Question

The following represents a project that should be scheduled using CPM: IMMEDIATE PREDECESSORS TIMES (DAYS) ACTIVITY...

The following represents a project that should be scheduled using CPM:

IMMEDIATE PREDECESSORS TIMES (DAYS)
ACTIVITY a m b
A 1 4 7
B 2 6 13
C A 1 1 4
D A 2 3 4
E B 2 4 6
F C,D 1 5 9
G D,E 1 2 9
H F,G 3 6 9


b. What is the critical path?


  • A-D-G-H

  • B-E-G-H

  • A-D-F-H

  • A-C-F-H

c. What is the expected project completion time? (Do not round intermediate calculations. Round your answer to 3 decimal places.)

Project completion time    days

d. What is the probability of completing this project within 20 days? (Use Excel's NORM.S.DIST() function to find the correct probability for your computed Z-value. Do not round intermediate calculations. Round "z" value to 2 decimal places and final answer to 4 decimal places.)


Probability
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Below is the screenshot of the formula applied -

Below is the screenshot of the result -

Add a comment
Know the answer?
Add Answer to:
The following represents a project that should be scheduled using CPM: IMMEDIATE PREDECESSORS TIMES (DAYS) ACTIVITY...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT