a. Develop a report that presents a planned schedule and
expected project completion time in
workdays. Include a project network in your report using MS
Project.
b. Explain how does this project compared to the average project.
The average duration for a
construction of a villa project normally takes 120 workdays.
c. Find the probability of finishing this project in 120
workdays?
d. Also find what expected completion time will ensure a 90% chance
of completing the
project in 120 workdays?
a. Develop a report that presents a planned schedule and
expected project completion time in
workdays. Include a project network in your report using MS
Project.
Expected project completion time(te) is calculated using the
formula te=(to+4*tm+tp)/6 where to is optimistic time, tp is
pesimistic time and tm is most likely time.
Example: For activity id 1(that is activity A), to=8, tm=10, tp=12. Hence te=(to+4*tm+tp)/6 = (8+4*10+12)/6 = 10 workdays.
Project network diagram generated from MS project is shown below:
The red coloured tasks shows
the critical tasks, which gives the critical path with the longest
working time to complete the project. The expected project
completion time is therefore the sum of the expected workdays along
the critical path A-B-C-E-I-J-K-N-O-P.
Total completion time = 10+10+14+8+14+22+12+14+12+6 = 122 workdays.
b. Explain how does this project compared to the average
project. The average duration for a
construction of a villa project normally takes 120
workdays.
Along the critical path, the project takes an estimated total time of 122 workdays. But the average duration of a villa project is usually 120 workdays. This means that this project lags behind the average duration for completing a villa project, and takes extra 2 workdays.
c. Find the probability of finishing this project in 120
workdays?
where sd=standard deviation of critical path, x = 120 workdays(as given in question) , and
mean is the sum of all mean time estimates(te) along the critical path.
Therefore,
Now, from the cumulative distribution table, we can get the probability corresponding to the calculated z-value.
For z-value -0.17, the probability is 0.4325.
Hence, there is 43.25% probability of finishing
this project in 120 workdays.
d. Also find what expected completion time will ensure a
90% chance of completing the
project in 120 workdays?
From the cumulative distribution table, for a probability value of 0.90 , the corresponding z-value is 1.281551.
? ,
where
Substituting the values in the formula, we get
Hence, to ensure a 90% chance of completing the project in 120 workdays, the expected completion time is 105.47 workdays.
a. Develop a report that presents a planned schedule and expected project completion time in workdays....
6:20 all 4G Done Project Management (0307530) Project Management (03753 Assignment No. 2/Fall 2019-220 Dee Date: Wednesday 6/11/2019 ( Total Raw Paints 20 Objective: This assignment is intended to provide you with an opportunity o e scheduling network analysis techniques using CPM and PERT.Ih sllaborations.of ans kindwill.nteeleatel dge and skils in id igmentand Examine the Sollewing table of activities, with stochastic (peobabilistic) dution estimates and predecessoe information (duration estimates are in eck) for a small peoject AtyOpin M yPi Predeo...
Project management
Zeus Project-A You are Donald Tuck, the project manager in charge of the Zeus project. Zeus was the code name given to the development of a virtual electronic medical reference guide. Zeus would be designed for emergency medical technicians and paramedics who need a quick reference guide to use in emergency situations, even in offline mode. Donald and his project team were developing a project plan aimed at producing 30 working models in time for InterMedCON 2018, the...
EX16 XL _CH01_GRADER ML2 HW - Real Estate Sales Report 1.3 Project Description: You own a small real estate company in Indianapolis. You track the real estate properties you list for dlients. You want to analyze sales for selected properties. Yesterday, you prepared a workbook with a worksheet for recent sales data and another worksheet listing several properties you listed. You want to calculate the number of days that the houses were on the market and their sales percentage of...
High-End Lifts uses a volume-based, plant-wide approach to
allocating overhead. They use direct-labor hours as the cost driver
for determining the budgeted rate. You will need to derive the
predetermined overhead rate for them. First few images are
information for the actual problems. Please help!!
Challenge 2: Job-Order Costing for Customized Work Based on your advice, High-End Lifts has moved forward and set up the production process to build all of its residential elevators in- house. In the past, High-End...