Question

Problem 5-10 The following represents a project that should be scheduled using CPM: IMMEDIATE TIMES (DAYS) ACTIVITY PREDECESS
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Formula ta+ 4 tm t tp inte 6 2 i > to-ta o 2 0The PERT diagrann А TT 79 G B Activity te. A 14 1. B 0:83 c D 6.5 0.83 E 2.5 0183 . 3:17. 0.83 G 4.5 2-17 Н 2The paths are A- C - F - H ₂ 4 + 5 + 3.17 + 6 = 13-17 liy A-D-F-H = 4 + 61.5 + 3.17 + 6 = 19.67 rry A - D - G = 4 + 6.5 t 415ie the variance = A D - G H 1 t 0.83 + 2.17 + 2 = Probabili ability 22 - 21 0166, 6 0.5 636 1. Probability = 10:56

Hope this helps :)

If you liked the answer then please give an Up-vote, this will be quite encouraging for me, thank you!

Add a comment
Know the answer?
Add Answer to:
Problem 5-10 The following represents a project that should be scheduled using CPM: IMMEDIATE TIMES (DAYS)...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT