Question

Rich Cole Control Devices, Inc., produces custom-built relay devices for auto makers. The most recent project undertaken by Cole requires 14 different activities appropriate data are shown in the following table Time (days) Immediate bPredecessor(s)Activitya Time (days) Immediate Activity a bPredecessor(s) E, F G, H 10 17 B, C 5 6 10 6 L, M a) The expected completion time of the project days (round your response to two decimal places) The activities that represent the projects critical path are b) If the time to complete the activities on the critical path is normally distributed, then the probability that the critical path will be finished in 54 days or less- I frNumber of days that would result in 99% probability of completion = days round your response to two decimal places

0 0
Add a comment Improve this question Transcribed image text
Answer #1

First we calculate the most likely time. This is done by

Most likely time = (a + 4m + b)/6

Then we calculate the project variance by

Variance = ((b – a)/6)^2

Once we have these values we shall calculate the early start, finish, and late start, finish values in order to determine the slack and critical path.

The calculated values for each of them are shown below.

1Activity Predecessor most likely variance Slack 0.00 10.50 12.83 10.50 12.83 0.00 4.17 12.83 22.67 12.83 22.67 0.00 13.67 18.50 17.83 22.67 4.17 6.67 22.67 26.17 22.67 26.170.00 26.17 31.00 26.17 31.00 0.00 1.50 31.00 39.83 31.00 39.83 0.00 1.50 0.00 42.17 50.33 42.17 50.33 0.00 ES EF 5.83 2.33 12.83 13.67 LF 5.83 2.33 0.25 0.44 0.00 1.36 6.25 1.36 2.25 0.25 1.36 1.00 0.69 1.00 0.44 0.69 0.00 5.83 5.83 5.83 10.00 17.83 7.83 9.83 4.83 5.83 3.50 4.83 5.33 8.83 4.33 2.33 8.17 5.83 10 17 10 13.67 19.50 20.33 26.17 10 G,H 31.00 36.33 32.50 37.83 12 36.33 40.67 37.83 42.17 39.83 42.17 39.83 42.17 15 16 6 18 20 Sheet731 Sheet733 Sheet734 Sheet735 Sheet736 Shect737 AVERAGE: 1293680556 COUNT: 96 SUM: 1034.944444囲回凹- +130%

a)

Expected completion time of the project is = 50.33 days

The activities that present the critical path are A-C-E-H-I-K-M-N

b)

We can consider the project completion mean time as 50.33 days. The variance along the critical path is 9.94 days (sum up the variance for ACEHIK)

This means the standard deviation is sqrt(9.94) = 3.15 days.

The z value will be

Z = (54-50.33)/3.15 = 1.16

This means the probability of the project finishing in 54 days or less is P(z) = 0.878 or 87.8%

c)

For 99% probability the z value is 2.32. This means we have

2.32 = (X – 50.33)/3.15

X = 57.65 days

At 57.65 days, there will be a 99% probability of completion.

Add a comment
Know the answer?
Add Answer to:
Rich Cole Control Devices, Inc., produces custom-built relay devices for auto makers. The most recent project...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Coleman Rich Control Devices, Inc., produces custom-built relay devices for auto makers. The most recent project...

    Coleman Rich Control Devices, Inc., produces custom-built relay devices for auto makers. The most recent project undertaken by Rich requires 14 different activities. Rich's managers would like to determine the total project completion time (in days) and those activities that lie along the critical path. The appropriate data are shown in the following table: பா் Immediate Immediate Time (days) Time (days) Predecessor(s) Activity Predecessor(s) b b Activity a 6 E, F G, H A 4 5 8 3 3 B...

  • please help!! The estimated times and immediate predecessors for the activities in a project at Howard...

    please help!! The estimated times and immediate predecessors for the activities in a project at Howard Umrah's retinal scanning company are given in the following table. Assu that the activity times are independent. Time (weeks) Immediate Time (weeks) Immediate Activity a bPredecessor(s)Activitya bPredecessor(s) 12 10 12 8 17 This exercise contains only parts a, b, c, d, and e a) Based on the activity time estimates, the expected times and variance for each of the activities are (round your response...

  • The estimated times and immediate predecessors for the activities in a project

    The estimated times and immediate predecessors for the activities in a project at Howard Umrah's retinal scanning company are given in the following table. Assume that the activity times are independent This exercise contains only parts a, b, c, d, and e. a) Based on the activity time estimates, the expected times and variance for each of the activities are (round your response to two decimal places): ExpectedActivityTimeWarlanceA9.830.26010.336.44C10.001.00010.001.78b) The expected completion time of the critical path weeks fround your response to two decimal...

  • project management

    1.     Ross Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor relationships in the following table for building new motels.  ActivityTime (weeks)a         m           bImmediatePredecessor(s) Activity aTime (weeks)m bImmediatePredecessor(s)A4810—G234C, EB2824AH222FC81216AI666FD4610AJ4612D, G, HE123BK223I, JF6820C, E a)  The expected (estimated) time for activity C is                         weeks. (Round your response to two decimal places.) b)  The variance for activity C is                         weeks. (Round your response to two decimal places.) c)  Based on the calculation of the estimated times, the critical path...

  • HW Score: 62.5%,5 of The estimated times and immediate predecessors for the activities in a projects...

    HW Score: 62.5%,5 of The estimated times and immediate predecessors for the activities in a projects Howard Urinalarning company are given in the following assume that the activity times are independent Question Help Activity . Immediate Predecessor) А 8 Time (weeksi . Predecessors Activity b 8 10 С 7 19 13 4 10 18 D 6 10 14 This exercise contains only parts , bedande a) Based on the activity time estimate the expected times and variance for each of...

  • Problem 5-10 The following represents a project that should be scheduled using CPM: IMMEDIATE TIMES (DAYS)...

    Problem 5-10 The following represents a project that should be scheduled using CPM: IMMEDIATE TIMES (DAYS) ACTIVITY PREDECESSORS a m b А 7 B 2 3 7 с A 3 5 7 D А 5 6 10 E B 1 2 6 F CD 1 3 6 DE 1 3 14 H F G 5 14 b. What is the critical path? A-D-G-H B-E-G-H A-D-F-H A-C-F-H c. What is the expected project completion time? (Round your answer to 3 decimal...

  • The following represents a project that should be scheduled using CPM: TIMES (DAYS) ACTIVITY IMMEDIATE PREDECESSORS...

    The following represents a project that should be scheduled using CPM: TIMES (DAYS) ACTIVITY IMMEDIATE PREDECESSORS a m b A — 1 3 5 B — 1 2 3 C A 1 2 3 D A 2 3 4 E B 3 4 11 F C, D 3 4 5 G D, E 1 4 6 H F, G 2 4 5 b. What is the critical path? A-C-F-H A-D-F-H B-E-G-H A-D-G-H c. What is the expected project completion time?...

  • The following represents a project that should be scheduled using CPM: TIMES (DAYS) IMMEDIATE b ACTIVITY...

    The following represents a project that should be scheduled using CPM: TIMES (DAYS) IMMEDIATE b ACTIVITY PREDECESSORS m a 1 4 7 3 5 10 B 2 5 4 6 11 D B 1 2 3 E C,D D,E F,G 3 5 7 F G 1 2 6 2 5 b. What is the critical path? A-D-F-H A-D-G-H B-E-G-H A-C-F-H c. What is the expected project completion time? (Do not round intermediate calculations. Round your answer to 3 decimal places.)...

  • The following represents a project that should be scheduled using CPM: IMMEDIATE PREDECESSORS TIMES (DAYS) ACTIVITY...

    The following represents a project that should be scheduled using CPM: IMMEDIATE PREDECESSORS TIMES (DAYS) ACTIVITY a m b A — 1 4 7 B — 2 6 13 C A 1 1 4 D A 2 3 4 E B 2 4 6 F C,D 1 5 9 G D,E 1 2 9 H F,G 3 6 9 b. What is the critical path? A-D-G-H B-E-G-H A-D-F-H A-C-F-H c. What is the expected project completion time? (Do not round...

  • Problem 5-10 The following represents a project that should be scheduled using CPM: IMMEDIATE PREDECESSORS TIMES...

    Problem 5-10 The following represents a project that should be scheduled using CPM: IMMEDIATE PREDECESSORS TIMES (DAYS) ACTIVITY a m b A — 1 4 7 B — 3 5 10 C A 2 5 8 D A 4 6 11 E B 1 2 3 F C,D 3 5 7 G D,E 1 2 6 H F,G 2 5 6 b. What is the critical path? B-E-G-H A-D-G-H A-D-F-H A-C-F-H c. What is the expected project completion time? (Round...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT