Activity | To | Tm | Tp | Te | (Var)^0.5 | Var |
A | 6 | 8 | 10 | 8 | 0.666667 | 0.444444 |
B | 2 | 9 | 23 | 10.16667 | 3.5 | 12.25 |
C | 9 | 12 | 16 | 12.16667 | 1.166667 | 1.361111 |
D | 5 | 6 | 10 | 6.5 | 0.833333 | 0.694444 |
E | 1 | 3 | 4 | 2.833333 | 0.5 | 0.25 |
F | 5 | 9 | 20 | 10.16667 | 2.5 | 6.25 |
G | 2 | 3 | 5 | 3.166667 | 0.5 | 0.25 |
H | 1 | 1 | 1 | 1 | 0 | 0 |
I | 7 | 7 | 7 | 7 | 0 | 0 |
J | 4 | 7 | 14 | 7.666667 | 1.666667 | 2.777778 |
K | 3 | 3 | 4 | 3.166667 | 0.166667 | 0.027778 |
1. Expected time for activity C is 12.16
2. Variance of activity C is 1.3611
3 ABEFIK is the critical path with duration 41.31
4 Variance along CP is 19.222
5 Prob that project will be completed in 40 weeks is
z =40-41.31 / (19.222)^0.5
=-0.2987
which corresponds to probability of 0.3818
Ross Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor relationships in the...
Ross Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor relationships in the following table for building new motels. Time (weeks) Immediate Time (weeks) Immediate Activity a m b Predecessor(s) Activity a m b Predecessor(s) A 6 8 10 — G 3 3 5 C, E B 2 9 23 A H 1 1 1 F C 8 12 18 A I 7 7 7 F D 4 7 10 A J 4 7 14 D, G,...
or4(2 complete) HW Score: 4 oblem 3.17b ss Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor relationships in the Time (weeks) Immediate Time (weeks) Immediate Activitym Predecessorte) Activitym D b Predecessorts) 9 1 B 294 C91416 C, E J 6 7 12 D,G H L, J 8 20 C. E a) The expected (estimated) time for activity C is 13.50 weeks. (Round your response to two decimal places) b) The variance for activity C is 1.36...
1. Ross Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor relationships in the following table for building new motels. ActivityTime (weeks)a m bImmediatePredecessor(s) Activity aTime (weeks)m bImmediatePredecessor(s)A4810—G234C, EB2824AH222FC81216AI666FD4610AJ4612D, G, HE123BK223I, JF6820C, E a) The expected (estimated) time for activity C is weeks. (Round your response to two decimal places.) b) The variance for activity C is weeks. (Round your response to two decimal places.) c) Based on the calculation of the estimated times, the critical path...
I need to know: a. The expected (estimated) time for activity C is____weeks. (Round your response to two decimal places.) b. The variance for activity C is ___ weeks c. Based on the calculation of the estimate time the critical path it is __ __ __ __ __ __ d. The activity variance along the critical path is ___ weeks e. The probability hopkins hospital will finish the project in 40 weeks or less is _____ Ross Hopkins, president of...
HW Score: 62.5%,5 of The estimated times and immediate predecessors for the activities in a projects Howard Urinalarning company are given in the following assume that the activity times are independent Question Help Activity . Immediate Predecessor) А 8 Time (weeksi . Predecessors Activity b 8 10 С 7 19 13 4 10 18 D 6 10 14 This exercise contains only parts , bedande a) Based on the activity time estimate the expected times and variance for each of...
please help!! The estimated times and immediate predecessors for the activities in a project at Howard Umrah's retinal scanning company are given in the following table. Assu that the activity times are independent. Time (weeks) Immediate Time (weeks) Immediate Activity a bPredecessor(s)Activitya bPredecessor(s) 12 10 12 8 17 This exercise contains only parts a, b, c, d, and e a) Based on the activity time estimates, the expected times and variance for each of the activities are (round your response...
QUESTION 17 The critical path of the projected below as been determine what they Activity Time Immediate Predecessor A 7 8 C 2 A D A E F 5 G CE 8 D. QUESTION 17 A B The critical path of the project outlined below has been mined of B-F-H. What is the slack time for activity F? Time Immediate Activity (wks) Predecessor(s) 7 8 с 2 А A E B F G 9 CE H 8 DF D 2...
QUESTION 20 The critical path of the project outlined below has been determined of B-F-H. What is the slack time for activity F? Time Immediate Activity (wks) Predecessor(s) A 7 B B с 2 А D 2 А E 3 B F 5 G 9 CE H 8 DF B
The following represent activities in Marc Massoud's Construction Company project: Activity Immediate Predecessor(s) Time (weeks) Activity Immediate Predecessor(s) Time (weeks) = C, E WLUI WNVN = n a a) Choose the correct network to represent this situation. OA. OB b) The critical path is B-E-F-H c) The length of the critical path is . weeks.
Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Time Activity (weeks) А 7 Immediate Predecessor(s) Time Activity (weeks) E 3 F 7 G 11 H 8 Immediate Predecessor(s) B B CE D. B с D 2 3 A A Dave's earliest...