Question

Problem 9-14 Given the following activity times in months, determine the items listed below: Time Estimates (months) Activity
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer a, b, c and d

Answer a Answer b Answer c Answer d
Activity Optimistic time-a Expected completion time-m Pessimistic time-b Expected time= (a+4*m+ b)/6 Variance, (sigma)^2= (b-a/6)^2 Earliest start= Max[earliest finish of preceding activity] Earliest finish= Earliest start + expected time
A 4 8 12 8.00 1.78 0 8.00
B 6 10 15 10.17 2.25 0 10.17
C 2 10 14 9.33 4.00 0 9.33
D 1 4 13 5.00 4.00 8.00 13.00
E 3 6 9 6.00 1.00 8.00 14.00
F 3 6 18 7.50 6.25 10.17 17.67
G 2 8 12 7.67 2.78 9.33 17.00
H 9 15 22 15.17 4.69 17.67 32.83
I 5 12 21 12.33 7.11 17.67 30.00
J 7 20 25 18.67 9.00 13.00 31.67
K 5 6 12 6.83 1.36 30.00 36.83
L 3 8 20 9.17 8.03 36.83 46.00

Note: Chegg's guidelines mandate to solve one question or 1st four subparts of a question at a time. Please post again for remaining questions.

Add a comment
Know the answer?
Add Answer to:
Problem 9-14 Given the following activity times in months, determine the items listed below: Time Estimates...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Activity on arrow construction

    QUESTION 1 The following table provides information about a particular project:ActivityDuration (Days)PrecedingActivityA5_B6_C4AD3AE1AF4EG14D,EH12B,CI2G,H (a)   Represent the project by means of a simple network diagram.        (b)   Prepare in tabular form, an activity schedule showing the following details: Earliest-start, earliest-finish, latest-start, latest-finish and slack times.         (c)   Identify the critical path.                                                               ...

  • 9. Given the following information in the table, construct an activity on the node diagram. Label the critical path as well as the early and late start/finish times and the slack for each activit...

    9. Given the following information in the table, construct an activity on the node diagram. Label the critical path as well as the early and late start/finish times and the slack for each activity. (20 points) Predecessor Duration (Days) Activity A, B C, D F,G 9. Given the following information in the table, construct an activity on the node diagram. Label the critical path as well as the early and late start/finish times and the slack for each activity. (20...

  • Using the information shown in the table below, what is the latest start time for activity E? ACTIVITY Immediate Pred...

    Using the information shown in the table below, what is the latest start time for activity E? ACTIVITY Immediate Predecessor ACTIVITY TIME EARLIEST START EARLIEST FINISH LATEST START LATEST FINISH SLACK A None 2 0 0 2 0 B A 1 2 3 3 4 1 C A 3 2 5 2 5 0 D B 7 3 10 4 11 E B, C 3 5 8 11 F C 5 11 5 11 0 G D ,E, F 4...

  • also needs daves latest start and latest finish: Dave Fletcher was able to determine the activity...

    also needs daves latest start and latest finish: Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for e activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s) C, E D, F Dave's earliest start (ES) and earliest finish (EF) are: Activity ES...

  • Problem 15-8 (Algo) Based on the precedence table below, identify the critical path, earliest start and...

    Problem 15-8 (Algo) Based on the precedence table below, identify the critical path, earliest start and finish, and slack for each task. Activity Duration (Days) Immediate Predecessor none none none KUHIGT mono 00 00 ONTHOOOO D, E G, J, K b. Identify the earliest start and finish, and slack for each task. (Leave no cells blank - be certain to enter "0" wherever required.) Task Earliest Start s+ Start (ES) Earliest Completion (EC) Immediate Predecessors None None None B C...

  • Question 14 Assume that activity F has the following times: Early start time (ES) = 7...

    Question 14 Assume that activity F has the following times: Early start time (ES) = 7 days Early finish time (EF) = 12 days Latest start time (LS) = 15 days Latest finish time (LF) = 20 days If disaster strikes and activity F will take 20 days to complete rather than the original activity duration (assume that it started at the ES time), by how long will the completion of the project be delayed? O a. 20 days b....

  • Problem 5: For the given activity network, if there are 35 days required to complete the...

    Problem 5: For the given activity network, if there are 35 days required to complete the project, find the following Complete the network by filling in ES, LS, EF and LF Earliest start for activities D, E, F, H, G, L, M ill. Earliest finish for activities D, E, F, H,G,L,M Latest start for activities D, E, F, H, G, LM V. Latest finish activities D, E, F.H.GLM vi. Slack/Float time for each activities D, E, F, H, G, LM...

  • Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher...

    Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Time Activity (weeks) А 7 Immediate Predecessor(s) Time Activity (weeks) E 3 F 7 G 11 H 8 Immediate Predecessor(s) B B CE D. B с D 2 3 A A Dave's earliest...

  • 11 The following activity times are given: Determine the following a) Earliest start time b) Earliest...

    11 The following activity times are given: Determine the following a) Earliest start time b) Earliest finish time c) Latest Start Time d) Latest finish time e) Critical Path Activity Completion time( in months) 1-2 5 1-3 6 1-4 2 2-5 3 2-6 1 3-5 3 4-5 0 4-7 2 5-8 9 5-7 5 7-8 4 6-9 7 8-9 3

  • a.) Create project network for activites A thru G b.) Then compute on the network above,...

    a.) Create project network for activites A thru G b.) Then compute on the network above, the correct Activity on Arrow format (AOA), the earliest start, earliest finish, latest start, and latest finish times for project. a n b b Activity C, E E A Activity А 6 B 2 с 8 D 5 E 6 8 8 12 6 3 9 E Immediate Predecessor(s) G 3 3 5 Н 2 2 2 I 5 5 5 J 4 7...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT