In the following table the activities with their precedence sequence and expected time (days) are listed for a project on which Carl Betterton's construction company is working:
Activity |
Immediate Predecessor(s) |
Time (days) |
A |
minus− |
5 |
B |
A |
4 |
C |
A |
6 |
D |
B |
6 |
E |
B |
4 |
F |
C |
4 |
G |
D |
6 |
H |
E, F |
7 |
Carl's team should be able to complete the project in
nothing
days.
Critical path activities for Carl's project are
.
The various paths and their expected completion time of the project are
So the critical path is A-C-F-H as it has the longest expected completion time of 22 days
Expected completion time of the project = expected completion time of the critical path = 22 days. So Carl's team should be able to complete the project in 22 days
In the following table the activities with their precedence sequence and expected time (days) are listed...
In the following table the activities with their precedence sequence and expected time (days) are listed for a project: Activity Immediate Predecessor(s) Time (days) - ITMO OWNono Ana E, F D GH a) The activities on the critical path are b) The project length is days. A-B-E-G-1 A-B-D-H-1 A-C-F-G-
project are listed for a In the following table the activities with their precedence sequence and expected time (days) Immediate Predecessor(s) Time (days) Activity 7 A 2 A B 4 C 4 5 5 E C F 2 G E, F 3 H G, H a) The activities on the critical path are b) The project length is days.
In the following table the activities with their precedence sequence and expected time (days) are listed for a project: Activity Immediate Predecessor(s) Time (days) S A Figure 1 C A 4 5 5 F 5 F G E, F D GH 2 3 H The correct AOA precedence diagram is shown in a Figure 2 Q Figure 3
In the following table the activities with their precedence sequence and expected time (days) are listed for a project Activity Immediate Predecessor(s) Time (days) E, F G, H The correct AOA precedence diagram is shown in Figure 1 Figure 2 Figure 3 Figure 1 Figure 2 Figure 3 In the following table the activities with their precedence sequence and expected time (days) are listed for a project Activity Immediate Predecessor(s) Time (days) E, F G, H The correct AOA precedence...
The following represent activities in Marc Massoud's Construction Company project: Activity Immediate Predecessor(s) Time (weeks) Activity Immediate Predecessor(s) Time (weeks) = C, E WLUI WNVN = n a a) Choose the correct network to represent this situation. OA. OB b) The critical path is B-E-F-H c) The length of the critical path is . weeks.
A project for improving a billing process has the following precedence relationships and activity times: Activity Activity Time (weeks) Immediate Predecessor(s) B, C I Q7 Moow E F, G b. Calculate the slack for each activity. Which activities are on the critical path? Activity Activity Time (weeks) On critical path? Yes Slack (weeks) D 0 Yes 0 0 00000000 @ Tm I
A Question 11 The following table provides a list of activities in a project, along with their respective durations and precedence requirements: Immediate Duration Activity Predecessor(s) (weeks) 2 B 3 C B D А E A.C 1 F DE 3 с 3 2 6 G Determine the amount of slack time for Activity E: a. O weeks b. 1 week C. 2 weeks O d. 3 weeks Question 12 Assume that activity A has the following times: Early start time...
Given the following Project Activities and Precedence Relations table; determine the Critical Path, and the minimum Project Duration. Create the Gantt Chart for the project represented in the table. Project Activities and Precedence Relations ACTIVITY DURATION PRECEDED BY: А 3 B 2 A C 2 1 D E 1 B F 2 1 D D G H 4 2 BD E J 1 E F 4 K L 3 G M N 3 3 H 0 4 HKL P MNO...
Given the following activities and precedents, draw a PERT/CPM diagram. ACTIVITY IMMEDIATE PREDECESSOR DURATION (DAYS) A - 10 B - 12 C A 4 D A, B 8 E A, B 9 F C 10 G D, F 12 H E, G 15 Answer the following: What is the critical path? How long will it take to complete this project? Can activity E be delayed without delaying the completion of the project? If so, how many days?
Given the following Project Activities and Precedence Relations table; determine the Critical Path, and the minimum Project Duration. Create the Gantt Chart for the project represented in the table. Project Activities and Precedence Relations ACTIVITY DURATION PRECEDED BY: A 3 B 2 A C 2 D 1 E 1 B F G 2 1 D D H 4 BD 2 J J 1 4 K F L 3 G M N 3 3 IJ H 0 4 HKL MNO Р...