We solve the given problem using POM-QM as shown below:
We enter the required data as shown below:
On solving, we get
Hence, as seen from above, the answers for part a, b, c, are correct
d) Required duration = R = 23 weeks
Expected duration = E = 20.33 weeks
Std. Deviation = = 2.69
We get the Z value as:
Z = = = 0.993
For Z = 0.99, the probability from Z table = 0.8389 = 83.89%
-----------------------------------------------------------------------------------------------------------------------
In case of any doubt, please ask through the comment section before Upvote/downvote.
If you liked the answer, please give an upvote. This will be quite encouraging for me, thank-you!!!
HW Score: 62.5%,5 of The estimated times and immediate predecessors for the activities in a projects...
The estimated times and immediate predecessors for the activities in a project at Howard Umrah's retinal scanning company are given in the following table. Assume that the activity times are independent This exercise contains only parts a, b, c, d, and e. a) Based on the activity time estimates, the expected times and variance for each of the activities are (round your response to two decimal places): ExpectedActivityTimeWarlanceA9.830.26010.336.44C10.001.00010.001.78b) The expected completion time of the critical path weeks fround your response to two decimal...
please help!! The estimated times and immediate predecessors for the activities in a project at Howard Umrah's retinal scanning company are given in the following table. Assu that the activity times are independent. Time (weeks) Immediate Time (weeks) Immediate Activity a bPredecessor(s)Activitya bPredecessor(s) 12 10 12 8 17 This exercise contains only parts a, b, c, d, and e a) Based on the activity time estimates, the expected times and variance for each of the activities are (round your response...
The estimated times and immediate predecessors for the activities in a project at ABC Retinal Scanning Company are given in the following table. Assume that the activity times are independent. Activity Immediate Predecessor a (time weeks) m (time weeks) b (time weeks) A - 9 10 11 B - 4 10 16 C A 9 10 11 D B 5 8 11 Calculate the expected time (mean) and variance for each activity, then answer the following: a. What is the...
The estimated times and immediate predecessors for the activities in a project at Caesar Douglas’s screening company are given in the following table. Assume that the activity times are independent. All times are in weeks. Activity Predecessors Optimistic Time (a) Most Likely Time (m) Pessimistic Time (b) A -- 9 10 11 B -- 4 10 16 C A 9 10 11 D B 5 8 11 What is the critical path based on expected times? You may use any...
Q5: A construction project consists of activities, immediate predecessors (IPA) and duration in weeks are as shown in the following table. Draw the project network diagram, find the critical path and calculate the corresponding project completion time. Also, find the total float as well as the free float for each activity and the non- critical activities. (10 Marks) ТРА Duration (Weeks) Activity A B نما 4 с 14 D A 10 E F A BD BD с F.H 5 4...
Problem 5-10 The following represents a project that should be scheduled using CPM: IMMEDIATE PREDECESSORS TIMES (DAYS) ACTIVITY a m b A — 1 4 7 B — 3 5 10 C A 2 5 8 D A 4 6 11 E B 1 2 3 F C,D 3 5 7 G D,E 1 2 6 H F,G 2 5 6 b. What is the critical path? B-E-G-H A-D-G-H A-D-F-H A-C-F-H c. What is the expected project completion time? (Round...
Problem 5-10 The following represents a project that should be scheduled using CPM: IMMEDIATE TIMES (DAYS) ACTIVITY PREDECESSORS a m b А 7 B 2 3 7 с A 3 5 7 D А 5 6 10 E B 1 2 6 F CD 1 3 6 DE 1 3 14 H F G 5 14 b. What is the critical path? A-D-G-H B-E-G-H A-D-F-H A-C-F-H c. What is the expected project completion time? (Round your answer to 3 decimal...
Ross Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor relationships in the following table for building ne a b 2 5 1 Activity А B С D E F 1 Time (weeks) a m b 6 8 10 2 9 23 9 12 16 5 6 10 1 3 4 5 9 20 Immediate Predecessor(s) Activity G A H А А B к CE Time (weeks) m 3 1 7 7 3 Immediate Predecessor(s) CE F...
The following represents a project that should be scheduled using CPM: TIMES (DAYS) ACTIVITY IMMEDIATE PREDECESSORS a m b A — 1 3 5 B — 1 2 3 C A 1 2 3 D A 2 3 4 E B 3 4 11 F C, D 3 4 5 G D, E 1 4 6 H F, G 2 4 5 b. What is the critical path? A-C-F-H A-D-F-H B-E-G-H A-D-G-H c. What is the expected project completion time?...
The following represents a project that should be scheduled using CPM: IMMEDIATE PREDECESSORS TIMES (DAYS) ACTIVITY a m b A — 1 4 7 B — 2 6 13 C A 1 1 4 D A 2 3 4 E B 2 4 6 F C,D 1 5 9 G D,E 1 2 9 H F,G 3 6 9 b. What is the critical path? A-D-G-H B-E-G-H A-D-F-H A-C-F-H c. What is the expected project completion time? (Do not round...