Exercise 9.1

Consider the following information that you have compiled re-
garding the steps needed to complete a project. You have identi-
fied all relevant steps and have made some determinations re-
garding predecessor/successor relationships. Using MS Project,

develop a simple network diagram for this project, showing the
links among the project activities.

Activity Predecessors
A – Survey site —
B – Install sewer and storm drainage A
C – Install gas and electric power lines A
D – Excavate site for spec house B, C
E – Pour foundation D

Exercise 9.2
Suppose we have a complete activity predecessor table (shown
here) and we wish to create a network diagram highlighting the
activity sequence for this project. Using MS Project, enter the
activities and their predecessors and create a complete activity
network diagram for this project.
Project—remodeling an aPPliance
Activity Predecessors
A Conduct competitive analysis —
B Review field sales reports —
C Conduct tech capabilities
assessment


D Develop focus group data A, B, C
E Conduct telephone surveys D
F Identify relevant specification
improvements E
G Interface with marketing staff F
H Develop engineering
specifications G
I Check and debug designs H
J Develop testing protocol G
K Identify critical performance
levels J
L Assess and modify product
components I, K
M Conduct capabilities
assessment L
N Identify selection criteria M

Activity Predecessors
O Develop RFQ M
P Develop production master
schedule N, O
Q Liaise with sales staff P
R Prepare product launch Q

Exercise 9.3

Suppose that we add some duration estimates to each of the ac-
tivities from exercise 9.1. A portion of the revised table is shown

here. Recreate the network diagram for this project and note
how MS Project uses nodes to identify activity durations, start
and finish dates, and predecessors. What is the critical path for
this network diagram? How do we know?
Activity Duration Predecessors
A – Survey site 5 days —
B – Install sewer and storm
drainage 9 days A
C – Install gas and electric
power lines 4 days A
D – Excavate site for spec
house 2 days B, C
E – Pour foundation 2 days D

0 0
Add a comment Improve this question Transcribed image text
Know the answer?
Add Answer to:
Hello, I need help in the following exercises from book: Project Management: Achieving competitive advantage (4th...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • F: The activities in the following table describe the construction of a new house. Activity Predecessor(s)...

    F: The activities in the following table describe the construction of a new house. Activity Predecessor(s) Duration(days) A: Clear site B: Bring utilities to site Excavate D: Pour foundation E: Outside plumbing B, C Frame house D G: Do electric wiring H: Lay floor Lay roof F Inside plumbing E, H K: Shingling Outside sheathing insulation F.J M: Install windows and outside doors F Do brick work L, M 0: Insulate walls and ceiling GJ Cover walls and ceiling 0...

  • I need help Software Project Management question Q1. For the following table of information:        a)...

    I need help Software Project Management question Q1. For the following table of information:        a) Draw a network diagram (Activity on Arrow)        b) List down all the network paths        c) Determine the critical path(s) Activity Predecessor Duration A Start 5 days B A 2 days C A 3 days D B 4 days E C 6 days F C 3 days G D, E 4 days H F 2 days I G 3 days J H 1...

  • Your Assignment is to Create a Project Schedule in MS Project. You are to Create a...

    Your Assignment is to Create a Project Schedule in MS Project. You are to Create a Project Schedule using the durations, including Predecessors and Names on each activity Amir’s Sheds is a successful franchise in the home building industry. Amir’s Sheds build specific purpose sheds for home gardens, farms and industrial storage facilities. The project starts on Monday, June 3, 2019 WBS for Building a Shed Task ID Task Description Predecessor Time Resources (people and materials required to complete the...

  • Scenario: Your organisation, ABC construction group has made a winning bid to construct a new manufacturing...

    Scenario: Your organisation, ABC construction group has made a winning bid to construct a new manufacturing plant. The client expects the plant to be functional within a year. You are assigned as the Project Manager to ensure that the whole project stays on schedule. The two important conditions as per the client contract are:- ABC construction group will incur a penalty if the work is not completed by the deadline of 47 weeks from now. ABC construction group will be...

  • Problem 15-7 Consider the following table of precedence relationships for a portion of a house building...

    Problem 15-7 Consider the following table of precedence relationships for a portion of a house building project: Task Duration Estimates Immediate Predecessor(s) A Prepare Site 3 days None B Install Rough Plumbing 2 days Prepare Site C Pour Concrete Foundation 3 days Install Rough Plumbing D Concrete Curing Time 4 days Pour Concrete Foundation E Preassemble Wall Frames 6 days None F Erect Wall Frames 2 days Preassemble WF, Cure Concrete G Install Roof 1 day Erect Wall Frames H...

  • The following activities of a hospital expansion project has been identified in the following table. First,...

    The following activities of a hospital expansion project has been identified in the following table. First, all activities of the project are listed. Next, the immediate predecessor(s) of each activity is identified (activity relationships). Please plot the activity network diagram and answer the following questions. Hospital Expansion Project Activity Description Immediate predecessor(s) Activity Time (Weeks) A Select administrative and medical staff - 12 B Select site and do site survey - 9 C Select equipment A 10 D Prepare final...

  • Describe the project network to build a house from the data below. Calculate the time and...

    Describe the project network to build a house from the data below. Calculate the time and critical path. Activity Description Predecessor Time (Days) A Clear the location - 1 B Bring the tool to the location - 2 C Conducting excavations A 1 D Pour the foundation C 2 E Plumbing installation from outside B, C 6 F Create a home frame D 10 G Installation of electric wire F 3 H Install the floor G 1 I Installing the...

  • Microsoft Project Assignment Description A system development project has been defined to contain the following list of...

    Microsoft Project Assignment Description A system development project has been defined to contain the following list of activities along with their estimated times for completion. The project will start on 5/1/2019. Project Data Provided: Activity ID Activity Name Days Predecessors Optimistic(O) Realistic(R) Pessimistic(P) 1 Gather Requirement 1 2 3 2 Analyze processes 1 2 6 1 3 Define DFDs 0.5 1 1.5 2 4 Design Processes 2 7 12 2 5 Design database 4 7 22 3 6 Design UI...

  • Question #1: Some of the tasks in this project can be done in parallel. Prepare a...

    Question #1: Some of the tasks in this project can be done in parallel. Prepare a diagram showing the required network of tasks and define the critical path. What is the length of the project without crashing? Do not just answer, but show the whole process. Question #2: If the critical path is longer than 29 days, what is the least additional amounting that Dr. Watage can spend and still achieve this schedule objective (29 days)? Do not just answer,...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT