Question

Describe the project network to build a house from the data below. Calculate the time and...

  1. Describe the project network to build a house from the data below. Calculate the time and critical path.

Activity

Description

Predecessor

Time (Days)

A

Clear the location

-

1

B

Bring the tool to the location

-

2

C

Conducting excavations

A

1

D

Pour the foundation

C

2

E

Plumbing installation from outside

B, C

6

F

Create a home frame

D

10

G

Installation of electric wire

F

3

H

Install the floor

G

1

I

Installing the roof

F

1

J

Installation of plumbing from inside

E, H

5

K

Installing the roof

I

2

L

Installation of the outer wall layers

F, J

1

M

Installing windows and outside doors

F

2

N

Build a wall

L, M

4

O

Isolate the walls and ceiling

G, J

2

P

Close the walls and ceiling

O

2

Q

Isolate the roof

I, P

1

R

Finish the interior

P

7

S

Finish the exterior

I, N

7

T

Build a garden

S

3

0 0
Add a comment Improve this question Transcribed image text
Answer #1

*******Please please please LIKE THIS ANSWER, so that I can get a small benefit, Please*******

Solution:

Activity Immediate Predecessors Duration
A - 1
B - 2
C A 1
D C 2
E B,C 6
F D 10
G F 3
H G 1
I F 1
J E,H 5
K I 2
L F,J 1
M F 2
N L,M 4
O G,J 2
P O 2
Q I,P 1
R P 7
S I,N 7
T S 3

Edge and it's preceded and succeeded node

Edge Node1 → Node2
A 1→2
B 1→3
C 2→4
E 3→8
d 4→3
D 4→5
F 5→6
G 6→7
I 6→9
L 6→11
M 6→12
H 7→8
O 7→14
J 8→10
d 9→13
d 9→16
K 9→18
d 10→6
d 10→7
d 11→12
N 12→13
S 13→17
P 14→15
d 15→16
R 15→18
Q 16→18
T 17→18

The network diagram for the project, along with activity time, is

Forward Pass Method
E1=0

E2=E1+t1,2 [t1,2=A=1]=0+1=1

E3=Max{Ei+ti,3}[i=1,4]

=Max{E1+t1,3;E4+t4,3}

=Max{0+2;2+0}

=Max{2;2}

=2

E4=E2+t2,4 [t2,4=C=1]=1+1=2

E5=E4+t4,5 [t4,5=D=2]=2+2=4

E6=Max{Ei+ti,6}[i=5,10]

=Max{E5+t5,6;E10+t10,6}

=Max{4+10;0+0}

=Max{14;0}

=14

E7=Max{Ei+ti,7}[i=6,10]

=Max{E6+t6,7;E10+t10,7}

=Max{14+3;0+0}

=Max{17;0}

=0

E8=Max{Ei+ti,8}[i=3,7]

=Max{E3+t3,8;E7+t7,8}

=Max{2+6;0+1}

=Max{8;1}

=8

E9=E6+t6,9 [t6,9=I=1]=14+1=0

E10=E8+t8,10 [t8,10=J=5]=8+5=0

E11=E6+t6,11 [t6,11=L=1]=14+1=0

E12=Max{Ei+ti,12}[i=6,11]

=Max{E6+t6,12;E11+t11,12}

=Max{14+2;0+0}

=Max{16;0}

=0

E13=Max{Ei+ti,13}[i=9,12]

=Max{E9+t9,13;E12+t12,13}

=Max{0+0;0+4}

=Max{0;4}

=0

E14=E7+t7,14 [t7,14=O=2]=0+2=0

E15=E14+t14,15 [t14,15=P=2]=0+2=0

E16=Max{Ei+ti,16}[i=9,15]

=Max{E9+t9,16;E15+t15,16}

=Max{0+0;0+0}

=Max{0;0}

=0

E17=E13+t13,17 [t13,17=S=7]=0+7=0

E18=Max{Ei+ti,18}[i=9,15,16,17]

=Max{E9+t9,18;E15+t15,18;E16+t16,18;E17+t17,18}

=Max{0+2;0+7;0+1;0+3}

=Max{2;7;1;3}

=0


Backward Pass Method
L18=E18=0

L17=L18-t17,18 [t17,18=T=3]=0-3=-3

L16=L18-t16,18 [t16,18=Q=1]=0-1=-1

L15=Min{Lj-t15,j}[j=18,16]

=Min{L18-t15,18;L16-t15,16}

=Min{0-7;-1-0}

=Min{-7;-1}

=-7

L14=L15-t14,15 [t14,15=P=2]=-7-2=-9

L13=L17-t13,17 [t13,17=S=7]=-3-7=-10

L12=L13-t12,13 [t12,13=N=4]=-10-4=-14

L11=L12-t11,12 [t11,12=d=0]=-14-0=-14

L10=Min{Lj-t10,j}[j=7,6]

=Min{L7-t10,7;L6-t10,6}

=Min{-11-0;-16-0}

=Min{-11;-16}

=-16

L9=Min{Lj-t9,j}[j=18,16,13]

=Min{L18-t9,18;L16-t9,16;L13-t9,13}

=Min{0-2;-1-0;-10-0}

=Min{-2;-1;-10}

=-10

L8=L10-t8,10 [t8,10=J=5]=-16-5=-5

L7=Min{Lj-t7,j}[j=14,8]

=Min{L14-t7,14;L8-t7,8}

=Min{-9-2;-5-1}

=Min{-11;-6}

=-11

L6=Min{Lj-t6,j}[j=12,11,9,7]

=Min{L12-t6,12;L11-t6,11;L9-t6,9;L7-t6,7}

=Min{-14-2;-14-1;-10-1;-11-3}

=Min{-16;-15;-11;-14}

=-16

L5=L6-t5,6 [t5,6=F=10]=-16-10=-26

L4=Min{Lj-t4,j}[j=5,3]

=Min{L5-t4,5;L3-t4,3}

=Min{-26-2;-11-0}

=Min{-28;-11}

=-28

L3=L8-t3,8 [t3,8=E=6]=-5-6=-11

L2=L4-t2,4 [t2,4=C=1]=-28-1=-29

L1=Min{Lj-t1,j}[j=3,2]

=Min{L3-t1,3;L2-t1,2}

=Min{-11-2;-29-1}

=Min{-13;-30}

=-30

No critical path found

*******Please please please LIKE THIS ANSWER, so that I can get a small benefit, Please*******

Add a comment
Know the answer?
Add Answer to:
Describe the project network to build a house from the data below. Calculate the time and...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • F: The activities in the following table describe the construction of a new house. Activity Predecessor(s)...

    F: The activities in the following table describe the construction of a new house. Activity Predecessor(s) Duration(days) A: Clear site B: Bring utilities to site Excavate D: Pour foundation E: Outside plumbing B, C Frame house D G: Do electric wiring H: Lay floor Lay roof F Inside plumbing E, H K: Shingling Outside sheathing insulation F.J M: Install windows and outside doors F Do brick work L, M 0: Insulate walls and ceiling GJ Cover walls and ceiling 0...

  • Problem 15-7 Consider the following table of precedence relationships for a portion of a house building...

    Problem 15-7 Consider the following table of precedence relationships for a portion of a house building project: Task Duration Estimates Immediate Predecessor(s) A Prepare Site 3 days None B Install Rough Plumbing 2 days Prepare Site C Pour Concrete Foundation 3 days Install Rough Plumbing D Concrete Curing Time 4 days Pour Concrete Foundation E Preassemble Wall Frames 6 days None F Erect Wall Frames 2 days Preassemble WF, Cure Concrete G Install Roof 1 day Erect Wall Frames H...

  • Assume you are the Design/Build Contractor for a CVS Pharmacy in Logan, OH. The building is...

    Assume you are the Design/Build Contractor for a CVS Pharmacy in Logan, OH. The building is 11,945 square feet in size with construction scheduled to commence on January 18, 2017. Use the progress completion schedule from a similar CVS Pharmacy in Athens, OH, to organize the overall schedule for the project by weekly progress for a completion date (turn over to owner) on May 23, 2017. 1. Progress in one week: awnings, landscaping, permanent electrical power, gas service 2. Progress...

  • Consider the office renovation project data in the following table. A "zero" time estimate means that...

    Consider the office renovation project data in the following table. A "zero" time estimate means that the activity could take a very small amount of time and should be treated as a numeric zero in the analysis. a. Based on the critical path, find the probability of completing the office renovation project by 38 days. Refer to the standard normal table. (Make sure to round all intermediate calculations for te and variance to two decimal places.) Time Estimates (days) Activity...

  • In this problem, you will estimate the heat lost by a typical house, assuming that the...

    In this problem, you will estimate the heat lost by a typical house, assuming that the temperature inside is Tin=20∘C and the temperature outside is Tout=0∘C. The walls and uppermost ceiling of a typical house are supported by 2×6 inch wooden beams (kwood=0.12W/(mK)) with fiberglass insulation (kins=0.04W/(mK)) in between. The thickness of the wall is Lwall=18cm allowing for interior and exterior covering. Assume that the house is a cube of length L=9.0m on a side. Approximate that the roof has...

  • a. Develop a report that presents a planned schedule and expected project completion time in workdays....

    a. Develop a report that presents a planned schedule and expected project completion time in workdays. Include a project network in your report using MS Project. b. Explain how does this project compared to the average project. The average duration for a construction of a villa project normally takes 120 workdays. c. Find the probability of finishing this project in 120 workdays? d. Also find what expected completion time will ensure a 90% chance of completing the project in 120...

  • Scenario: Your organisation, ABC construction group has made a winning bid to construct a new manufacturing...

    Scenario: Your organisation, ABC construction group has made a winning bid to construct a new manufacturing plant. The client expects the plant to be functional within a year. You are assigned as the Project Manager to ensure that the whole project stays on schedule. The two important conditions as per the client contract are:- ABC construction group will incur a penalty if the work is not completed by the deadline of 47 weeks from now. ABC construction group will be...

  • Problem 9-14 Given the following activity times in months, determine the items listed below: Time Estimates...

    Problem 9-14 Given the following activity times in months, determine the items listed below: Time Estimates (months) Activity Activity Predecessor а т 4 12 A B 6 10 15 С 2 10 14 1 D A 4 13 E A 3 F В 3 6 18 G 2 8 12 Н С.Е.F С.Е.F 15 22 I 5 12 21 J D 20 25 K G.I 5 12 L Н.К 3 20 Expected activity times b. Variance times а. c. Earliest...

  • Given all the information in the table, use PERT/CPM to help Mr. Hawthorne address to the...

    Given all the information in the table, use PERT/CPM to help Mr. Hawthorne address to the following questions. A. Create the network diagram representing the problem. B. What is the total time expected to be required to complete the project if no delays occur? C. What are the earliest and latest start and finish times for the individual activities required to meet the expected project completion time provided in question B (show your method for determining this)? D. Which are...

  • Hello, I need help in the following exercises from book: Project Management: Achieving competitive advantage (4th...

    Hello, I need help in the following exercises from book: Project Management: Achieving competitive advantage (4th ed.).Jeffery Pinto Exercise 9.1 Consider the following information that you have compiled re- garding the steps needed to complete a project. You have identi- fied all relevant steps and have made some determinations re- garding predecessor/successor relationships. Using MS Project, develop a simple network diagram for this project, showing the links among the project activities. Activity Predecessors A – Survey site — B –...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT