I need help Software Project Management question
Q1. For the following table of information:
a) Draw a network diagram (Activity on Arrow)
b) List down all the network paths
c) Determine the critical path(s)
Activity |
Predecessor |
Duration |
A |
Start |
5 days |
B |
A |
2 days |
C |
A |
3 days |
D |
B |
4 days |
E |
C |
6 days |
F |
C |
3 days |
G |
D, E |
4 days |
H |
F |
2 days |
I |
G |
3 days |
J |
H |
1 day |
K |
I, J |
2 days |
Without earlier/later start and finish
With earlier/later start and finish
I need help Software Project Management question Q1. For the following table of information: a)...
Given the information in the following table: Activity Duration Predecessor A 4 None B 6 A C 4 A D 2 C E 4 B F 5 B, D G 3 C H 4 F, G I 2 E, H Construct the (AON) Activity on Node network diagram Find each activity’s ES, EF, LS and LS Identify all paths. Which path is the critical path? Calculate the slack for each activity. How long will it take to complete the project?
Hello, I need help in the following exercises from book: Project Management: Achieving competitive advantage (4th ed.).Jeffery Pinto Exercise 9.1 Consider the following information that you have compiled re- garding the steps needed to complete a project. You have identi- fied all relevant steps and have made some determinations re- garding predecessor/successor relationships. Using MS Project, develop a simple network diagram for this project, showing the links among the project activities. Activity Predecessors A – Survey site — B –...
QUESTION 2 Given the following information, you are to determine the following Project network. Early, late and slack activity times. Project duration. Critical path Task Predecessor Duration A None 8 B A 5 C A 10 D A 15 E A 10 F B 12 G C, D 12 H E, 7 I G, H 7 J F,G,I 10 K J 12
Assignment for week 5Given the following information, draw the project network. Compute the early, late and slack times for the project network. which activities are on the critical path have only the start or finish of the activity on the critical path?ID duration finish to start finish to start additional lag lag predecessor lag Relationship A 2 none 0 none 0B 4 A 0 none 0C 6 A 0 finish-finish C to F 7D 8 A 0 none 0E 18...
for each problem I have this setup so far. I need help on each part and im not too sure if I am on the right track for each question on the picture. this chapter is on project management for statistics 1. A project is shown by the following network. The durations of activities (in weeks) are indicated on the arrows. a. Identify all of the paths, compute the length of each, identify the critical path and the b. Determine...
1. The activities needed for a new project your company is undertaking are listed in the following table. ACTIVITY IMMEDIATE PREDECESSOR(S) A ---- B ---- C A D A, B E B F C, D, E G D, E H F I F, G J G The activity times were determined for the project, and were as below. ACTIVITY ACTIVITY TIME (days) A 11 B 9 C 7 D 12 E 8 F 9 G 10 H 6 I 7...
The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations and what activities each must precede: Activity Duration (weeks) Precedes A (start) 2 B, C B 2 E C 6 F E 3 F F (end) 4 — This exercise contains only parts b, c, and d. b) Define the critical path, listing all critical activities in chronological order. Critical path activities are the activities that lie on the longest...
9. Given the following information in the table, construct an activity on the node diagram. Label the critical path as well as the early and late start/finish times and the slack for each activity. (20 points) Predecessor Duration (Days) Activity A, B C, D F,G 9. Given the following information in the table, construct an activity on the node diagram. Label the critical path as well as the early and late start/finish times and the slack for each activity. (20...
A project has the following set of activities Activity Immediate Predecessor Duration (weeks) A - 8 B - 10 C A 3 D A 7 E B, C 6 F B, C 7 G D, E 5 H F 3 Draw the AON diagram Identify all the possible paths What is the critical path? Can activity B be delayed without delaying the completion of the project? If so, by how many days?
Activity Duration Precedence Problem# 3 For the project information given below (wecks) information a) Draw the network diagram to accurately B must be after C represent the information given C must be after A 10 15 b) Determine the earliest start, earliest D must be after B E must be after C F must be after D and E G must be after F H must be after G 1 must be after F finished, latest start, latest finish for...