Problem 15-7
Consider the following table of precedence relationships for a portion of a house building project:
Task | Duration Estimates |
Immediate Predecessor(s) | ||
A | Prepare Site | 3 | days | None |
B | Install Rough Plumbing | 2 | days | Prepare Site |
C | Pour Concrete Foundation | 3 | days | Install Rough Plumbing |
D | Concrete Curing Time | 4 | days | Pour Concrete Foundation |
E | Preassemble Wall Frames | 6 | days | None |
F | Erect Wall Frames | 2 | days | Preassemble WF, Cure Concrete |
G | Install Roof | 1 | day | Erect Wall Frames |
H | Install Wiring | 6 | days | Install Roof |
I | Install Exterior Siding | 5 | days | Install Roof |
J | Install Insulation | 3 | days | Install Exterior Siding |
K | Hang Drywall | 1 | day | Install Insulation, Install Wiring |
L | Windows | 1 | day | Hang Dry Wall |
M | Paint Interior | 7 | days | Install Windows |
N | Paint Exterior | 3 | days | Install Exterior Siding |
O | Level Yard | 2 | days | Cure Concrete |
P | Landscape Yard | 4 | days | Level Yard |
a-1. Calculate earliest start and finish for each
task. (Leave no cells blank - be certain to enter "0"
wherever required.)
a-2. Calculate slack for every project activity. (Leave no cells blank - be certain to enter "0" wherever required.)
a-3. Identify the critical path..
A-B-C-D-O-P | |
A-B-C-D-F-G-I-J-K-L-M | |
A-B-C-D-F-G-I-N | |
A-B-C-D-F-G-H-K-L-M | |
E-F-G-I-J-K-L-M | |
E-F-G-H-K-L-M | |
E-F-G-H-K-L-M |
c-1. What will happen to the project if the materials needed for the frame preassembly are not available until the second day of the project?
Would delay the start of F | |
Would delay the start of A | |
The project will not be affected |
c-2. What if the materials were delayed until the tenth day?
The project will not be affected | |
Would delay the start of A | |
Would delay the start of F |
CPM refers to critical path method where shortest path is taken to plan the project. The steps in CPM schedule include: -
Problem 15-7 Consider the following table of precedence relationships for a portion of a house building...
F: The activities in the following table describe the construction of a new house. Activity Predecessor(s) Duration(days) A: Clear site B: Bring utilities to site Excavate D: Pour foundation E: Outside plumbing B, C Frame house D G: Do electric wiring H: Lay floor Lay roof F Inside plumbing E, H K: Shingling Outside sheathing insulation F.J M: Install windows and outside doors F Do brick work L, M 0: Insulate walls and ceiling GJ Cover walls and ceiling 0...
Describe the project network to build a house from the data below. Calculate the time and critical path. Activity Description Predecessor Time (Days) A Clear the location - 1 B Bring the tool to the location - 2 C Conducting excavations A 1 D Pour the foundation C 2 E Plumbing installation from outside B, C 6 F Create a home frame D 10 G Installation of electric wire F 3 H Install the floor G 1 I Installing the...
Given all the information in the table, use PERT/CPM to help Mr. Hawthorne address to the following questions. A. Create the network diagram representing the problem. B. What is the total time expected to be required to complete the project if no delays occur? C. What are the earliest and latest start and finish times for the individual activities required to meet the expected project completion time provided in question B (show your method for determining this)? D. Which are...
Scenario: Your organisation, ABC construction group has made a winning bid to construct a new manufacturing plant. The client expects the plant to be functional within a year. You are assigned as the Project Manager to ensure that the whole project stays on schedule. The two important conditions as per the client contract are:- ABC construction group will incur a penalty if the work is not completed by the deadline of 47 weeks from now. ABC construction group will be...
Problem 15-8 (Algo) Based on the precedence table below, identify the critical path, earliest start and finish, and slack for each task. Activity Duration (Days) Immediate Predecessor none none none KUHIGT mono 00 00 ONTHOOOO D, E G, J, K b. Identify the earliest start and finish, and slack for each task. (Leave no cells blank - be certain to enter "0" wherever required.) Task Earliest Start s+ Start (ES) Earliest Completion (EC) Immediate Predecessors None None None B C...
Hello, I need help in the following exercises from book: Project Management: Achieving competitive advantage (4th ed.).Jeffery Pinto Exercise 9.1 Consider the following information that you have compiled re- garding the steps needed to complete a project. You have identi- fied all relevant steps and have made some determinations re- garding predecessor/successor relationships. Using MS Project, develop a simple network diagram for this project, showing the links among the project activities. Activity Predecessors A – Survey site — B –...
Consider the office renovation project data in the following table. A "zero" time estimate means that the activity could take a very small amount of time and should be treated as a numeric zero in the analysis. a. Based on the critical path, find the probability of completing the office renovation project by 38 days. Refer to the standard normal table. (Make sure to round all intermediate calculations for te and variance to two decimal places.) Time Estimates (days) Activity...
can you please answer question 1 and 3 please ABC General Contractors ABC General Contractors was an established construction company handling small-to medium- sized commercial and industrial construction projects. Some recent projects that the company had completed were a 20,000-square-foot factory building, a four-story office building, and a water filtration plant. TELEVISION TOWER BID The company was now in the process of preparing a bid for a television station for the erection of a 225-foot-high television antenna tower and the...
1. Develop a network drawing for Hill Construction and determine the critical path. How long is the project expected to take? 2. What is the probability of finishing in 270 days? 3. If it is necessary to crash to 250 or 240 days, how would Hill do so, and at what costs? As noted in the case, assume that optimistic time estimates can be used as crash times. Southwestern University: (A)* Southwestern University (SWU), a large state college in Stephenville,...
Chapter 3 – Program Management Case Study Minnesota State University (MSU), a large state college in Mankato, Minnesota, 30 miles southwest of the Dallas/Fort Worth metroplex, enrolls close to 15,000 students. In a typical town–gown relationship, the school is a dominant force in the small city, with more students during fall and spring than permanent residents. A longtime Division II football powerhouse, MSU is a member of the Northern Sun Intercollegiate conference and is usually in the top 20 in...