Pik-Fast, a chain of convenience stores, is planning to open a new store. The activities required, their immediate predecessors, and the optimistic, most likely, and pessimistic estimates of their times (in days) are provided below.
Activity | Description | Immediate Predecessors | Optimistic Time (days) | Most Likely Time (days) | Pessimistic Time (days) | TE | ES | EF | LF | LS | Slack | Standard Dev | Variance |
A | Select manager | -- | 10 | 12 | 20 | 13 | 0 | 1.67 | |||||
B | Select site | -- | 8 | 15 | 22 | 15 | 0 | 2.33 | |||||
C | Hire workers | A | 17 | 21 | 31 | 22 | 0 | 2.33 | |||||
D | Basic training | C | 3 | 4 | 5 | 4 | 0 | 0.33 | |||||
E | Secure permits | B | 12 | 18 | 30 | 19 | 0 | 3.00 | |||||
F | Construct building | E | 26 | 30 | 40 | 31 | 0 | 2.33 | |||||
G | Purchase equipment | -- | 30 | 45 | 60 | 45 | 0 | 5.00 | |||||
H | Install equipment | F,G | 4 | 6 | 8 | 6 | 0 | 0.67 | |||||
I | Advertise opening | B | 15 | 55 | 89 | 54 | 0 | 12.33 | |||||
J | Final training | D,H | 2 | 3 | 4 | 3 | 0 | 0.33 | |||||
K | Stock store | H,I | 4 | 6 | 8 | 6 | 0 | 0.67 | |||||
L | Open store | J,K | 1 | 1 | 1 | 1 | 0 | 0.00 |
Showing formulas
b) Identify the critical path and projected project completion time using the expected completion times.
c) Calculate the expected slack times for any two paths not including the critical path. For the path slack time, compute this compared to the critical path and that also considers the slack time for each activity on that path.
d) Find the probability that the critical path will be completed within 80 working days.
Pik-Fast, a chain of convenience stores, is planning to open a new store. The activities required, their...
Pik-Fast, a chain of convenience stores, is planning to open a new store. The activities required, their immediate predecessors, and the optimistic, most likely, and pessimistic estimates of their times (in days) are provided below. Activity Description Immediate Predecessors Optimistic Time (days) Most Likely Time (days) Pessimistic Time (days) TE ES EF LF LS Slack Standard Dev Variance A Select manager -- 10 12 20 13 0 1.67 B Select site -- 8 15 22 15 0 2.33 C Hire workers...
1. Sid Orland is involved in planning a scientific research project. The activities are displayed in the following diagram. Optimistic, most likely, and pessimistic time estimates are displayed in the following table. Figure for Problem 1. r e 14 16 E 4 H 4 7 11 7 11 16 20 G 5 0 33 611 16 11 16 D 3 Most Likely Pessimistic Activity Optimistic 4 4 (a) Determine the expected times and variances for each activity along the critical...
The estimated times and immediate predecessors for the activities in a project at Caesar Douglas’s screening company are given in the following table. Assume that the activity times are independent. All times are in weeks. Activity Predecessors Optimistic Time (a) Most Likely Time (m) Pessimistic Time (b) A -- 9 10 11 B -- 4 10 16 C A 9 10 11 D B 5 8 11 What is the critical path based on expected times? You may use any...
Using the following information about Project A, its activities and predecessor activities below: Activity Predecessors A в B C D E, F D G The following table contains the pessimistic, likely, and optimistic estimates for how long activities are estimated to take for Project A. Activity Pessimistic Likely Optimistic 2 5 20 H 16 e. Calculate the time estimates (TE) f. Calculate the variance (s) g. Convert the TE to whole integers and place them in the network diagram for...
2. You are in charge of planning and coordinating next fall's sales management training program ur company. You have never done this before, but you decided to use the lessons from for yo your BUS 190 class to develop a table of tasks to be done, their immediate predecessors, and the most pessimistic, optimistic, and frequent times for each task. The table you developed is below: Task completion time estimate (weeks) Most Immediate Variance Task Predecessor Optimistic probable Pessimistic Mean...
1. A sporting goods store is planning to open an outlet in a college town. The activities consist of the hiring of the manager of the outlet and his/her employees. Also it is necessary to coordinate the renovation of a building that previously was a fast food restaurant. To schedule this project using PERT, the following time estimates (in weeks) are gathered: What is the critical path and expected completion time for this project? (15 pts) Which activity has the...
1. The activities needed for a new project your company is undertaking are listed in the following table. ACTIVITY IMMEDIATE PREDECESSOR(S) A ---- B ---- C A D A, B E B F C, D, E G D, E H F I F, G J G The activity times were determined for the project, and were as below. ACTIVITY ACTIVITY TIME (days) A 11 B 9 C 7 D 12 E 8 F 9 G 10 H 6 I 7...
A small software development project has eight major activities. The times are estimated and provided in the table below: Activity Optimistic Time Most Likely Time Pessimistic Time Immediate Predecessor(s) A 3 4 5 -- B 5 7 9 -- C 2 3 10 A D 2 5 8 B E 1 7 7 B F 3 5 7 C, D G 7 8 9 D, E H 2 6 10 F Answer the following questions based on above table 1-2...
uction needs to complete construction of Shopping Mall project, which is start in August. They are concerned with the completion time. Some of the ighly unreliable. List of activities and their optimistic, pessimistic, and most ion times in weeks) are given in following table: Optimistic Most Likely Pessimistic E(t) 3 5 9 13 11 0.1111 2.7778 7 Immediate Predecessor(s) None A None None AC D, E D, E F G F DF 2 6 9 5 10 6 5 2...
HW Score: 62.5%,5 of The estimated times and immediate predecessors for the activities in a projects Howard Urinalarning company are given in the following assume that the activity times are independent Question Help Activity . Immediate Predecessor) А 8 Time (weeksi . Predecessors Activity b 8 10 С 7 19 13 4 10 18 D 6 10 14 This exercise contains only parts , bedande a) Based on the activity time estimate the expected times and variance for each of...