Question

Coleman Rich Control Devices, Inc., produces custom-built relay devices for auto makers. The most recent project undertaken b
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Procedure Total effective time is calculated using the formula: (a+4m+b)/6 Early Start and Early Finish 1. The activities havTe = (a+4m+b)/6 EF = ES + Te LS = LF - Te Slack = LF - EF Activity Predecessors Std Deviation =(b a)/6 Variation = std deviata) Project completion time (m): 50.82 days Critical Path = A-C-E-H-I-J-L-N b) Let x be the expected project completion time =

Add a comment
Know the answer?
Add Answer to:
Coleman Rich Control Devices, Inc., produces custom-built relay devices for auto makers. The most recent project...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Rich Cole Control Devices, Inc., produces custom-built relay devices for auto makers. The most recent project...

    Rich Cole Control Devices, Inc., produces custom-built relay devices for auto makers. The most recent project undertaken by Cole requires 14 different activities appropriate data are shown in the following table Time (days) Immediate bPredecessor(s)Activitya Time (days) Immediate Activity a bPredecessor(s) E, F G, H 10 17 B, C 5 6 10 6 L, M a) The expected completion time of the project days (round your response to two decimal places) The activities that represent the project's critical path are...

  • project management

    1.     Ross Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor relationships in the following table for building new motels.  ActivityTime (weeks)a         m           bImmediatePredecessor(s) Activity aTime (weeks)m bImmediatePredecessor(s)A4810—G234C, EB2824AH222FC81216AI666FD4610AJ4612D, G, HE123BK223I, JF6820C, E a)  The expected (estimated) time for activity C is                         weeks. (Round your response to two decimal places.) b)  The variance for activity C is                         weeks. (Round your response to two decimal places.) c)  Based on the calculation of the estimated times, the critical path...

  • A project has the following set of activities Activity Immediate Predecessor Duration (weeks) A - 8...

    A project has the following set of activities Activity Immediate Predecessor Duration (weeks) A - 8 B - 10 C A 3 D A 7 E B, C 6 F B, C 7 G D, E 5 H F 3 Draw the AON diagram Identify all the possible paths What is the critical path? Can activity B be delayed without delaying the completion of the project? If so, by how many days?

  • project are listed for a In the following table the activities with their precedence sequence and...

    project are listed for a In the following table the activities with their precedence sequence and expected time (days) Immediate Predecessor(s) Time (days) Activity 7 A 2 A B 4 C 4 5 5 E C F 2 G E, F 3 H G, H a) The activities on the critical path are b) The project length is days.

  • please help!! The estimated times and immediate predecessors for the activities in a project at Howard...

    please help!! The estimated times and immediate predecessors for the activities in a project at Howard Umrah's retinal scanning company are given in the following table. Assu that the activity times are independent. Time (weeks) Immediate Time (weeks) Immediate Activity a bPredecessor(s)Activitya bPredecessor(s) 12 10 12 8 17 This exercise contains only parts a, b, c, d, and e a) Based on the activity time estimates, the expected times and variance for each of the activities are (round your response...

  • HW Score: 62.5%,5 of The estimated times and immediate predecessors for the activities in a projects...

    HW Score: 62.5%,5 of The estimated times and immediate predecessors for the activities in a projects Howard Urinalarning company are given in the following assume that the activity times are independent Question Help Activity . Immediate Predecessor) А 8 Time (weeksi . Predecessors Activity b 8 10 С 7 19 13 4 10 18 D 6 10 14 This exercise contains only parts , bedande a) Based on the activity time estimate the expected times and variance for each of...

  • can you help me wirh this question please Question 7 1 pts 5- Draw the activity-on-node...

    can you help me wirh this question please Question 7 1 pts 5- Draw the activity-on-node project network associated with the following activities for a construction project. How long should it take the team to complete this project? What are the critical path activities? Provide your answers in the blank fields below. Immediate Predecessor(s) Time (Days) Activity IA 3 B A 4 IC с A 6 D B 6 E B 4 IF c с 4 G D 6 H...

  • Ross​ Hopkins, president of Hopkins​ Hospitality, has developed the​ tasks, durations, and predecessor relationships in the...

    Ross​ Hopkins, president of Hopkins​ Hospitality, has developed the​ tasks, durations, and predecessor relationships in the following table for building new motels.                                                                                                                                                             Time ​(weeks​) Immediate Time ​(weeks​) Immediate Activity a m b ​Predecessor(s) Activity a m b ​Predecessor(s) A 6 8 10 — G 3 3 5 ​C, E B 2 9 23 A H 1 1 1 F C 8 12 18 A I 7 7 7 F D 4 7 10 A J 4 7 14 ​D, G,...

  • 2. what is the project variance value of completion? !!! Que A small software development project...

    2. what is the project variance value of completion? !!! Que A small software development project at Krishna Dhir's firm has five major activities. The times are estimated and provided in the table below: Activity Immediate Predecessor a 2 الما COO m 5 6 7 5 3 b 8 9 10 14 3 4 2 3 a) The expected completion time for this project is (enter your response as a whole number),

  • Ross Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor relationships in the...

    Ross Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor relationships in the following table for building ne a b 2 5 1 Activity А B С D E F 1 Time (weeks) a m b 6 8 10 2 9 23 9 12 16 5 6 10 1 3 4 5 9 20 Immediate Predecessor(s) Activity G A H А А B к CE Time (weeks) m 3 1 7 7 3 Immediate Predecessor(s) CE F...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT