Question

Table 1. Network information Activitv Description Immediate Predecessor Arrange financing Let Subcontracts Set and pour foundations Plumbin Framin Roofin Electrical wirin Installation of windows and doors Ductwork and insulation Sheetrock, paneling, an Installation of cabinets Brickin Outside trim Inside trim (including fixtures Paintin Floorin D.I F,G,H.J F.G,H.J hanging ?.? Table 2. Activity times in workdays Most Likelv 10 10 14 10 Activity Optimistic Pessimistic 12 16 18 12 12 24 12 4 10 10 10 10 20 18 24 16 27 24 18 14 12 25 10 14 12 23 10 10 4

a. Develop a report that presents a planned schedule and expected project completion time in
workdays. Include a project network in your report using MS Project.
b. Explain how does this project compared to the average project. The average duration for a
construction of a villa project normally takes 120 workdays.
c. Find the probability of finishing this project in 120 workdays?
d. Also find what expected completion time will ensure a 90% chance of completing the
project in 120 workdays?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

a. Develop a report that presents a planned schedule and expected project completion time in
workdays. Include a project network in your report using MS Project.

Expected project completion time(te) is calculated using the formula te=(to+4*tm+tp)/6 where to is optimistic time, tp is pesimistic time and tm is most likely time.

Example: For activity id 1(that is activity A), to=8, tm=10, tp=12. Hence te=(to+4*tm+tp)/6 = (8+4*10+12)/6 = 10 workdays.

Optimi Most Pessi ID Activity stic likelymistic estimate time timete- (to 4tm +tp)/6 10 20 2 10 10

Project network diagram generated from MS project is shown below:

15 13 16 9 4 14 15 10The red coloured tasks shows the critical tasks, which gives the critical path with the longest working time to complete the project. The expected project completion time is therefore the sum of the expected workdays along the critical path A-B-C-E-I-J-K-N-O-P.

Total completion time = 10+10+14+8+14+22+12+14+12+6 = 122 workdays.

b. Explain how does this project compared to the average project. The average duration for a
construction of a villa project normally takes 120 workdays.

Along the critical path, the project takes an estimated total time of 122 workdays. But the average duration of a villa project is usually 120 workdays. This means that this project lags behind the average duration for completing a villa project, and takes extra 2 workdays.


c. Find the probability of finishing this project in 120 workdays?

= (x-mean) / sd

where sd=standard deviation of critical path, x = 120 workdays(as given in question) , and

mean is the sum of all mean time estimates(te) along the critical path.

Therefore,

  • mean = 122 workdays
  • sd = 0.67+2+1.33+1.33+1.33+0.67+1.33+1.33+0.67+0.67 = 11.333
  • x = 120 workdays.

( 120-122)/11 . 333ー-0.17647

Now, from the cumulative distribution table, we can get the probability corresponding to the calculated z-value.

TABLE A.2 Cumulative normal distribution (z table) z 0.00 0.01 0.02 0.0 0.04 0.05 0.06 0.07 0.08 0.09 3.6 .0002 0002 .000 000

For z-value -0.17, the probability is 0.4325.

Hence, there is 43.25% probability of finishing this project in 120 workdays.

d. Also find what expected completion time will ensure a 90% chance of completing the
project in 120 workdays?

From the cumulative distribution table, for a probability value of 0.90 , the corresponding z-value is 1.281551.

= (x-mean) / sd? , where

  • Mean is the expected completion time which is unknown
  • x = 120 workdays (given)
  • sd = 0.67+2+1.33+1.33+1.33+0.67+1.33+1.33+0.67+0.67 = 11.333

Substituting the values in the formula, we get

1.2815 = (120-mean)/11,333

mean - 120-1.2815 11.333-105.477

Hence, to ensure a 90% chance of completing the project in 120 workdays, the expected completion time is 105.47 workdays.

Add a comment
Know the answer?
Add Answer to:
a. Develop a report that presents a planned schedule and expected project completion time in workdays....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 6:20 all 4G Done Project Management (0307530) Project Management (03753 Assignment No. 2/Fall 2019-220 Dee Date:...

    6:20 all 4G Done Project Management (0307530) Project Management (03753 Assignment No. 2/Fall 2019-220 Dee Date: Wednesday 6/11/2019 ( Total Raw Paints 20 Objective: This assignment is intended to provide you with an opportunity o e scheduling network analysis techniques using CPM and PERT.Ih sllaborations.of ans kindwill.nteeleatel dge and skils in id igmentand Examine the Sollewing table of activities, with stochastic (peobabilistic) dution estimates and predecessoe information (duration estimates are in eck) for a small peoject AtyOpin M yPi Predeo...

  • Project management Zeus Project-A You are Donald Tuck, the project manager in charge of the Zeus...

    Project management Zeus Project-A You are Donald Tuck, the project manager in charge of the Zeus project. Zeus was the code name given to the development of a virtual electronic medical reference guide. Zeus would be designed for emergency medical technicians and paramedics who need a quick reference guide to use in emergency situations, even in offline mode. Donald and his project team were developing a project plan aimed at producing 30 working models in time for InterMedCON 2018, the...

  • EX16 XL _CH01_GRADER ML2 HW - Real Estate Sales Report 1.3 Project Description: You own a...

    EX16 XL _CH01_GRADER ML2 HW - Real Estate Sales Report 1.3 Project Description: You own a small real estate company in Indianapolis. You track the real estate properties you list for dlients. You want to analyze sales for selected properties. Yesterday, you prepared a workbook with a worksheet for recent sales data and another worksheet listing several properties you listed. You want to calculate the number of days that the houses were on the market and their sales percentage of...

  • High-End Lifts uses a volume-based, plant-wide approach to allocating overhead. They use direct-labor hours as the...

    High-End Lifts uses a volume-based, plant-wide approach to allocating overhead. They use direct-labor hours as the cost driver for determining the budgeted rate. You will need to derive the predetermined overhead rate for them. First few images are information for the actual problems. Please help!! Challenge 2: Job-Order Costing for Customized Work Based on your advice, High-End Lifts has moved forward and set up the production process to build all of its residential elevators in- house. In the past, High-End...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT