Your Assignment is to Create a Project Schedule in MS Project.
Amir’s Sheds is a successful franchise in the home building industry. Amir’s Sheds build specific purpose sheds for home gardens, farms and industrial storage facilities.
The project starts on Monday, June 3, 2019
WBS for Building a Shed
Task ID |
Task Description |
Predecessor |
Time |
Resources (people and materials required to complete the task) |
2 |
Preparation phase |
|||
3 |
Design Shed |
3 days |
Designer |
|
4 |
Obtain council approvals |
3 |
14 days |
Project manager to submit engineering, design specifications and construction certificates |
5 |
Sign Contract |
4\ |
1 days |
Project manager |
6 |
Construction Phase |
|||
7 |
Check existing boundaries |
5 |
1 day |
Surveyor, |
8 |
Check underground cable locations |
5 |
1 day |
Project manager to contact utilities |
9 |
Establish site services and amenities |
5 |
2 days |
Fence construction team (2), electrician, plumber, require hired toilet, fencing materials |
10 |
Excavate site |
7,8,9 |
3 days |
Excavation team |
11 |
Pour Concrete and wait for it to set |
10 |
2 days day |
Construction team |
12 |
Install Shed |
11 |
2 days |
Construction team |
13 |
Completion Phase |
|||
14 |
Connect utilities to shed |
12 |
2 days |
Electrician, Plumber |
15 |
Clean up site |
12 |
3 days |
Construction team |
16 |
Hand over keys and warranties |
14,15 |
1 day |
Project Manager |
17 |
Final Payment |
16 |
0 days |
Amir’s Sheds is a successful franchise in the home building industry. Amir’s Sheds build specific purpose sheds for home gardens, farms and industrial storage facilities.
Project schedule-Gantt Chart
Your Assignment is to Create a Project Schedule in MS Project. You are to Create a...
2. Prepare a project schedule for Infotech software company. Assign the relevant resource Name and project Starts Calculate the total duration of the project: InfoTech software development company to develop the software by the following task and subtask all the events are linear form. 5/7/2019 on 2. System Design 1.Software Requirement Specification Database Design (3 days) Detailed Design (2 days) Architectural Design (2 days) Requirement gathering (1 day) (3 days) (2 days) (2 days) Data collection Cost Analysis Risk Analysis...
You are the project manager's assistant on a construction site. The project manager is off site for the day and you are responsible for the ongoing progress of the site in her absence. Two similar beams are delivered to a construction site. Each beam is a hollow box beam, constructed of A36 structural steel, (E=29.0 x 10ʻpsi, density of 490 1bm/ft), each beam having outside dimensions of 16" base and 18" height, 18 feet long. Beam A has top and...
Project Schedules and Scheduling Tools In this assignment, you will create a schedule for the month of December of this year for your team members—John, Sally, Pedro, and Eunice. While creating the schedule, keep in mind the following conditions: Every employee in the company needs to work for 45 hours per week. John works from Saturdays to Wednesdays in the 6:00 a.m. to 4:00 p.m. shift, with a 1-hour lunch break. Sally works from Mondays to Thursdays in the 3:00...
You are the project manager's assistant on a construction site. The project manager is off site for the day and you are responsible for the ongoing progress of the site in her absence. Two similar beams are delivered to a construction site. Each beam is a hollow box beam, constructed of A36 structural steel, (E=29.0 x 106 psi, density of 490 lbm/ft?), each beam having outside dimensions of 16" base and 18" height, 18 feet long. Beam A has top...
You are the project manager's assistant on a construction site. The project manager is off site for the day and you are responsible for the ongoing progress of the site in her absence. Two similar beams are delivered to a construction site. Each beam is a hollow box beam, constructed of A36 structural steel, (E=29.0 x 106 psi, density of 490 lbm/ft?), each beam having outside dimensions of 16" base and 18" height, 18 feet long. Beam A has top...
(----Project Management----) Node diagram and an estimated cost The project consists of a 10-story building with 100 lamps per floor. The floors are completed in ascending order, and only when the floor is completed can the next one begin. Its brigade consists of experts and electrical assistants with the following characteristics: 1) Costs: Electrician expert ($ 16 / hour) 2)Electrician expert assistant ($ 10 / hour) Production: An electrician expert with an electrician expert assistant can install: Perito installs 16...
You just completed developing the schedule for your project and got the approval from stakeholders and the sponsor. One of the team members assigned to work on a critical component informs you that she needs additional time to complete her activities as several relevant pieces were missed during planning. Her updated estimate would have no impact on the critical path; thus, the project duration would be the same. The best approach the project manager may take in this situation will...
Your schedule has a critical path of tasks A-D-E-F. A team member tells you that task B, which was originally planned to take 6 days with 5 days of float, has been re-estimated to take 9 days. What effect would you expect this to have on the schedule? Select one: a. Task B would have 1 day of lag b. The project completion date would be increased by 3 days. c. Task B is now part of the critical path...
Create a Gantt Chart for the following project, and show the Gantt Chart below. Set a start date of January 6, 2020. Assume that work can be done 5 days per week. Identify the Critical Path. When will the project be completed? Create a Gantt Chart for the following project, and show the Gantt Chart below. Set a start date of January 6, 2020. Assume that work can be done 5 days per week. Identify the Critical Path. When will...
Match the type of schedule listed with the description following. Schedule types may be used more than once a. Activity on arrow (AOA) b. Activity on node (AON) C. Matrix d. Bar chart 40 Graphically the simplest Graphic style makes it adaptable to high-rise construction 42.Utilizes i-j notation 43 Could also be termed precedent notation Would be used for a summary report to the owner Questions 45-49 Match the terms listed with their description. Terms may be used only once...