Question

Microsoft Project Assignment Description A system development project has been defined to contain the following list of...

Microsoft Project Assignment Description

A system development project has been defined to contain the following list of activities along with their estimated times for completion. The project will start on 5/1/2019.

Project Data Provided:

Activity ID

Activity Name

Days

Predecessors

Optimistic(O)

Realistic(R)

Pessimistic(P)

1

Gather Requirement

1

2

3

2

Analyze processes

1

2

6

1

3

Define DFDs

0.5

1

1.5

2

4

Design Processes

2

7

12

2

5

Design database

4

7

22

3

6

Design UI

2

4

8

3,4

7

Build Database

3

5

7

4,5

8

Develop Software

4

8

12

6,7

9

Test and document

4

8

12

7

10

Install

1

2

6

8,9

           

Follow each of the following Six steps making use of Project functionality.

Step 1. Create the above project in Microsoft Project and Enter the Tasks (activities) and Predecessors then go to Step 2 to enter the task durations

Step 2. PERT Analysis:

Do the analysis manually to calculate the Expected Time (duration) for each task:

To find the Expected Time (TE) for each task you use the Optimistic(o), Realistic(r) and Pessimistic(p) durations employing the formula TE = (o + 4r + p)/6

TASK

Optimistic (o)

Realistic (r)

Pessimistic (p)

Task 1

2

5

10

Example:  

                              In this case the calculation is:      TE = (2 + 4*(5) + 10) / 6

TE = (2 + 20 + 10) / 6

TE = (32)/6

TE = 6 (note that we take the division “ceiling” value) After calculating each expected time (TE) enter the expected time value as the Duration for each task. Retain your calculations to include in the word file submitted.

Step 3. Within Project - Create a network diagram view for the activities, and save the network diagram view

Step 4. Within Project - Create a detailed Gantt chart view for the project (Covered in “Using Microsoft Project.PDF”), make sure that you:

  1. Highlight the activities that are on the critical path in the Gantt chart.
  2. Highlight the activities that are on the critical path in the task list
  3. Show the total slack time (not free slack time) for each activity in the task list.
  4. Save your detail Gantt view

Step 5. Remove any unnecessary custom view that is not required. Make sure you only have the two custom views that are required for Q3 and Q4 under “Custom” in the drop-down menu list. In other words, leave the built-in views alone (you do not have to worry about them) but make sure you only have two custom or self-defined views: one view for the network diagram for Q3 and one view for the detailed Gantt view for Q4.

Step 6. Answer the following questions based on what you get directly from Microsoft Project 2013. –

Q(1) Having done the PERT analysis manually – capture those calculations in this document.

Q(2) What’s the expected finish date of the project?

Q(3) How many working days does the project take?

Q(4) List the names of activities that are on the critical path?

Q(5) List the total slack time (not free slack time) in working days for each activity that is not on the critical path. You should clearly specify which activity has how much total slack time.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Te (a+4m+b)/6 EF ES + Te LS LF-Te Slack LF EF 5td Devlation LF Calculation Value Calculation Value Calculation Calculation Va

Add a comment
Know the answer?
Add Answer to:
Microsoft Project Assignment Description A system development project has been defined to contain the following list of...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Using the following information about Project A, its activities and predecessor activities below: Activity Predecessors A...

    Using the following information about Project A, its activities and predecessor activities below: Activity Predecessors A в B C D E, F D G The following table contains the pessimistic, likely, and optimistic estimates for how long activities are estimated to take for Project A. Activity Pessimistic Likely Optimistic 2 5 20 H 16 e. Calculate the time estimates (TE) f. Calculate the variance (s) g. Convert the TE to whole integers and place them in the network diagram for...

  • 6. A project has been defined to contain the following list of activities, along with their...

    6. A project has been defined to contain the following list of activities, along with their precedence relations and time and cost estimates for the activity durations. Time estimates (weeks L Cost estimates ($) Activity Predecessor(s) Normal time Crashed time Normal cost Crashed cost 10 9 $6000 $8000 - 85 $1100 $2000 A 7 5 $3000 $3800 B 12 4 $4000 $6000 B 4 2 $5000 $6500 AD 6 3 $2500 $4000 CE $2800 $$3000 a. Draw the Activity-on-node (AON)...

  • Consider the following project activities: Calculate the expected time (te) for each activity. Draw an Activity...

    Consider the following project activities: Calculate the expected time (te) for each activity. Draw an Activity on Node (AON) diagram to reflect the flow of these activities. Calculate the Early Start (ES), Early Finish (EF), Late Start (LS), and Late Finish (LF) for each activity. Calculate the slack for each activity. Identify all activities on the Critical Path. Use the data to calculate the probability the project will finish in 20 weeks (Hint: z-score). Activity A 8 с D E...

  • 1. Sid Orland is involved in planning a scientific research project. The activities are displayed in the following...

    1. Sid Orland is involved in planning a scientific research project. The activities are displayed in the following diagram. Optimistic, most likely, and pessimistic time estimates are displayed in the following table. Figure for Problem 1. r e 14 16 E 4 H 4 7 11 7 11 16 20 G 5 0 33 611 16 11 16 D 3 Most Likely Pessimistic Activity Optimistic 4 4 (a) Determine the expected times and variances for each activity along the critical...

  • A small software development project has eight major activities. The times are estimated and prov...

    A small software development project has eight major activities. The times are estimated and provided in the table below: Activity Optimistic Time Most Likely Time Pessimistic Time Immediate Predecessor(s) A 3 4 5 -- B 5 7 9 -- C 2 3 10 A D 2 5 8 B E 1 7 7 B F 3 5 7 C, D G 7 8 9 D, E H 2 6 10 F Answer the following questions based on above table 1-2...

  • Consider a project having the following six activities:                                  

    Consider a project having the following six activities:                                                      Immediate                                                  Max        Crash cost             Activity                           Predecessors           Time (weeks)             Crash*    per week                   A                                none                                    6                          6                N/A                   B                                none                                    5                          2               $500                   C                                A                                       3                          2             $1000                   D                                A, B                                    4                          2             $2000                   E                                 C, D                                    5                          2             $1250                   F                                D                                       6                          2             $1000                                                                                                 *Shortest possible time for the task 1. Draw the project network and list...

  • Pik-Fast, a chain of convenience stores, is planning to open a new store.  The activities required, their...

    Pik-Fast, a chain of convenience stores, is planning to open a new store.  The activities required, their immediate predecessors, and the optimistic, most likely, and pessimistic estimates of their times (in days) are provided below. Activity Description Immediate Predecessors Optimistic Time (days) Most Likely Time (days) Pessimistic Time (days) TE ES EF LF LS Slack Standard Dev Variance A Select manager -- 10 12 20 13 0 1.67 B Select site -- 8 15 22 15 0 2.33 C Hire workers...

  • Pik-Fast, a chain of convenience stores, is planning to open a new store.  The activities required, their...

    Pik-Fast, a chain of convenience stores, is planning to open a new store.  The activities required, their immediate predecessors, and the optimistic, most likely, and pessimistic estimates of their times (in days) are provided below. Activity Description Immediate Predecessors Optimistic Time (days) Most Likely Time (days) Pessimistic Time (days) TE ES EF LF LS Slack Standard Dev Variance A Select manager -- 10 12 20 13 0 1.67 B Select site -- 8 15 22 15 0 2.33 C Hire workers...

  • 1. State whether each of the following statement is true or false. a) The sequence of...

    1. State whether each of the following statement is true or false. a) The sequence of activities in a project is depicted by the precedence (0.5 mark) (0.5 mark) relationships. The critical path is the shortest path through the project network. Slack is the amount of time an activity can be delayed without delaying the project. In PERT, three time estimates (optimistic, most likely and pessimistic) provide an estimate of the mean and variance for each activity based on the...

  • 1. When finding the approximate probability of project duration, it is necessary to know which of...

    1. When finding the approximate probability of project duration, it is necessary to know which of following? a. The mean and variance of each activity b. The mean of each activity on the CP c. The sd of only the activities on the CP d. Each activity's probability of completion e. The distribution of activity times 2. The sd of a path is computed as: a. the sum of the sd of all activities on the path b. the square...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT