The estimated times and immediate predecessors for the activities in a project at ABC Retinal Scanning Company are given in the following table. Assume that the activity times are independent.
Activity | Immediate Predecessor |
a (time weeks) |
m (time weeks) |
b (time weeks) |
A | - | 9 | 10 | 11 |
B | - | 4 | 10 | 16 |
C | A | 9 | 10 | 11 |
D | B | 5 | 8 | 11 |
Calculate the expected time (mean) and variance for each activity, then answer the following:
a. What is the variance of the critical path? What is the variance of the other path in the network?
0.22
5.00
b. What is the project standard deviation?
0.47
c. What is the expected completion time of the critical path? What is the expected completion time of the other path in the network?
22 weeks
20 weeks
d. If the time to complete the critical path is normally distributed, what is the probability that this path will be finished in 22 weeks or less?
100%
e. If the time to complete the other non-critical path is normally distributed, what is the probability that this path will be finished in 22 weeks or less? 96%
96%
I believe those are the correct answers. Can you please show me the step-by-step directions for this and correct any errors?
a.
Activity | Optimistic time-a | Expected completion time-m | Pessimistic time-b | Expected time= (a+4*m+ b)/6 | Variance, (sigma)^2= (b-a/6)^2 |
A | 9 | 10 | 11 | 10.00 | 0.11 |
B | 4 | 11 | 18 | 11.00 | 5.44 |
C | 9 | 9 | 13 | 9.67 | 0.44 |
D | 5 | 8 | 12 | 8.17 | 1.36 |
b.
Paths | Duration |
A-C | 19.67 (critical path) |
B-D | 19.17 |
c.
Paths | Duration | Variance |
A-C (Critical path) | 19.67 | 0.56 |
B-D | 19.17 | 6.81 |
d.
step 1 | variance along the critical path | 0.56 | |||
step 2 | mean project time (u) of critical path is= | 19.67 | |||
step 3 | Required completion time is | 22.0 | |||
step 4 | standard deviation= sqrt(variance)= | 0.75 | |||
step 5 | because Z= (given completion time- u)/standard deviation | 3.130 | |||
step 6 | P(<=z)= using NORM.S.DIST(z,true) | 0.9991 or 99.91% |
e.
step 1 | variance along the critical path | 6.81 | |||
step 2 | mean project time (u) of non-critical path is= | 19.17 | |||
step 3 | Required completion time is | 22.0 | |||
step 4 | standard deviation= sqrt(variance)= | 2.61 | |||
step 5 | because Z= (given completion time- u)/standard deviation | 1.086 | |||
step 6 | P(<=z)= using NORM.S.DIST(z,true) | 0.8613 or 86.13% |
The estimated times and immediate predecessors for the activities in a project at ABC Retinal Scanning...
please help!! The estimated times and immediate predecessors for the activities in a project at Howard Umrah's retinal scanning company are given in the following table. Assu that the activity times are independent. Time (weeks) Immediate Time (weeks) Immediate Activity a bPredecessor(s)Activitya bPredecessor(s) 12 10 12 8 17 This exercise contains only parts a, b, c, d, and e a) Based on the activity time estimates, the expected times and variance for each of the activities are (round your response...
The estimated times and immediate predecessors for the activities in a project at Howard Umrah's retinal scanning company are given in the following table. Assume that the activity times are independent This exercise contains only parts a, b, c, d, and e. a) Based on the activity time estimates, the expected times and variance for each of the activities are (round your response to two decimal places): ExpectedActivityTimeWarlanceA9.830.26010.336.44C10.001.00010.001.78b) The expected completion time of the critical path weeks fround your response to two decimal...
HW Score: 62.5%,5 of The estimated times and immediate predecessors for the activities in a projects Howard Urinalarning company are given in the following assume that the activity times are independent Question Help Activity . Immediate Predecessor) А 8 Time (weeksi . Predecessors Activity b 8 10 С 7 19 13 4 10 18 D 6 10 14 This exercise contains only parts , bedande a) Based on the activity time estimate the expected times and variance for each of...
The estimated times and immediate predecessors for the activities in a project at Caesar Douglas’s screening company are given in the following table. Assume that the activity times are independent. All times are in weeks. Activity Predecessors Optimistic Time (a) Most Likely Time (m) Pessimistic Time (b) A -- 9 10 11 B -- 4 10 16 C A 9 10 11 D B 5 8 11 What is the critical path based on expected times? You may use any...
Q5: A construction project consists of activities, immediate predecessors (IPA) and duration in weeks are as shown in the following table. Draw the project network diagram, find the critical path and calculate the corresponding project completion time. Also, find the total float as well as the free float for each activity and the non- critical activities. (10 Marks) ТРА Duration (Weeks) Activity A B نما 4 с 14 D A 10 E F A BD BD с F.H 5 4...
Problem 5-10 The following represents a project that should be scheduled using CPM: IMMEDIATE PREDECESSORS TIMES (DAYS) ACTIVITY a m b A — 1 4 7 B — 3 5 10 C A 2 5 8 D A 4 6 11 E B 1 2 3 F C,D 3 5 7 G D,E 1 2 6 H F,G 2 5 6 b. What is the critical path? B-E-G-H A-D-G-H A-D-F-H A-C-F-H c. What is the expected project completion time? (Round...
For the following project with times to complete activities in weeks: ActivityDepend on a m b 1 3 6 2 3 6 3 79 2 23 34 5 B,C (a) Calculate the expected time and variance for each activity. Draw the project network (AOA). Determine the critical path, expected completion time and variance. (b) Determine the probability of finishing the project in 14 weeks or less. (c) You want to tell the client you are 95% sure the project will...
1. The activities needed for a new project your company is undertaking are listed in the following table. ACTIVITY IMMEDIATE PREDECESSOR(S) A ---- B ---- C A D A, B E B F C, D, E G D, E H F I F, G J G The activity times were determined for the project, and were as below. ACTIVITY ACTIVITY TIME (days) A 11 B 9 C 7 D 12 E 8 F 9 G 10 H 6 I 7...
PERT Analysis: The following represents a project with four activities. All times are in weeks. Activity Immediate Predecessor Optimistic Time Most Likely Time Pessimistic Time A - 3 8 14 B - 8 8 8 C A 6 9 18 D B 6 11 17 According to the data in the above Table: What is the critical path? What is the minimum expected completion time for the project? According to the above Table, there are four activities in the project....
The following represents a project that should be scheduled using CPM: TIMES (DAYS) ACTIVITY IMMEDIATE PREDECESSORS a m b A — 1 3 5 B — 1 2 3 C A 1 2 3 D A 2 3 4 E B 3 4 11 F C, D 3 4 5 G D, E 1 4 6 H F, G 2 4 5 b. What is the critical path? A-C-F-H A-D-F-H B-E-G-H A-D-G-H c. What is the expected project completion time?...