Question

Draw an activity on the arrow network for the activities of a project as shown in...

Draw an activity on the arrow network for the activities of a project as shown in table, indicate the critical path and calculate the total float

Activity description immediate predecessor Expected time (Weeks)
A - 5
B - 4
C A 7
D B 7
E B 8
F B 5
G C,D 8
H E,I 11
I F 2
J F 12
K H,I 11

2.convert the above into activity on the node

0 0
Add a comment Improve this question Transcribed image text
Answer #1

First Lets the draw (AON) diagram for values. ES EF 1 ES EF If=o А 5 с 7 6112 ES 13 20 T 15+F=0 Es Earlystart EF= Early finiCritical path is B-E-H-K project completion days = 34 (weeks) Activity Total float A B С D F Orto O O O doo

Add a comment
Know the answer?
Add Answer to:
Draw an activity on the arrow network for the activities of a project as shown in...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT