Question

The estimated times and immediate predecessors for the activities in a project at ABC Retinal Scanning...

The estimated times and immediate predecessors for the activities in a project at ABC Retinal Scanning Company are given in the following table. Assume that the activity times are independent.

Activity Immediate Predecessor

a

(time weeks)

m

(time weeks)

b

(time weeks)

A - 9 10 11
B - 4 10 16
C A 9 10 11
D B 5 8 11

Calculate the expected time (mean) and variance for each activity, then answer the following:

a. What is the variance of the critical path? What is the variance of the other path in the network?

0.22

5.00

b. What is the project standard deviation?

0.47

c. What is the expected completion time of the critical path? What is the expected completion time of the other path in the network?

22 weeks

20 weeks

d. If the time to complete the critical path is normally distributed, what is the probability that this path will be finished in 22 weeks or less?                           

100%

e. If the time to complete the other non-critical path is normally distributed, what is the probability that this path will be finished in 22 weeks or less? 96%

96%

I believe those are the correct answers. Can you please show me the step-by-step directions for this and correct any errors?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

a.

Activity Optimistic time-a Expected completion time-m Pessimistic time-b Expected time= (a+4*m+ b)/6 Variance, (sigma)^2= (b-a/6)^2
A 9 10 11 10.00 0.11
B 4 11 18 11.00 5.44
C 9 9 13 9.67 0.44
D 5 8 12 8.17 1.36

b.

Paths Duration
A-C 19.67 (critical path)
B-D 19.17

c.

Paths Duration Variance
A-C (Critical path) 19.67 0.56
B-D 19.17 6.81

d.

step 1 variance along the critical path 0.56
step 2 mean project time (u) of critical path is= 19.67
step 3 Required completion time is 22.0
step 4 standard deviation= sqrt(variance)=   0.75
step 5 because Z= (given completion time- u)/standard deviation 3.130
step 6 P(<=z)= using NORM.S.DIST(z,true) 0.9991 or 99.91%

e.

step 1 variance along the critical path 6.81
step 2 mean project time (u) of non-critical path is= 19.17
step 3 Required completion time is 22.0
step 4 standard deviation= sqrt(variance)=   2.61
step 5 because Z= (given completion time- u)/standard deviation 1.086
step 6 P(<=z)= using NORM.S.DIST(z,true) 0.8613 or 86.13%
Add a comment
Know the answer?
Add Answer to:
The estimated times and immediate predecessors for the activities in a project at ABC Retinal Scanning...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT