Problem 5-10
The following represents a project that should be scheduled using CPM:
IMMEDIATE PREDECESSORS | TIMES (DAYS) | |||
ACTIVITY | a | m | b | |
A | — | 1 | 4 | 7 |
B | — | 3 | 5 | 10 |
C | A | 2 | 5 | 8 |
D | A | 4 | 6 | 11 |
E | B | 1 | 2 | 3 |
F | C,D | 3 | 5 | 7 |
G | D,E | 1 | 2 | 6 |
H | F,G | 2 | 5 | 6 |
b. What is the critical path?
B-E-G-H | |
A-D-G-H | |
A-D-F-H | |
A-C-F-H |
c. What is the expected project completion time? (Round your answer to 3 decimal places.)
Project completion time days
d. What is the probability of completing this project within 22 days? (Do not round intermediate calculations. Round your answer to 4 decimal places.)
Problem 5-10 The following represents a project that should be scheduled using CPM: IMMEDIATE PREDECESSORS TIMES...
Problem 5-10 The following represents a project that should be scheduled using CPM: IMMEDIATE TIMES (DAYS) ACTIVITY PREDECESSORS a m b А 7 B 2 3 7 с A 3 5 7 D А 5 6 10 E B 1 2 6 F CD 1 3 6 DE 1 3 14 H F G 5 14 b. What is the critical path? A-D-G-H B-E-G-H A-D-F-H A-C-F-H c. What is the expected project completion time? (Round your answer to 3 decimal...
The following represents a project that should be scheduled using CPM: IMMEDIATE PREDECESSORS TIMES (DAYS) ACTIVITY a m b A — 1 4 7 B — 2 6 13 C A 1 1 4 D A 2 3 4 E B 2 4 6 F C,D 1 5 9 G D,E 1 2 9 H F,G 3 6 9 b. What is the critical path? A-D-G-H B-E-G-H A-D-F-H A-C-F-H c. What is the expected project completion time? (Do not round...
The following represents a project that should be scheduled using CPM: TIMES (DAYS) ACTIVITY IMMEDIATE PREDECESSORS a m b A — 1 3 5 B — 1 2 3 C A 1 2 3 D A 2 3 4 E B 3 4 11 F C, D 3 4 5 G D, E 1 4 6 H F, G 2 4 5 b. What is the critical path? A-C-F-H A-D-F-H B-E-G-H A-D-G-H c. What is the expected project completion time?...
The following represents a project that should be scheduled using CPM: TIMES (DAYS) IMMEDIATE b ACTIVITY PREDECESSORS m a 1 4 7 3 5 10 B 2 5 4 6 11 D B 1 2 3 E C,D D,E F,G 3 5 7 F G 1 2 6 2 5 b. What is the critical path? A-D-F-H A-D-G-H B-E-G-H A-C-F-H c. What is the expected project completion time? (Do not round intermediate calculations. Round your answer to 3 decimal places.)...
The following represents a project that should be scheduled using CPM: Intermediate Times(Days) Activity Predecessors a m b A ----- 1 2 6 B ----- 1 2 9 C A 2 2 11 D A 1 8 9 E B 1 2 3 F C,D 3 4 11 G D,E 1 3 11 H F,G 2 3 11 What is the critical path? What is the expected project completion time? (Round your answer to 3 decimal places.) Project completion time...
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 3 B A 9 C A 5 D C 2 E B D 7 F D 6 G E F 4 b. What is the critical path? A-B-D-F-G A-B-E-G A-C-D-F-G A-C-D-E-G c. How many weeks will it take to complete the project? Number of weeks d. How much slack does activity B have? Slack of activity B week(s)
Problem 5-7 The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 7 B A 6 C A 2 D C 4 E B D 3 F D 4 G E F 6 b. What is the critical path? A-B-D-F-G A-C-D-E-G A-C-D-F-G A-B-E-G c. How many weeks will it take to complete the project? Number of weeks d. How much slack does activity B have? Slack of activity B week(s)
Problem 5-7 (Algo) The following activities are part of a project to be scheduled using CPM ACTIVITY IMMEDIATE PREDECESSOR TIME (HEEKS) A 9 B A. 3 C A. 7 D C E BD 4 F 3 E F G a. What is the critical path? A-C-D-E-G O A-B-D-F-G A-B-E-G A-C-D-F-G b. How many weeks will it take to complete the project? Number of weeks <Prey 3 of 8 Next>
Problem 5-7 The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) А 7 B 6 2 3 B.D D b. What is the critical path? Оооо A-C-D-E-G A-B-D-F-G A-B-E-G O A-C-D-F-G c. How many weeks will it take to complete the project? Number of weeks d. How much slack does activity B have? Slack of activity B week(s)
I need help with the following problem. Schedule the following activities using CPM. ACTIVITY Immediate Predecessors Time in Weeks A ---- 2 B A 5 C A 4 D B 3 E C, D 6 F D 3 G F 3 H E, G 4 Draw the network diagram below using the square activity I have provided. Just select the object, then copy it and paste how many you need and then arrange them in the order you need and...