Question

The estimated times and immediate predecessors for the activities in a project


The estimated times and immediate predecessors for the activities in a project at Howard Umrah's retinal scanning company are given in the following table. Assume that the activity times are independent 

image.png

This exercise contains only parts a, b, c, d, and e. 

a) Based on the activity time estimates, the expected times and variance for each of the activities are (round your response to two decimal places): 


Expected
ActivityTimeWarlance
A9.830.26
010.336.44
C10.001.00
010.001.78

b) The expected completion time of the critical path weeks fround your response to two decimal places


0 0
Add a comment Improve this question Transcribed image text
✔ Recommended Answer
Answer #1

(a)

Expected time Variance
Activity a m b te = (a + 4m + b)/6 (b - a)2/36
A 8 10 11 9.83 0.25
B 4 10 18 10.33 5.44
C 7 10 13 10.00 1.00
D 6 10 14 10.00 1.78

(b)

Path Expected duration
A-C 19.83
B-D 20.33

The longest and hence the critical path is B-D and the expected duration is 20.33 weeks.

Add a comment
Know the answer?
Add Answer to:
The estimated times and immediate predecessors for the activities in a project
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT