Question

B 1 D G 4 E 3 С 3 F Activity Time Earliest Start Earliest Finish Latest Finish Latest Start Slack Activity A 2 0 0 2 0 B 1 2

A. ACFG

B. ABEG

C. ACEG

D. ABDG

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Activity Time 2 Earliest Start Latest Start Slack 0 0 0 1 1 Activity A B с D E F 3 2 4 Earliest Finish 2 3 5 10 8 11 15 3 7 3

The critical path is constituted by activities with zero slack.

From the table, the zero-slack activities are A, C, F, and G.

So,

The critical path is ACFG

Add a comment
Know the answer?
Add Answer to:
A. ACFG B. ABEG C. ACEG D. ABDG B 1 D G 4 E 3 С...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Figure to accompany Table 7.1 Table 7.1 Activity Slack 0 в 1 1 1 Activity Earliest...

    Figure to accompany Table 7.1 Table 7.1 Activity Slack 0 в 1 1 1 Activity Earliest Earliest Latest Time Start Finish Latest Start Finish 2 0 02 2 3 3 4 312 5 12 15 7 3 10 4 35 11 | 11 | 5 11 4 11 15 11 15 1 G 0 Refer to the Figure to accompany Table 7.1. Which one of the following is the critical path? O ACFG ABDG ABEG ACEG

  • Using the information shown in the table below, what is the latest start time for activity E? ACTIVITY Immediate Pred...

    Using the information shown in the table below, what is the latest start time for activity E? ACTIVITY Immediate Predecessor ACTIVITY TIME EARLIEST START EARLIEST FINISH LATEST START LATEST FINISH SLACK A None 2 0 0 2 0 B A 1 2 3 3 4 1 C A 3 2 5 2 5 0 D B 7 3 10 4 11 E B, C 3 5 8 11 F C 5 11 5 11 0 G D ,E, F 4...

  • What is the critical path? Start-A-D-G-End O Start-A-D-F-End Start-A-E-G-End O Start-B-E-G-End What is the EF (earliest...

    What is the critical path? Start-A-D-G-End O Start-A-D-F-End Start-A-E-G-End O Start-B-E-G-End What is the EF (earliest finish) of activity E? o o ООООО < N N What is the LS (latest start) of activity E? ООООО The list of activities, their times (in weeks), and precedence relationships for a new project are given below. Activity Immediate Predecessor Activity Time A L - L 4 B - 1 2 C - A, B F DL 4 G C, D, E What...

  • Problem 9-14 Given the following activity times in months, determine the items listed below: Time Estimates...

    Problem 9-14 Given the following activity times in months, determine the items listed below: Time Estimates (months) Activity Activity Predecessor а т 4 12 A B 6 10 15 С 2 10 14 1 D A 4 13 E A 3 F В 3 6 18 G 2 8 12 Н С.Е.F С.Е.F 15 22 I 5 12 21 J D 20 25 K G.I 5 12 L Н.К 3 20 Expected activity times b. Variance times а. c. Earliest...

  • Activity on arrow construction

    QUESTION 1 The following table provides information about a particular project:ActivityDuration (Days)PrecedingActivityA5_B6_C4AD3AE1AF4EG14D,EH12B,CI2G,H (a)   Represent the project by means of a simple network diagram.        (b)   Prepare in tabular form, an activity schedule showing the following details: Earliest-start, earliest-finish, latest-start, latest-finish and slack times.         (c)   Identify the critical path.                                                               ...

  • Please solve the following problems related to Chapter 17: Project Management: 1. Based on the following...

    Please solve the following problems related to Chapter 17: Project Management: 1. Based on the following AOA diagram, please answer the following question: (1) Determine the critical path and the expected project duration (2) Determine the following quantities for each activity: the earliest start time, the latest start time, the earliest finish time and the latest finish time and the slack time. C17) F (5) 1 (61 A(4) D (11) G (3) H(101 B (10) E (12)

  • also needs daves latest start and latest finish: Dave Fletcher was able to determine the activity...

    also needs daves latest start and latest finish: Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for e activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s) C, E D, F Dave's earliest start (ES) and earliest finish (EF) are: Activity ES...

  • QUESTION 5 Given is a CPM project network diagram as shown below. A с F Start...

    QUESTION 5 Given is a CPM project network diagram as shown below. A с F Start E H End B D Start A B E H End Activity day с 7 D 3 F 5 G 6 0 2 4 3 0 a) The Project Completion time = days. b) The Earliest Start time, Es, of Activity G = days. c) The Latest Finish time, LF, of Acitivity C - days. d) The critical activities are (ex. Fill in answer...

  • Consider the following information about a small project: b-1. Identify the critical path. A. A-D-E-F b....

    Consider the following information about a small project: b-1. Identify the critical path. A. A-D-E-F b. A-B-C-F C. A-B-E-F Identify the earliest start and finish, and slack for each task. (Leave no cells blank - be certain to enter "0" wherever required.) c. Which of these activities should the project manager track most closely? A. A-B-E-F b. A-D-E-F c. A-B-C-F Problem 15.6 Task Duration Estimate (in Days) Immediate Predecessors None А B A B and D E and C Earliest...

  • Problem 15-8 (Algo) Based on the precedence table below, identify the critical path, earliest start and...

    Problem 15-8 (Algo) Based on the precedence table below, identify the critical path, earliest start and finish, and slack for each task. Activity Duration (Days) Immediate Predecessor none none none KUHIGT mono 00 00 ONTHOOOO D, E G, J, K b. Identify the earliest start and finish, and slack for each task. (Leave no cells blank - be certain to enter "0" wherever required.) Task Earliest Start s+ Start (ES) Earliest Completion (EC) Immediate Predecessors None None None B C...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT