Question

Scenario: Your organisation, ABC construction group has made a winning bid to construct a new manufacturing...

Scenario: Your organisation, ABC construction group has made a winning bid to construct a new manufacturing plant. The client expects the plant to be functional within a year. You are assigned as the Project Manager to ensure that the whole project stays on schedule. The two important conditions as per the client contract are:-

  • ABC construction group will incur a penalty if the work is not completed by the deadline of 47 weeks from now.
  • ABC construction group will be provided additional incentive if the work is completed within 40 weeks.

The table below describes the activity list for ABC construction group for this project:-

Activity

Description

Immediate predecessors

Estimated duration

A

B

C

D

E

F

G

H

I

J

K

L

M

N

Excavate

Lay the foundation

Put up rough wall

Put up the roof

Install exterior plumbing

Install interior plumbing

Put up exterior siding

Do exterior painting

Do the electric work

Put the wallboard

Install the flooring

Interior painting

Exterior fixtures

Interior fixtures

-

A

B

C

C

E

D

E,G

C

F,I

J

J

H

K,L

2 weeks

4 weeks

10 weeks

6 weeks

4 weeks

5 weeks

7 weeks

9 weeks

7 weeks

8 weeks

4 weeks

5 weeks

2 weeks

6 weeks

(Source: - Turner, 2016)

For any given activity, its immediate predecessors (as given in the third column of Table) are those activities that must be completed by no later than the starting time of the given activity. (Similarly, the given activity is called an immediate successor of each of its immediate predecessors.) For example, the top entries in this column indicate that:-

  • Excavation does not need to wait for any other activities.
  • Excavation must be completed before starting to lay the foundation.
  • The foundation must be completely laid before starting to put up the rough wall, etc.

When a given activity has more than one immediate predecessor, all must be finished before the activity can begin. In order to schedule the activities, you have consulted with each of the crew supervisors to develop an estimate of how long each activity should take when it is done in the normal way. These estimates are given in the rightmost column of Table. Adding up these times gives a grand total of 79 weeks, which is far beyond the deadline for the project. Fortunately, some of the activities can be done in parallel, which substantially reduces the project completion time.

Given all this information, please develop answers to the following questions:-

  1. Develop a project network diagram to visually display the whole project and describe the project network diagram– [10 Marks]
  2. Schedule the whole project with PERT/CPM. In doing so, you must be able to satisfy these crucial objectives:-
  • Total time required to complete the project if no delays occur
  • The start and finish of individual activities to meet the project completion deadline
  • The start and finish of individual activities if no delays occur
  • Critical activities where any delays must be avoided to prevent delaying project completion
  • The delay that can be tolerated for other activities, without delaying project completion.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answear Summatized the information provided in the question, your organisation , ABC construction group has made a winning bian Activity duration is shown in circle @ along with the activity code. - In the forward pars early start and eadly finish is3 • Critical activities where any delay, must be avoided to prevent delaying project completion are A, B, C, E, F, J, Lin shoEstimated Duration (weeks) 2 Early Start Early Finish Late Start Late Total Finish Float (TF) А 0 0 2 6 2 4 10 2 6 lolo B 6 1................................................................................XXXX...................................................................

PLEASE - - - - PLEASE KINDLY UP-VOTE. IT HELPS ME A LOT. THANK YOU IN ADVANCE.

Add a comment
Know the answer?
Add Answer to:
Scenario: Your organisation, ABC construction group has made a winning bid to construct a new manufacturing...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Given all the information in the table, use PERT/CPM to help Mr. Hawthorne address to the...

    Given all the information in the table, use PERT/CPM to help Mr. Hawthorne address to the following questions. A. Create the network diagram representing the problem. B. What is the total time expected to be required to complete the project if no delays occur? C. What are the earliest and latest start and finish times for the individual activities required to meet the expected project completion time provided in question B (show your method for determining this)? D. Which are...

  • F: The activities in the following table describe the construction of a new house. Activity Predecessor(s)...

    F: The activities in the following table describe the construction of a new house. Activity Predecessor(s) Duration(days) A: Clear site B: Bring utilities to site Excavate D: Pour foundation E: Outside plumbing B, C Frame house D G: Do electric wiring H: Lay floor Lay roof F Inside plumbing E, H K: Shingling Outside sheathing insulation F.J M: Install windows and outside doors F Do brick work L, M 0: Insulate walls and ceiling GJ Cover walls and ceiling 0...

  • 2. Can the project be completed before construction can begin, which is scheduled 40 weeks later?...

    2. Can the project be completed before construction can begin, which is scheduled 40 weeks later? a. Yes, because the project duration time is 39 weeks. b. No, because the project duration time is 41 weeks. c. No, because the project duration time is 42 weeks. d. Yes, because the project duration time is 40 weeks. 3. Which activities can be delayed without delaying the projection completion time? a. B, D and F b. B, D and G c. A,...

  • question 3.12 Chapter 3 Project Management 91 Table for 3.8 Time Activity Immediate Code Description in...

    question 3.12 Chapter 3 Project Management 91 Table for 3.8 Time Activity Immediate Code Description in hours) Predecesur Planning Find location determine resource requirements Purchasing Requisition of lumber and sand Excavation Planning Dig and grade Sawing Planning Saw lumber inte appropriate sizes Placement Purchasing Position lumber in comect locations Sawing. c om Assembly Nail lamber together Placement Tafill Put sand in and under the equipment Ambly Outfill Put dirt a nd the equipment Assembly Decoration Put grass all over the...

  • Office Automation Inc., has developed a proposal for introducing a new computerized office system that will...

    Office Automation Inc., has developed a proposal for introducing a new computerized office system that will improve word processing and interoffice communications for a particular company. Contained in the proposal is a list of activities that must be accomplished in order to complete the new office system project. Information about the activities is shown in the table below. Times are in weeks. Data for Office Automation, Inc. Activity Description Immediate Predecessors Normal Time Crash Time Normal Cost ($) Crash Cost...

  • Orleans Construction Company Case (adapted from Meredith and Mantel) The Orleans Construction Company, a small construction...

    Orleans Construction Company Case (adapted from Meredith and Mantel) The Orleans Construction Company, a small construction company in North Carolina, has been awarded a contract for the construction of a new 25,000 soccer stadium at Greensboro. The City is hoping to use this facility to attract a new soccer franchise. The construction cannot start earlier than March 2, 2020 (because of the availability of bond funds) and must be completed within 1 year (52 weeks). A penalty clause of $13,000...

  • You have recently been hired to help with planning for a music festival in Sydney, Australia...

    You have recently been hired to help with planning for a music festival in Sydney, Australia planned for late December 2020. Much still needs to be done in order for the event to go ahead. As the project manager working with the city, you are tasked with determining whether it is feasible to put on the event by the proposed date. The following activities would have to be undertaken before the festivities. Immediate Predecessor Activity A B С D E...

  • can you please answer question 1 and 3 please ABC General Contractors ABC General Contractors was...

    can you please answer question 1 and 3 please ABC General Contractors ABC General Contractors was an established construction company handling small-to medium- sized commercial and industrial construction projects. Some recent projects that the company had completed were a 20,000-square-foot factory building, a four-story office building, and a water filtration plant. TELEVISION TOWER BID The company was now in the process of preparing a bid for a television station for the erection of a 225-foot-high television antenna tower and the...

  • You have recently been hired to help with planning for a music festival in Sydney, Australia...

    You have recently been hired to help with planning for a music festival in Sydney, Australia planned for late December 2020. Much still needs to be done in order for the event to go ahead. As the project manager working with the city, you are tasked with determining whether it is feasible to put on the event by the proposed date. The following activities would have to be undertaken before the festivities. Activity A B C D E F G...

  • Choose an event or significant task and prepare an activities list following a format similar to...

    Choose an event or significant task and prepare an activities list following a format similar to that used in the text, Table 9.3, Chapter 9, page 391. Be sure to include the immediate predecessors. Then, create a project network similar to that shown in Figure 9.7, Chapter 9, page 392. Do NOT include times for the activities and do NOT attempt to determine the critical path. Examples of events you might consider (there are many others): formal dinner for 5...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT