The following represents a project that should be scheduled using CPM:
Intermediate | Times(Days) | |||
Activity | Predecessors | a | m | b |
A | ----- | 1 | 2 | 6 |
B | ----- | 1 | 2 | 9 |
C | A | 2 | 2 | 11 |
D | A | 1 | 8 | 9 |
E | B | 1 | 2 | 3 |
F | C,D | 3 | 4 | 11 |
G | D,E | 1 | 3 | 11 |
H | F,G | 2 | 3 | 11 |
What is the critical path?
What is the expected project completion time? (Round your answer to 3 decimal places.)
Project completion time ????? days
What is the probability of completing this project within 19 days? (Do not round intermediate calculations. Round your answer to 4 decimal places.)
Probability ???
EXPECTED TIME = (A + (4M) + B) / 6; WHERE A = OPTIMISTIC TIME, M = MOST LIKELY TIME, B = PESSIMISTIC TIME
VARIANCE = ((B - A) / 6)**2
ACTIVITY |
EXPECTED TIME |
VARIANCE |
A |
(1 + (4 * 2) + 6) / 6 = 2.5 |
((6 - 1) / 6)^2 = 0.6944444 |
B |
(1 + (4 * 2) + 9) / 6 = 3 |
((9 - 1) / 6)^2 = 1.7777778 |
C |
(2 + (4 * 2) + 11) / 6 = 3.5 |
((11 - 2) / 6)^2 = 2.25 |
D |
(1 + (4 * 8) + 9) / 6 = 7 |
((9 - 1) / 6)^2 = 1.7777778 |
E |
(1 + (4 * 2) + 3) / 6 = 2 |
((3 - 1) / 6)^2 = 0.1111111 |
F |
(3 + (4 * 4) + 11) / 6 = 5 |
((11 - 3) / 6)^2 = 1.7777778 |
G |
(1 + (4 * 3) + 11) / 6 = 4 |
((11 - 1) / 6)^2 = 2.7777778 |
H |
(2 + (4 * 3) + 11) / 6 = 4.1666667 |
((11 - 2) / 6)^2 = 2.25 |
CPM
ACTIVITY |
DURATION |
ES |
EF |
LS |
LF |
SLACK |
A |
2.5 |
0 |
2.5 |
0 |
2.5 |
0 |
B |
3 |
0 |
3 |
5.5 |
8.5 |
5.5 |
C |
3.5 |
2.5 |
6 |
6 |
9.5 |
3.5 |
D |
7 |
2.5 |
9.5 |
2.5 |
9.5 |
0 |
E |
2 |
3 |
5 |
8.5 |
10.5 |
5.5 |
F |
5 |
9.5 |
14.5 |
9.5 |
14.5 |
0 |
G |
4 |
9.5 |
13.5 |
10.5 |
14.5 |
1 |
H |
4.1666667 |
14.5 |
18.6666667 |
14.5 |
18.6666667 |
0 |
FORWARD PASS
We calculate the ES and EF values using a forward pass where the ES of an activity is the maximum EF of all the predecessor activities.
BACKWARD PASS
We calculate the LS and LF values using a backward pass where the LF of the activity is the minimum of all the successor activities.
SLACK
Slack is the value which is determined by subtracting EF from the LF or ES from the LS.
CRITICAL PATH
The critical path is the chain in the project network where the slack value of all the activities is 0, what this means is that any delay in these activities would result in delaying the entire project.
#CRITICAL PATH = ADFH
#DURATION OF PROJECT = 18.667
#PROBABILITY
VARIANCE OF CRITICAL PATH = SIGMA(VARIANCE OF THE CRITICAL PATH) = 6.5
DUE TIME = 19
ESTIMATED TIME = LENGTH OF CRITICAL PATH = 18.6666667
STDEV = SQRT(VARIANCE) = SQRT(6.5) = 2.54950976
Z = (DUE - ESTIMATED) / STDEV = (19 - 18.6666667) / 2.54950976 = 0.13074408
#PROBABILITY = NORMSDIST(0.13074408) = 0.552
**Z VALUE HAS NOT BEEN ROUNDED
Do leave a like for the answer if you found it helpful.
The following represents a project that should be scheduled using CPM: Intermediate Times(Days) Activity Predecessors a...
The following represents a project that should be scheduled using CPM: IMMEDIATE PREDECESSORS TIMES (DAYS) ACTIVITY a m b A — 1 4 7 B — 2 6 13 C A 1 1 4 D A 2 3 4 E B 2 4 6 F C,D 1 5 9 G D,E 1 2 9 H F,G 3 6 9 b. What is the critical path? A-D-G-H B-E-G-H A-D-F-H A-C-F-H c. What is the expected project completion time? (Do not round...
The following represents a project that should be scheduled using CPM: TIMES (DAYS) ACTIVITY IMMEDIATE PREDECESSORS a m b A — 1 3 5 B — 1 2 3 C A 1 2 3 D A 2 3 4 E B 3 4 11 F C, D 3 4 5 G D, E 1 4 6 H F, G 2 4 5 b. What is the critical path? A-C-F-H A-D-F-H B-E-G-H A-D-G-H c. What is the expected project completion time?...
The following represents a project that should be scheduled using CPM: TIMES (DAYS) IMMEDIATE b ACTIVITY PREDECESSORS m a 1 4 7 3 5 10 B 2 5 4 6 11 D B 1 2 3 E C,D D,E F,G 3 5 7 F G 1 2 6 2 5 b. What is the critical path? A-D-F-H A-D-G-H B-E-G-H A-C-F-H c. What is the expected project completion time? (Do not round intermediate calculations. Round your answer to 3 decimal places.)...
Problem 5-10 The following represents a project that should be scheduled using CPM: IMMEDIATE PREDECESSORS TIMES (DAYS) ACTIVITY a m b A — 1 4 7 B — 3 5 10 C A 2 5 8 D A 4 6 11 E B 1 2 3 F C,D 3 5 7 G D,E 1 2 6 H F,G 2 5 6 b. What is the critical path? B-E-G-H A-D-G-H A-D-F-H A-C-F-H c. What is the expected project completion time? (Round...
Problem 5-10 The following represents a project that should be scheduled using CPM: IMMEDIATE TIMES (DAYS) ACTIVITY PREDECESSORS a m b А 7 B 2 3 7 с A 3 5 7 D А 5 6 10 E B 1 2 6 F CD 1 3 6 DE 1 3 14 H F G 5 14 b. What is the critical path? A-D-G-H B-E-G-H A-D-F-H A-C-F-H c. What is the expected project completion time? (Round your answer to 3 decimal...
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 3 B A 9 C A 5 D C 2 E B D 7 F D 6 G E F 4 b. What is the critical path? A-B-D-F-G A-B-E-G A-C-D-F-G A-C-D-E-G c. How many weeks will it take to complete the project? Number of weeks d. How much slack does activity B have? Slack of activity B week(s)
Problem 5-7 The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 7 B A 6 C A 2 D C 4 E B D 3 F D 4 G E F 6 b. What is the critical path? A-B-D-F-G A-C-D-E-G A-C-D-F-G A-B-E-G c. How many weeks will it take to complete the project? Number of weeks d. How much slack does activity B have? Slack of activity B week(s)
Problem 5-7 The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) А 7 B 6 2 3 B.D D b. What is the critical path? Оооо A-C-D-E-G A-B-D-F-G A-B-E-G O A-C-D-F-G c. How many weeks will it take to complete the project? Number of weeks d. How much slack does activity B have? Slack of activity B week(s)
Problem 5-7 (Algo) The following activities are part of a project to be scheduled using CPM ACTIVITY IMMEDIATE PREDECESSOR TIME (HEEKS) A 9 B A. 3 C A. 7 D C E BD 4 F 3 E F G a. What is the critical path? A-C-D-E-G O A-B-D-F-G A-B-E-G A-C-D-F-G b. How many weeks will it take to complete the project? Number of weeks <Prey 3 of 8 Next>
Activity Predecessors ti mes (da ys) a m b A .... 4 6 8 B A 4 6 8 C A 2 4 6 D B,C 1 8 9 E D 3 5 7 F D,E 2 3 4 1. The critical path is? 2. Slack time exists for activity ___? 3. The late start time for activity C is ___? 4. The expected time for project completion is? 5. What is the probability of completing this project...