1. A. CRITICAL PATH = A - C - F - G - I
PROJECT LENGTH = LENGTH OF CRITICAL PATH = 23
The ES, EF values are calculated using a forward pass where the ES of the next activity is the maximum EF of all the predecessor activities.
The LS, LF values are calculated using a backward pass where the LS of the next activity is the minimum LF of all the predecessor activities.
The critical path represents all the activities in a particular chain which have the largest duration and 0 slack for all activities, and due to this fact, any delay in the critical activities can cause a delay for the entire project.
ACTIVITY |
DURATION |
PRE 1 |
PRE 2 |
ES |
EF |
LS |
LF |
SLACK |
A |
7 |
0 |
7 |
0 |
7 |
0 |
||
B |
2 |
A |
7 |
9 |
8 |
10 |
1 |
|
C |
4 |
A |
7 |
11 |
7 |
11 |
0 |
|
D |
5 |
B |
9 |
14 |
10 |
15 |
1 |
|
E |
5 |
B |
9 |
14 |
11 |
16 |
2 |
|
F |
5 |
C |
11 |
16 |
11 |
16 |
0 |
|
G |
2 |
E |
F |
16 |
18 |
16 |
18 |
0 |
H |
3 |
D |
14 |
17 |
15 |
18 |
1 |
|
I |
5 |
G |
H |
18 |
23 |
18 |
23 |
0 |
CRITICAL PATH = A - C - F - G - I
PROJECT LENGTH = LENGTH OF CRITICAL PATH = 23
project are listed for a In the following table the activities with their precedence sequence and...
In the following table the activities with their precedence sequence and expected time (days) are listed for a project: Activity Immediate Predecessor(s) Time (days) - ITMO OWNono Ana E, F D GH a) The activities on the critical path are b) The project length is days. A-B-E-G-1 A-B-D-H-1 A-C-F-G-
In the following table the activities with their precedence sequence and expected time (days) are listed for a project on which Carl Betterton's construction company is working: Activity Immediate Predecessor(s) Time (days) A minus− 5 B A 4 C A 6 D B 6 E B 4 F C 4 G D 6 H E, F 7 Carl's team should be able to complete the project in nothing days. Critical path activities for Carl's project are .
In the following table the activities with their precedence sequence and expected time (days) are listed for a project: Activity Immediate Predecessor(s) Time (days) S A Figure 1 C A 4 5 5 F 5 F G E, F D GH 2 3 H The correct AOA precedence diagram is shown in a Figure 2 Q Figure 3
In the following table the activities with their precedence sequence and expected time (days) are listed for a project Activity Immediate Predecessor(s) Time (days) E, F G, H The correct AOA precedence diagram is shown in Figure 1 Figure 2 Figure 3 Figure 1 Figure 2 Figure 3 In the following table the activities with their precedence sequence and expected time (days) are listed for a project Activity Immediate Predecessor(s) Time (days) E, F G, H The correct AOA precedence...
In the following table the activities with their precedence sequence and expected time (days) are listed for a project on which Carl Betterton's construction company is working: Activity Immediate Predecessor(s) Time (days) A minus− 55 B A 44 C A 66 D B 66 E B 44 F C 44 G D 66 H E, F 99 Carl's team should be able to complete the project in ? days.
Draw an activity on the arrow network for the activities of a project as shown in table, indicate the critical path and calculate the total float Activity description immediate predecessor Expected time (Weeks) A - 5 B - 4 C A 7 D B 7 E B 8 F B 5 G C,D 8 H E,I 11 I F 2 J F 12 K H,I 11 2.convert the above into activity on the node
1. The activities needed for a new project your company is undertaking are listed in the following table. ACTIVITY IMMEDIATE PREDECESSOR(S) A ---- B ---- C A D A, B E B F C, D, E G D, E H F I F, G J G The activity times were determined for the project, and were as below. ACTIVITY ACTIVITY TIME (days) A 11 B 9 C 7 D 12 E 8 F 9 G 10 H 6 I 7...
Given the following Project Activities and Precedence Relations table; determine the Critical Path, and the minimum Project Duration. Create the Gantt Chart for the project represented in the table. Project Activities and Precedence Relations ACTIVITY DURATION PRECEDED BY: А 3 B 2 A C 2 1 D E 1 B F 2 1 D D G H 4 2 BD E J 1 E F 4 K L 3 G M N 3 3 H 0 4 HKL P MNO...
Given the following Project Activities and Precedence Relations table; determine the Critical Path, and the minimum Project Duration. Create the Gantt Chart for the project represented in the table. Project Activities and Precedence Relations ACTIVITY DURATION PRECEDED BY: A 3 B 2 A C 2 D 1 E 1 B F G 2 1 D D H 4 BD 2 J J 1 4 K F L 3 G M N 3 3 IJ H 0 4 HKL MNO Р...
A project for improving a billing process has the following precedence relationships and activity times: Activity Activity Time (weeks) Immediate Predecessor(s) B, C I Q7 Moow E F, G b. Calculate the slack for each activity. Which activities are on the critical path? Activity Activity Time (weeks) On critical path? Yes Slack (weeks) D 0 Yes 0 0 00000000 @ Tm I