11 The following activity times are given:
Determine the following
a) Earliest start time
b) Earliest finish time
c) Latest Start Time
d) Latest finish time
e) Critical Path
Activity Completion time( in months)
1-2 5
1-3 6
1-4 2
2-5 3
2-6 1
3-5 3
4-5 0
4-7 2
5-8 9
5-7 5
7-8 4
6-9 7
8-9 3
Early start, Early Finish, Latest Start and Latest Finish are included in the network diagram as per legend.
There are 2 critical paths with free float(Ff) of zero for all activities
1-3-5-7-8-9
1-3-5-8-9
11 The following activity times are given: Determine the following a) Earliest start time b) Earliest...
Problem 9-14 Given the following activity times in months, determine the items listed below: Time Estimates (months) Activity Activity Predecessor а т 4 12 A B 6 10 15 С 2 10 14 1 D A 4 13 E A 3 F В 3 6 18 G 2 8 12 Н С.Е.F С.Е.F 15 22 I 5 12 21 J D 20 25 K G.I 5 12 L Н.К 3 20 Expected activity times b. Variance times а. c. Earliest...
also needs daves latest start and latest finish: Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for e activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s) C, E D, F Dave's earliest start (ES) and earliest finish (EF) are: Activity ES...
What is the critical path? Start-A-D-G-End O Start-A-D-F-End Start-A-E-G-End O Start-B-E-G-End What is the EF (earliest finish) of activity E? o o ООООО < N N What is the LS (latest start) of activity E? ООООО The list of activities, their times (in weeks), and precedence relationships for a new project are given below. Activity Immediate Predecessor Activity Time A L - L 4 B - 1 2 C - A, B F DL 4 G C, D, E What...
Figure to accompany Table 7.1 Table 7.1 Activity Slack 0 в 1 1 1 Activity Earliest Earliest Latest Time Start Finish Latest Start Finish 2 0 02 2 3 3 4 312 5 12 15 7 3 10 4 35 11 | 11 | 5 11 4 11 15 11 15 1 G 0 Refer to the Figure to accompany Table 7.1. Which one of the following is the critical path? O ACFG ABDG ABEG ACEG
Using the information shown in the table below, what is the latest start time for activity E? ACTIVITY Immediate Predecessor ACTIVITY TIME EARLIEST START EARLIEST FINISH LATEST START LATEST FINISH SLACK A None 2 0 0 2 0 B A 1 2 3 3 4 1 C A 3 2 5 2 5 0 D B 7 3 10 4 11 E B, C 3 5 8 11 F C 5 11 5 11 0 G D ,E, F 4...
Given is a CPM project network diagram as shown below. Activity Start A B C D E F G H End day 0 5 6 9 6 9 8 5 4 0 a) The Project Completion time = days. b) The Earliest Start time, ES, of Activity G = days. c) The Latest Finish time, LF, of Acitivity C = days.. d) The critical activities are = (ex. Fill in answer as: ABCD) End Start
Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Time Activity (weeks) А 7 Immediate Predecessor(s) Time Activity (weeks) E 3 F 7 G 11 H 8 Immediate Predecessor(s) B B CE D. B с D 2 3 A A Dave's earliest...
A. ACFG B. ABEG C. ACEG D. ABDG B 1 D G 4 E 3 С 3 F Activity Time Earliest Start Earliest Finish Latest Finish Latest Start Slack Activity A 2 0 0 2 0 B 1 2 3 3 4 1 C 3 2 5 2 5 0 D 7 3 10 4 11 E 3 5 8 11 3 F 5 11 5 11 0 G 4 11 15 11 15 0 Refer to the figure above....
Given is a CPM project network diagram as shown below. A F Start E H End B D G Start H Activity day А 6 B 3 с 8 D 7 E 4 F 9 G 4 End 0 0 6 a) The Project Completion time = days. b) The Earliest Start time, ES, of Activity G - days. c) The Latest Finish time, LF, of Acitivity - dayy d) The critical activities are (ex. Fill in answer as: ABCD)
Please help fill in the green boxes given the earliest start time. I am unsure if B would start on week 2 or week 3. Earliest Start Earliest Finish Latest Start Latest Finish Slack ON 11 Activity 12 A 13 B 14c 15 D 16 E 17 F 18 G 19 H NON 26 Budgeted Budgeted Cost/Week Total Cost OS 11,000 $ 22,000 13,000 $ 39,000 12,000 $ 48,000 10,000 $ 40,000 11,000 $ 33,000 15,000 $ 75,000 9,000 $...