Question

Question #1: Some of the tasks in this project can be done in parallel. Prepare a diagram showing the required network of tasks and define the critical path. What is the length of the project without crashing? Do not just answer, but show the whole process.

Question #2: If the critical path is longer than 29 days, what is the least additional amounting that Dr. Watage can spend and still achieve this schedule objective (29 days)? Do not just answer, but show the whole process.

Here is the Scenario:

Dr. John Watage, deputy director of the family planning Research Center in Nigeria’s Over-The-River Providence, was assigned the task of organizing and training five teams of field workers to perform educational and outreach activities as part of a large project to demonstrate acceptance of a new method of birth control. These workers already had training in family planning education but must receive specific training regarding the new method of contraception. Two types of materials must also be prepared: (1) those for use in training the workers and (2) those for distribution in the field. Training faculty must be brought in and arrangements made for transportation and accommodations for the participants. Dr. Watage first called a meeting of his office staff. Together they identified the activities that must be carried out, their necessary sequences, and the time that they would require. Their results are displayed in Table 1. Louis Odaga, the chief clerk, noted that their project had to be completed in 29 days. Whipping out his solar-powered calculator, he added up the time needed. “no,” Dr. Watage replied, “some of these tasks can go forward in parallel.” “Be careful, though,” warned Mr. Oglagadu, the chief nurse, “there aren’t that many of us to go around. There are only 12 of us in this office.” “I can check whether we have enough heads and hands once I have tentatively scheduled the activities,” Dr. Watage responded. “If the schedule is too tight, I have permission from the Pathminder Fund to spend some funds to speed it up, just so long as I can prove that it can be done at the least cost necessary. Can you help me prove that? Here are the costs for the activities with the elapsed time that we planned and the costs and times if we shorten them to an absolute minimum.” Those data are given Table 2.

Here are the Tables

Table 1 Family Planning Research Center Activities Activity Immediate Predecessor A. Identify faculty and their schedules B.

Table 2 Family Planning Research Center Costs Activity Normal Time (days) 6 8 4 3 Crash Time (days) 3 4 2 1 A B С D E F G H 7

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Activity Predecessor Time Crash time Cost per day
A - 6 3 3000
B - 8 4 4000
C - 4 2 3000
D A 3 1 2000
E A 7 3 6000
F B,E 5 1 2000
G A,B 3 1 3500
H C 6 4 10000
I H 7 1 7000
J D,F,G,I 10 9 5500
K J 10 5 4500

The activity diagram is given below:

E 7 D A 6 3 B חד | תU J 10 K 10 8 C G 3 4 - Н. 6 7

The different paths with total times are given below:

Path Time
A-E-F-J-K 38
A-D-J-K 29
B-F-J-K 33
B-G-J-K 31
C-H-I-J-K 37

hence path A-E-F-J-K is the critical path taking 38 days

To complete the project in 29 days, we have to reduce 9 days

Critical path is A-E-F-J-K out of which F has least cost

we can reduce cost of activity F by 1 day with cost of 2000

Now both A-E-F-J-K and C-H-I-J-K take 37 days
Common activities are J and K out of which K is the least
We can reduce activity K by 5 days
Cost incurred will be 4500X5 = 22500
Next we can crash activity J by 1 day
Cost incurred will be 5500
Now for both A-E-F-J-K and C-H-I-J-K taking 31 days we need to check which uncommon
activity will have least cost
For A-E-F-J-K we can reduce activity F by 2 days incurring cost of 2000X2 = 4000
For C-H-I-J-K we can reduce activity C by 2 days incurring cost of 3000X2 = 6000

The summary of the movement of total time for all paths is given below when we do the activities listed above:

Activity F Activitiy K Activity J Activity F Activity C
Crash by 1 day 5 days 1 day 2 days 2 days
Path Time
A-E-F-J-K 38 37 32 31 29 29
A-D-J-K 29 29 24 23 23 23
B-F-J-K 33 32 27 26 24 24
B-G-J-K 31 30 25 24 24 24
C-H-I-J-K 37 37 32 31 31 29

Hence total extra cost taken =  2000 + 22500 + 5500 + 4000 + 6000 = 40000

Add a comment
Know the answer?
Add Answer to:
Question #1: Some of the tasks in this project can be done in parallel. Prepare a...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Dr. John Watage, deputy director of the family planning Research Center in Nigeria’s Over-The-River Providence, was...

    Dr. John Watage, deputy director of the family planning Research Center in Nigeria’s Over-The-River Providence, was assigned the task of organizing and training five teams of field workers to perform educational and outreach activities as part of a large project to demonstrate acceptance of a new method of birth control.  These workers already had training in family planning education but must receive specific training regarding the new method of contraception.  Two types of materials must also be prepared: (1) those for use...

  • Dr. John Watage, deputy director of the family planning Research Center in Nigeria’s Over-The-River Providence, was...

    Dr. John Watage, deputy director of the family planning Research Center in Nigeria’s Over-The-River Providence, was assigned the task of organizing and training five teams of field workers to perform educational and outreach activities as part of a large project to demonstrate acceptance of a new method of birth control. These workers already had training in family planning education but must receive specific training regarding the new method of contraception. Two types of materials must also be prepared: (1) those...

  • Case #2 Table 2 Family Planning Research Center Costs Activity A В. Crash Time (days) 3...

    Case #2 Table 2 Family Planning Research Center Costs Activity A В. Crash Time (days) 3 4 2 1 3 Normal Time (days) 6 8 4 3 7 5 3 6 7 10 10 Dr. John Watage, deputy director of the family planning Research Center in Nigeria's Over-The-River Providence, was assigned the task of organizing and training five teams of field workers to perform educational and outreach activities as part of a large project to demonstrate acceptance of a new...

  • 5. Imagine that you are in charge of planning a short course for executives wishing to...

    5. Imagine that you are in charge of planning a short course for executives wishing to upgrade their Operations Research skills. The following list of activities is involved: Cost Per ImmediateNormal DescriptionPredecessors (days) Crash Time (days)Reduction Day of Time Activity A Develop course outline 4 S50 Arrange speakers $100 Identify potential locations $150 Choose location 4 $150 Arrange travel for B, D speakers Final confirmation of $200 eakers Advertise course B, D Take rescrvations Arrange welcome party F, H $100...

  • QUESTION 1 Part1. The total expected project completion time is: A. 10 days B. 11 days...

    QUESTION 1 Part1. The total expected project completion time is: A. 10 days B. 11 days C. 15 days D. none of the above Part 2. What is the effect of a delay of 1 day in distributing tickets? A. no impact B. the project will delay by one day C. the project will delay by more than one day D. same as the effect of a delay of 1 day in setting up radio ads Part 3. What is...

  • QUESTION 1 Your company is planning to implement a construction project in a nearby town. You...

    QUESTION 1 Your company is planning to implement a construction project in a nearby town. You have identified ten (10) activities and their relationship to be carried out in order to complete the project. Table 1 and Figure 1 below show the relationship and the critical path diagram for the project. The duration to complete each activity (days) is stated below the activity. The relationship between activities is 'finish-start with no lag except for the following activities. Table 1: Relationship...

  • You must save 3 days on this project. How can you do so most efficiently? Fill...

    You must save 3 days on this project. How can you do so most efficiently? Fill in the AoA network with the new information in order to save day 1, day 2 and day 3 GIJ 4. Use the following table to complete the rest of the tasks: o) Vack Time Cost 0 Cost Activity Predecessors Normal CrashNormal Crash A,C 10 12 D,E D,E D,E G H 12 a. Draw the AoA network and identify the critical path (the drawing...

  • Can someone walk me through manual steps to solve e, f, and g? The Farmer's American...

    Can someone walk me through manual steps to solve e, f, and g? The Farmer's American Bank of Leesburg is planning to install a new computerized accounts system. Bank management has determined the activities required to complete the project, the precedence relationships of the activities, and activity time estimates, as shown in the following table: Time Estimates (weeks) Activity Activity Activity Description Position recruiting System development Predecessor a C A 5 17 ? -- 7 3 12 15 System training...

  • A manufacturer of personal computers has recently identified time estimates, activities and predecessors to design, manufacture and market a new laptop computer. Their estimates are listed...

    A manufacturer of personal computers has recently identified time estimates, activities and predecessors to design, manufacture and market a new laptop computer. Their estimates are listed below Immediate Activity Description Estimated completion time (days) 90 15 Predecessors Prototype design Purchase of materials Manufacture of prototype Revision of design Initial production run Staff training Staff input on prototype Sales training Preproduction advertising campaign Post production advertising campaign 20 21 25 14 28 30 C,F D,I Management has also provided you with...

  • 1. The activities needed for a new project your company is undertaking are listed in the...

    1. The activities needed for a new project your company is undertaking are listed in the following table. ACTIVITY IMMEDIATE PREDECESSOR(S) A ---- B ---- C A D A, B E B F C, D, E G D, E H F I F, G J G The activity times were determined for the project, and were as below. ACTIVITY ACTIVITY TIME (days) A 11 B 9 C 7 D 12 E 8 F 9 G 10 H 6 I 7...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT