Question

Figure to accompany Table 7.1 Table 7.1 Activity Slack 0 в 1 1 1 Activity Earliest Earliest Latest Time Start Finish Latest S

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer: ACFG is the critical path

Explanation: Activities on critical path have 0 slack times. And the Activities a, C, F and G have 0 slack.

Therefore, A-C-F-G is a critical path.

Add a comment
Know the answer?
Add Answer to:
Figure to accompany Table 7.1 Table 7.1 Activity Slack 0 в 1 1 1 Activity Earliest...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • A. ACFG B. ABEG C. ACEG D. ABDG B 1 D G 4 E 3 С...

    A. ACFG B. ABEG C. ACEG D. ABDG B 1 D G 4 E 3 С 3 F Activity Time Earliest Start Earliest Finish Latest Finish Latest Start Slack Activity A 2 0 0 2 0 B 1 2 3 3 4 1 C 3 2 5 2 5 0 D 7 3 10 4 11 E 3 5 8 11 3 F 5 11 5 11 0 G 4 11 15 11 15 0 Refer to the figure above....

  • Using the information shown in the table below, what is the latest start time for activity E? ACTIVITY Immediate Pred...

    Using the information shown in the table below, what is the latest start time for activity E? ACTIVITY Immediate Predecessor ACTIVITY TIME EARLIEST START EARLIEST FINISH LATEST START LATEST FINISH SLACK A None 2 0 0 2 0 B A 1 2 3 3 4 1 C A 3 2 5 2 5 0 D B 7 3 10 4 11 E B, C 3 5 8 11 F C 5 11 5 11 0 G D ,E, F 4...

  • 11 The following activity times are given: Determine the following a) Earliest start time b) Earliest...

    11 The following activity times are given: Determine the following a) Earliest start time b) Earliest finish time c) Latest Start Time d) Latest finish time e) Critical Path Activity Completion time( in months) 1-2 5 1-3 6 1-4 2 2-5 3 2-6 1 3-5 3 4-5 0 4-7 2 5-8 9 5-7 5 7-8 4 6-9 7 8-9 3

  • Problem 15-8 (Algo) Based on the precedence table below, identify the critical path, earliest start and...

    Problem 15-8 (Algo) Based on the precedence table below, identify the critical path, earliest start and finish, and slack for each task. Activity Duration (Days) Immediate Predecessor none none none KUHIGT mono 00 00 ONTHOOOO D, E G, J, K b. Identify the earliest start and finish, and slack for each task. (Leave no cells blank - be certain to enter "0" wherever required.) Task Earliest Start s+ Start (ES) Earliest Completion (EC) Immediate Predecessors None None None B C...

  • Activity on arrow construction

    QUESTION 1 The following table provides information about a particular project:ActivityDuration (Days)PrecedingActivityA5_B6_C4AD3AE1AF4EG14D,EH12B,CI2G,H (a)   Represent the project by means of a simple network diagram.        (b)   Prepare in tabular form, an activity schedule showing the following details: Earliest-start, earliest-finish, latest-start, latest-finish and slack times.         (c)   Identify the critical path.                                                               ...

  • Problem 9-14 Given the following activity times in months, determine the items listed below: Time Estimates...

    Problem 9-14 Given the following activity times in months, determine the items listed below: Time Estimates (months) Activity Activity Predecessor а т 4 12 A B 6 10 15 С 2 10 14 1 D A 4 13 E A 3 F В 3 6 18 G 2 8 12 Н С.Е.F С.Е.F 15 22 I 5 12 21 J D 20 25 K G.I 5 12 L Н.К 3 20 Expected activity times b. Variance times а. c. Earliest...

  • Basic Project Management Lesson 6. Exercises 1. The AOA diagram of a project is shown below....

    Basic Project Management Lesson 6. Exercises 1. The AOA diagram of a project is shown below. The duration of each activity in days is shown by its side. a. Calculate the earliest and latest schedules of each event. b. Show the critical path by thickening the critical arrows. c. Fill in the Slack Table. -- a 15 Start Finish 11 13 Slack Table: Task 1-2 1-3 2-3 2-4 Slack TTT 2-5 3-5 | 3-7 | 4-6 5-6 5-7 5-8 6-8...

  • Please solve the following problems related to Chapter 17: Project Management: 1. Based on the following...

    Please solve the following problems related to Chapter 17: Project Management: 1. Based on the following AOA diagram, please answer the following question: (1) Determine the critical path and the expected project duration (2) Determine the following quantities for each activity: the earliest start time, the latest start time, the earliest finish time and the latest finish time and the slack time. C17) F (5) 1 (61 A(4) D (11) G (3) H(101 B (10) E (12)

  • 11. In CPM/PERT, an activity that is on the critical path A. has equal values for...

    11. In CPM/PERT, an activity that is on the critical path A. has equal values for "Latest Start" and "Earliest Start" ( LS = ES ) B. has equal values for "Latest Finish" and "Earliest Finish" ( LF = EF ) C. is used in calculating total project duration D. has slack equal to zero E. all of the above 12. In CPM/PERT, the critical path through the network A. will require the most time of any path B. will...

  • also needs daves latest start and latest finish: Dave Fletcher was able to determine the activity...

    also needs daves latest start and latest finish: Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for e activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s) C, E D, F Dave's earliest start (ES) and earliest finish (EF) are: Activity ES...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT