HW Score: 62.5%,5 of The estimated times and immediate predecessors for the activities in a projects Howard Urinalarning comp
0 0
Add a comment Improve this question Transcribed image text
Answer #1

We solve the given problem using POM-QM as shown below:

We enter the required data as shown below:

1596170837417_image.png

On solving, we get

1596170864897_image.png

Hence, as seen from above, the answers for part a, b, c, are correct

d) Required duration = R = 23 weeks

Expected duration = E = 20.33 weeks

Std. Deviation = \sigma = 2.69

We get the Z value as:

Z = R Ε = \frac{23-20.33}{2.69} = 0.993

For Z = 0.99, the probability from Z table = 0.8389 = 83.89%

-----------------------------------------------------------------------------------------------------------------------

In case of any doubt, please ask through the comment section before Upvote/downvote.

If you liked the answer, please give an upvote. This will be quite encouraging for me, thank-you!!!

Add a comment
Know the answer?
Add Answer to:
HW Score: 62.5%,5 of The estimated times and immediate predecessors for the activities in a projects...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT