Question

project management

1.     Ross Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor relationships in the following table for building new motels.

 

 

Activity

Time (weeks)

a         m           b

Immediate

Predecessor(s)

 

Activity

 

a

Time (weeks)

m

 

b

Immediate

Predecessor(s)

A

4

8

10

G

2

3

4

C, E

B

2

8

24

A

H

2

2

2

F

C

8

12

16

A

I

6

6

6

F

D

4

6

10

A

J

4

6

12

D, G, H

E

1

2

3

B

K

2

2

3

I, J

F

6

8

20

C, E






 

a)  The expected (estimated) time for activity C is                         weeks. (Round your response to two decimal places.)

 

b) 





The variance for activity C is                         weeks. (Round your response to two decimal places.)


 

c)  Based on the calculation of the estimated times, the critical path is                              .

 

d) 





The estimated time for the critical path is                         weeks. (Round your response to two decimal places.)


 

e)  The activity variance along the critical path is                         weeks. (Round your response to two decimal places.)

 

f)  Using the standard normal table, the probability that Hopkins Hospitality will finish the project in 36 weeks or less is   . (Enter as a probability and round your response to three decimal places.)

Resim1.png

0 0
Add a comment Improve this question Transcribed image text
Request Professional Answer

Request Answer!

We need at least 10 more requests to produce the answer.

0 / 10 have requested this problem solution

The more requests, the faster the answer.

Request! (Login Required)


All students who have requested the answer will be notified once they are available.
Know the answer?
Add Answer to:
project management
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
  • I need to know: a. The expected​ (estimated) time for activity C is____weeks. ​(Round your response...

    I need to know: a. The expected​ (estimated) time for activity C is____weeks. ​(Round your response to two decimal​ places.) b. The variance for activity C is ___ weeks c. Based on the calculation of the estimate time the critical path it is __ __ __ __ __ __ d. The activity variance along the critical path is ___ weeks e. The probability hopkins hospital will finish the project in 40 weeks or less is _____ Ross Hopkins, president of...

  • Ross​ Hopkins, president of Hopkins​ Hospitality, has developed the​ tasks, durations, and predecessor relationships in the...

    Ross​ Hopkins, president of Hopkins​ Hospitality, has developed the​ tasks, durations, and predecessor relationships in the following table for building new motels.                                                                                                                                                             Time ​(weeks​) Immediate Time ​(weeks​) Immediate Activity a m b ​Predecessor(s) Activity a m b ​Predecessor(s) A 6 8 10 — G 3 3 5 ​C, E B 2 9 23 A H 1 1 1 F C 8 12 18 A I 7 7 7 F D 4 7 10 A J 4 7 14 ​D, G,...

  • Ross Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor relationships in the...

    Ross Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor relationships in the following table for building ne a b 2 5 1 Activity А B С D E F 1 Time (weeks) a m b 6 8 10 2 9 23 9 12 16 5 6 10 1 3 4 5 9 20 Immediate Predecessor(s) Activity G A H А А B к CE Time (weeks) m 3 1 7 7 3 Immediate Predecessor(s) CE F...

  • or4(2 complete) HW Score: 4 oblem 3.17b ss Hopkins, president of Hopkins Hospitality, has developed the...

    or4(2 complete) HW Score: 4 oblem 3.17b ss Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor relationships in the Time (weeks) Immediate Time (weeks) Immediate Activitym Predecessorte) Activitym D b Predecessorts) 9 1 B 294 C91416 C, E J 6 7 12 D,G H L, J 8 20 C. E a) The expected (estimated) time for activity C is 13.50 weeks. (Round your response to two decimal places) b) The variance for activity C is 1.36...

  • please help!! The estimated times and immediate predecessors for the activities in a project at Howard...

    please help!! The estimated times and immediate predecessors for the activities in a project at Howard Umrah's retinal scanning company are given in the following table. Assu that the activity times are independent. Time (weeks) Immediate Time (weeks) Immediate Activity a bPredecessor(s)Activitya bPredecessor(s) 12 10 12 8 17 This exercise contains only parts a, b, c, d, and e a) Based on the activity time estimates, the expected times and variance for each of the activities are (round your response...

  • HW Score: 62.5%,5 of The estimated times and immediate predecessors for the activities in a projects...

    HW Score: 62.5%,5 of The estimated times and immediate predecessors for the activities in a projects Howard Urinalarning company are given in the following assume that the activity times are independent Question Help Activity . Immediate Predecessor) А 8 Time (weeksi . Predecessors Activity b 8 10 С 7 19 13 4 10 18 D 6 10 14 This exercise contains only parts , bedande a) Based on the activity time estimate the expected times and variance for each of...

  • The estimated times and immediate predecessors for the activities in a project

    The estimated times and immediate predecessors for the activities in a project at Howard Umrah's retinal scanning company are given in the following table. Assume that the activity times are independent This exercise contains only parts a, b, c, d, and e. a) Based on the activity time estimates, the expected times and variance for each of the activities are (round your response to two decimal places): ExpectedActivityTimeWarlanceA9.830.26010.336.44C10.001.00010.001.78b) The expected completion time of the critical path weeks fround your response to two decimal...

  • Coleman Rich Control Devices, Inc., produces custom-built relay devices for auto makers. The most recent project...

    Coleman Rich Control Devices, Inc., produces custom-built relay devices for auto makers. The most recent project undertaken by Rich requires 14 different activities. Rich's managers would like to determine the total project completion time (in days) and those activities that lie along the critical path. The appropriate data are shown in the following table: பா் Immediate Immediate Time (days) Time (days) Predecessor(s) Activity Predecessor(s) b b Activity a 6 E, F G, H A 4 5 8 3 3 B...

  • The following represent activities in Marc Massoud's Construction Company project: Activity Immediate Predecessor(s) Time (weeks) Activity...

    The following represent activities in Marc Massoud's Construction Company project: Activity Immediate Predecessor(s) Time (weeks) Activity Immediate Predecessor(s) Time (weeks) = C, E WLUI WNVN = n a a) Choose the correct network to represent this situation. OA. OB b) The critical path is B-E-F-H c) The length of the critical path is . weeks.

  • The estimated times and immediate predecessors for the activities in a project at ABC Retinal Scanning...

    The estimated times and immediate predecessors for the activities in a project at ABC Retinal Scanning Company are given in the following table. Assume that the activity times are independent. Activity Immediate Predecessor a (time weeks) m (time weeks) b (time weeks) A - 9 10 11 B - 4 10 16 C A 9 10 11 D B 5 8 11 Calculate the expected time (mean) and variance for each activity, then answer the following: a. What is the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT