Question

Activity D is the immediate predecessor of activities K and M. If the latest start time of K is at the end of day 99 and the
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Since, activity D is the immediate predecessor of K and M, the latest finish time of D is the minimum among the latest start time of the succeeding activities(Activity K and M).Here latest start time of activities K and M are 99 and 106. So The latest finish time of activity D should be at the end of day 99

Add a comment
Know the answer?
Add Answer to:
Activity D is the immediate predecessor of activities K and M. If the latest start time...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT