Using the information shown in the table below, what is the latest start time for activity E?
ACTIVITY | Immediate Predecessor | ACTIVITY TIME | EARLIEST START | EARLIEST FINISH | LATEST START | LATEST FINISH | SLACK |
A | None | 2 | 0 | 0 | 2 | 0 | |
B | A | 1 | 2 | 3 | 3 | 4 | 1 |
C | A | 3 | 2 | 5 | 2 | 5 | 0 |
D | B | 7 | 3 | 10 | 4 | 11 | |
E | B, C | 3 | 5 | 8 | 11 | ||
F | C | 5 | 11 | 5 | 11 | 0 | |
G | D ,E, F | 4 | 11 | 15 | 11 | 15 | 0 |
5
6
8
7
For any activity, the slack is the difference between the earliest finish and earliest start or the latest finish and latest start. For activity E, the earliest finish and earliest start is 8 and 5. Hence the slack is 8-5 is 3. The difference between latest finish and latest start should also be 3. Hence we have 11 - Latest Start = 3. Hence Latest start for E is 11-3 = 8.
Thus the latest start time for activity E is 8.
Using the information shown in the table below, what is the latest start time for activity E? ACTIVITY Immediate Pred...
also needs daves latest start and latest finish: Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for e activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s) C, E D, F Dave's earliest start (ES) and earliest finish (EF) are: Activity ES...
Problem 15-8 (Algo) Based on the precedence table below, identify the critical path, earliest start and finish, and slack for each task. Activity Duration (Days) Immediate Predecessor none none none KUHIGT mono 00 00 ONTHOOOO D, E G, J, K b. Identify the earliest start and finish, and slack for each task. (Leave no cells blank - be certain to enter "0" wherever required.) Task Earliest Start s+ Start (ES) Earliest Completion (EC) Immediate Predecessors None None None B C...
A. ACFG B. ABEG C. ACEG D. ABDG B 1 D G 4 E 3 С 3 F Activity Time Earliest Start Earliest Finish Latest Finish Latest Start Slack Activity A 2 0 0 2 0 B 1 2 3 3 4 1 C 3 2 5 2 5 0 D 7 3 10 4 11 E 3 5 8 11 3 F 5 11 5 11 0 G 4 11 15 11 15 0 Refer to the figure above....
Problem 9-14 Given the following activity times in months, determine the items listed below: Time Estimates (months) Activity Activity Predecessor а т 4 12 A B 6 10 15 С 2 10 14 1 D A 4 13 E A 3 F В 3 6 18 G 2 8 12 Н С.Е.F С.Е.F 15 22 I 5 12 21 J D 20 25 K G.I 5 12 L Н.К 3 20 Expected activity times b. Variance times а. c. Earliest...
11 The following activity times are given: Determine the following a) Earliest start time b) Earliest finish time c) Latest Start Time d) Latest finish time e) Critical Path Activity Completion time( in months) 1-2 5 1-3 6 1-4 2 2-5 3 2-6 1 3-5 3 4-5 0 4-7 2 5-8 9 5-7 5 7-8 4 6-9 7 8-9 3
Activity D is the immediate predecessor of activities K and M. If the latest start time of K is at the end of day 99 and the latest start time of M is at the end of day 106, the latest finish time of D should be at the end of day
What is the critical path? Start-A-D-G-End O Start-A-D-F-End Start-A-E-G-End O Start-B-E-G-End What is the EF (earliest finish) of activity E? o o ООООО < N N What is the LS (latest start) of activity E? ООООО The list of activities, their times (in weeks), and precedence relationships for a new project are given below. Activity Immediate Predecessor Activity Time A L - L 4 B - 1 2 C - A, B F DL 4 G C, D, E What...
The table below defines the activities and the normal time duration for each activities within a small project. You can decrease (crash) the durations at an additional expense. Table 1 summarizes the time-cost information for the activities to complete the project. Table 1: The time-cost information for the activities Activity Normal Completion Time (weeks) Immediate Predecessor Crash Time (weeks) Normal cost for activities Crash cost for activities/week A 2 - 1 1200 400 B 3 - 1 1400 500 C...
Figure to accompany Table 7.1 Table 7.1 Activity Slack 0 в 1 1 1 Activity Earliest Earliest Latest Time Start Finish Latest Start Finish 2 0 02 2 3 3 4 312 5 12 15 7 3 10 4 35 11 | 11 | 5 11 4 11 15 11 15 1 G 0 Refer to the Figure to accompany Table 7.1. Which one of the following is the critical path? O ACFG ABDG ABEG ACEG
QUESTION 1 G E. H. C A Finish Start D. Complete the network activity diagram using the table below to answer questions 1-15. The expected activity completion times are provided in days. Each question is 1 point. Most Probable Activity Optimistic Pessimistic A 7 B 12 C 5 12 7 E 10 15 20 6 9 18 G 6 13 H 11 What is the early start (ES) time for activity F? 13 12 10 None of the above are...