Question

project are listed for a In the following table the activities with their precedence sequence and expected time (days) Immedi
0 0
Add a comment Improve this question Transcribed image text
Answer #1

1. A. CRITICAL PATH = A - C - F - G - I

PROJECT LENGTH = LENGTH OF CRITICAL PATH = 23

The ES, EF values are calculated using a forward pass where the ES of the next activity is the maximum EF of all the predecessor activities.

The LS, LF values are calculated using a backward pass where the LS of the next activity is the minimum LF of all the predecessor activities.

The critical path represents all the activities in a particular chain which have the largest duration and 0 slack for all activities, and due to this fact, any delay in the critical activities can cause a delay for the entire project.

ACTIVITY

DURATION

PRE 1

PRE 2

ES

EF

LS

LF

SLACK

A

7

0

7

0

7

0

B

2

A

7

9

8

10

1

C

4

A

7

11

7

11

0

D

5

B

9

14

10

15

1

E

5

B

9

14

11

16

2

F

5

C

11

16

11

16

0

G

2

E

F

16

18

16

18

0

H

3

D

14

17

15

18

1

I

5

G

H

18

23

18

23

0

CRITICAL PATH = A - C - F - G - I

PROJECT LENGTH = LENGTH OF CRITICAL PATH = 23

Add a comment
Know the answer?
Add Answer to:
project are listed for a In the following table the activities with their precedence sequence and...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT