Coffee Customer Loyalty A key goal for a...

    Marketing Planning Helps Dunkin’ Donuts Score Big in Coffee Customer Loyalty A key goal for a marketing manager is to make sure that the company’s brand stays relevant. Successfully realizing this goal requires a marketing planning process that is both thorough and grounded in best practices, and also flexible enough to allow the firm to react to (and hopefully stay ahead of) changing customer preferences and shifts in values. Over its 67 years in business, Dunkin’ Donuts has shown that...

  • sore. opis 2 of 9 (5 complete) HW Score: 50%, 20 of 40 p Problem 1...

    sore. opis 2 of 9 (5 complete) HW Score: 50%, 20 of 40 p Problem 1 Question Help Receives Food Takes the Money Takes The Money The minimum cycle time is 125 seconds. (Enter your response as a whole number.) The longest cycle time is 160 seconds. (Enter your response as a whole number) b. Suppose Billy's Hamburger Barn redesigns the process so there are now two attendants. The first attendant takes the order. Once this step is finished, the...

  • what are the answers to the last question Save Homework: HW #3 Score: 6.67 of 8...

    what are the answers to the last question Save Homework: HW #3 Score: 6.67 of 8 pts Problem 1 2 of 9 (7 complete) HW Score: 76.67%, 30.67 of 40 pts 3 Question Help Billy's Hamburger Barn has a single drive-up window. Currently, there is one attendant at the window who takes the order (40 - 60 seconds), gathers up the food and bags it (45-50 seconds), and then takes the customer's money (40-50 seconds) before handing the food to...

  • PART I: Multiple Choice Write all answers to the following questions. No partial credit available. Consumption...

    PART I: Multiple Choice Write all answers to the following questions. No partial credit available. Consumption utility is composed of price and convenience. True or False? A firm reduces inefficiencies by making trade-offs. True or False? A firm can increase its profitability by: A. increasing costs and reducing price. B. moving away from the efficient frontier. C. increasing inefficiencies. D. reducing inefficiencies. Operations comes from the Latin word "opus," which means: A. activity. B. helping people. C. improvement. D. work....

  • Define Starbucks’ niche in the coffeehouse marketplace, both in its early days and today… Discuss the...

    Define Starbucks’ niche in the coffeehouse marketplace, both in its early days and today… Discuss the factors that caused Starbucks' sales to stumble in the mid-to-late 2000s. If you were the CEO at the time, how would you have reversed this trend? What comes next for Starbucks? What new marketing strategies might the company develop to remain relevant? 2. Company and Marketing Strategy Partnering to Build Customer Engagement, Value, and | Relationships CHAPTER PREVIEW In the first chapter, we explored...

  • 56) One employee is in charge of the following activities at a refreshment stand: Activity Greet...

    56) One employee is in charge of the following activities at a refreshment stand: Activity Greet customer Take order Process order Print receipt Activity Time per Customer 5 seconds 25 seconds 1.5 minutes 30 seconds If demand rate is 20 customers per hour, what are the flow rate (in customers per hour), utilization, and cycle time (in minutes per customer)? A) 20, 0.83, 0.05 B) 24, 1, 0.04 c)20,0.83, 3 D) 24, 1,25 57) Patients are arriving at a clinic...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT