Question

Your schedule has a critical path of tasks A-D-E-F. A team member tells you that task B, which was originally planned to take 6 days with 5 days of float, has been re-estimated to take 9 days. What ef...

Your schedule has a critical path of tasks A-D-E-F. A team member tells you that task B, which was originally planned to take 6 days with 5 days of float, has been re-estimated to take 9 days. What effect would you expect this to have on the schedule?

Select one:

a. Task B would have 1 day of lag

b. The project completion date would be increased by 3 days.

c. Task B is now part of the critical path

d. The critical path would still be A-D-E-F

0 0
Add a comment Improve this question Transcribed image text
Answer #1

סד.tol duraton 6dadA а чл 9 day, complete So t oill not effeet the cntical Patn CS Scanned with CamScanner

Add a comment
Know the answer?
Add Answer to:
Your schedule has a critical path of tasks A-D-E-F. A team member tells you that task B, which was originally planned to take 6 days with 5 days of float, has been re-estimated to take 9 days. What ef...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Consider the following information about a small project: b-1. Identify the critical path. A. A-D-E-F b....

    Consider the following information about a small project: b-1. Identify the critical path. A. A-D-E-F b. A-B-C-F C. A-B-E-F Identify the earliest start and finish, and slack for each task. (Leave no cells blank - be certain to enter "0" wherever required.) c. Which of these activities should the project manager track most closely? A. A-B-E-F b. A-D-E-F c. A-B-C-F Problem 15.6 Task Duration Estimate (in Days) Immediate Predecessors None А B A B and D E and C Earliest...

  • A=8 B=6 E=5 G=4 C=7 F=9 D=7 The following activities are part of a project to...

    A=8 B=6 E=5 G=4 C=7 F=9 D=7 The following activities are part of a project to be scheduled using CPM. Determine the critical Path. How many weeks will it take to complete the project? Suppose F could be shortened by two weeks and B by one week. How would this affect the completion date? OBJECTIVE QUESTION 14 The following activities are part of a project to be scheduled using CPM. B-6 A-8 G-4 D-7 E-5 F-9 a. Determine the critical...

  • Question #1: Some of the tasks in this project can be done in parallel. Prepare a...

    Question #1: Some of the tasks in this project can be done in parallel. Prepare a diagram showing the required network of tasks and define the critical path. What is the length of the project without crashing? Do not just answer, but show the whole process. Question #2: If the critical path is longer than 29 days, what is the least additional amounting that Dr. Watage can spend and still achieve this schedule objective (29 days)? Do not just answer,...

  • Case #2 Table 2 Family Planning Research Center Costs Activity A В. Crash Time (days) 3...

    Case #2 Table 2 Family Planning Research Center Costs Activity A В. Crash Time (days) 3 4 2 1 3 Normal Time (days) 6 8 4 3 7 5 3 6 7 10 10 Dr. John Watage, deputy director of the family planning Research Center in Nigeria's Over-The-River Providence, was assigned the task of organizing and training five teams of field workers to perform educational and outreach activities as part of a large project to demonstrate acceptance of a new...

  • Dr. John Watage, deputy director of the family planning Research Center in Nigeria’s Over-The-River Providence, was...

    Dr. John Watage, deputy director of the family planning Research Center in Nigeria’s Over-The-River Providence, was assigned the task of organizing and training five teams of field workers to perform educational and outreach activities as part of a large project to demonstrate acceptance of a new method of birth control.  These workers already had training in family planning education but must receive specific training regarding the new method of contraception.  Two types of materials must also be prepared: (1) those for use...

  • Dr. John Watage, deputy director of the family planning Research Center in Nigeria’s Over-The-River Providence, was...

    Dr. John Watage, deputy director of the family planning Research Center in Nigeria’s Over-The-River Providence, was assigned the task of organizing and training five teams of field workers to perform educational and outreach activities as part of a large project to demonstrate acceptance of a new method of birth control. These workers already had training in family planning education but must receive specific training regarding the new method of contraception. Two types of materials must also be prepared: (1) those...

  • The Forest In Your Mouth B Y E D Y O N G P U B...

    The Forest In Your Mouth B Y E D Y O N G P U B L I S H E D J A N U A R Y 2 5 , 2 0 1 6 T H E S T U DY O F the human microbiome—the booming and much-hyped quest to understand the microbes that share our bodies—began in the mouth. Specifically, it began with dental plaque. In 1683, Antony van Leeuwenhoek, the first human ever to see...

  • What an Executive Summary Is An executive summary is a specific type of document that does...

    What an Executive Summary Is An executive summary is a specific type of document that does two things: it summarizes a research article, and it offers recommendations as to how information from the article can be used. Some long reports can contain an executive summary section, as indicated in the Pearson handbook. Write a 2 pahe Executive Summary In business contexts, an executive summary is always written for a specific purpose: to explain the information in the article to a...

  • Case Study 12: Hong Kong Police’s Project Management B Chuah Background In the 1990’s, Hong Kong...

    Case Study 12: Hong Kong Police’s Project Management B Chuah Background In the 1990’s, Hong Kong Police (HKP) was responsible for the public safety and internal security of Hong Kong. She came under the umbrella of the Security Bureau of the Government of Hong Kong. It had more than 34,000 employees, of these, over 26,000 were disciplinary staff. This was the largest department within the hierarchy of the Government of Hong Kong. The organization structure of HKP was rather complicated....

  • How can we assess whether a project is a success or a failure? This case presents...

    How can we assess whether a project is a success or a failure? This case presents two phases of a large business transformation project involving the implementation of an ERP system with the aim of creating an integrated company. The case illustrates some of the challenges associated with integration. It also presents the obstacles facing companies that undertake projects involving large information technology projects. Bombardier and Its Environment Joseph-Armand Bombardier was 15 years old when he built his first snowmobile...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT