Question

11 The following activity times are given: Determine the following a) Earliest start time b) Earliest...

11 The following activity times are given:
Determine the following
a) Earliest start time
b) Earliest finish time
c) Latest Start Time
d) Latest finish time
e) Critical Path
Activity Completion time( in months)
1-2 5
1-3 6
1-4 2
2-5 3
2-6 1
3-5 3
4-5 0
4-7 2
5-8 9
5-7 5
7-8 4
6-9 7
8-9 3

0 0
Add a comment Improve this question Transcribed image text
Answer #1

E-Start Activit) E-finish L-start duration L. Finish ff free float 52.66 131 141 011-25 1156 fe=1 [52-518 16139 ff=1 616-913

Early start, Early Finish, Latest Start and Latest Finish are included in the network diagram as per legend.

There are 2 critical paths with free float(Ff) of zero for all activities

1-3-5-7-8-9

1-3-5-8-9

Add a comment
Know the answer?
Add Answer to:
11 The following activity times are given: Determine the following a) Earliest start time b) Earliest...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT