Question

Ross Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor relationships in the foll

I need to know:

a. The expected​ (estimated) time for activity C is____weeks. ​(Round your response to two decimal​ places.)

b. The variance for activity C is ___ weeks

c. Based on the calculation of the estimate time the critical path it is __ __ __ __ __ __

d. The activity variance along the critical path is ___ weeks

e. The probability hopkins hospital will finish the project in 40 weeks or less is _____

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Activity Optimistic time-a Expected completion time-m Pessimistic time-b Expected time= (a+4*m+ b)/6 Variance, (sigma)^2= (b-a/6)^2
A 4 8 12 8.00 1.78
B 2 9 24 10.33 13.44
C 8 14 18 13.67 2.78
D 4 7 10 7.00 1.00
E 1 3 4 2.83 0.25
F 5 8 21 9.67 7.11
G 2 3 5 3.17 0.25
H 1 1 1 1.00 0.00
I 7 7 7 7.00 0.00
J 4 8 14 8.33 2.78
K 3 3 4 3.17 0.03

Answer a: Expected time of activity C= 13.67

Answer b: Variance for activity C= 2.78

Paths Duration
ABEFHJK 43.33
ABEGJK 35.83
ABEFIK 41.00
ACGJK 36.33
ACFHJK 43.83
ACFIK 41.50
ADJK 26.50

Answer c) Based on the calculation of the estimated​ times, the critical path is ACFHJK

Answer d: The estimated time for the critical path is 43.83

Add a comment
Know the answer?
Add Answer to:
I need to know: a. The expected​ (estimated) time for activity C is____weeks. ​(Round your response...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • project management

    1.     Ross Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor relationships in the following table for building new motels.  ActivityTime (weeks)a         m           bImmediatePredecessor(s) Activity aTime (weeks)m bImmediatePredecessor(s)A4810—G234C, EB2824AH222FC81216AI666FD4610AJ4612D, G, HE123BK223I, JF6820C, E a)  The expected (estimated) time for activity C is                         weeks. (Round your response to two decimal places.) b)  The variance for activity C is                         weeks. (Round your response to two decimal places.) c)  Based on the calculation of the estimated times, the critical path...

  • Ross​ Hopkins, president of Hopkins​ Hospitality, has developed the​ tasks, durations, and predecessor relationships in the...

    Ross​ Hopkins, president of Hopkins​ Hospitality, has developed the​ tasks, durations, and predecessor relationships in the following table for building new motels.                                                                                                                                                             Time ​(weeks​) Immediate Time ​(weeks​) Immediate Activity a m b ​Predecessor(s) Activity a m b ​Predecessor(s) A 6 8 10 — G 3 3 5 ​C, E B 2 9 23 A H 1 1 1 F C 8 12 18 A I 7 7 7 F D 4 7 10 A J 4 7 14 ​D, G,...

  • Ross Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor relationships in the...

    Ross Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor relationships in the following table for building ne a b 2 5 1 Activity А B С D E F 1 Time (weeks) a m b 6 8 10 2 9 23 9 12 16 5 6 10 1 3 4 5 9 20 Immediate Predecessor(s) Activity G A H А А B к CE Time (weeks) m 3 1 7 7 3 Immediate Predecessor(s) CE F...

  • or4(2 complete) HW Score: 4 oblem 3.17b ss Hopkins, president of Hopkins Hospitality, has developed the...

    or4(2 complete) HW Score: 4 oblem 3.17b ss Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor relationships in the Time (weeks) Immediate Time (weeks) Immediate Activitym Predecessorte) Activitym D b Predecessorts) 9 1 B 294 C91416 C, E J 6 7 12 D,G H L, J 8 20 C. E a) The expected (estimated) time for activity C is 13.50 weeks. (Round your response to two decimal places) b) The variance for activity C is 1.36...

  • The following represent activities in Marc Massoud's Construction Company project: Activity Immediate Predecessor(s) Time (weeks) Activity...

    The following represent activities in Marc Massoud's Construction Company project: Activity Immediate Predecessor(s) Time (weeks) Activity Immediate Predecessor(s) Time (weeks) = C, E WLUI WNVN = n a a) Choose the correct network to represent this situation. OA. OB b) The critical path is B-E-F-H c) The length of the critical path is . weeks.

  • A project for improving a billing process has the following precedence relationships and activity times: Activity...

    A project for improving a billing process has the following precedence relationships and activity times: Activity Activity Time (weeks) Immediate Predecessor(s) B, C I Q7 Moow E F, G b. Calculate the slack for each activity. Which activities are on the critical path? Activity Activity Time (weeks) On critical path? Yes Slack (weeks) D 0 Yes 0 0 00000000 @ Tm I

  • also needs daves latest start and latest finish: Dave Fletcher was able to determine the activity...

    also needs daves latest start and latest finish: Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for e activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s) C, E D, F Dave's earliest start (ES) and earliest finish (EF) are: Activity ES...

  • Consider the following project activities: Calculate the expected time (te) for each activity. Draw an Activity...

    Consider the following project activities: Calculate the expected time (te) for each activity. Draw an Activity on Node (AON) diagram to reflect the flow of these activities. Calculate the Early Start (ES), Early Finish (EF), Late Start (LS), and Late Finish (LF) for each activity. Calculate the slack for each activity. Identify all activities on the Critical Path. Use the data to calculate the probability the project will finish in 20 weeks (Hint: z-score). Activity A 8 с D E...

  • The estimated times and immediate predecessors for the activities in a project at ABC Retinal Scanning...

    The estimated times and immediate predecessors for the activities in a project at ABC Retinal Scanning Company are given in the following table. Assume that the activity times are independent. Activity Immediate Predecessor a (time weeks) m (time weeks) b (time weeks) A - 9 10 11 B - 4 10 16 C A 9 10 11 D B 5 8 11 Calculate the expected time (mean) and variance for each activity, then answer the following: a. What is the...

  • QUESTION 17 The critical path of the projected below as been determine what they Activity Time...

    QUESTION 17 The critical path of the projected below as been determine what they Activity Time Immediate Predecessor A 7 8 C 2 A D A E F 5 G CE 8 D. QUESTION 17 A B The critical path of the project outlined below has been mined of B-F-H. What is the slack time for activity F? Time Immediate Activity (wks) Predecessor(s) 7 8 с 2 А A E B F G 9 CE H 8 DF D 2...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT