Question

In the following table the activities with their precedence sequence and expected time (days) are listed for a project: Activ

0 0
Add a comment Improve this question Transcribed image text
Answer #1

ACTIVITY

DURATION

ES

EF

LS

LF

SLACK

A

7

0

7

0

7

0

B

2

7

9

8

10

1

C

4

7

11

7

11

0

D

5

9

14

10

15

1

E

5

9

14

11

16

2

F

5

11

16

11

16

0

G

2

16

18

16

18

0

H

3

14

17

15

18

1

I

6

18

24

18

24

0

FORWARD PASS

1. Go from left to right in a network.

2. ES = maximum of the EF value from all the direct predecessors.

3. EF = ES + Duration.

BACKWARD PASS

1. Go from right to left in a network.

2. LF = minimum of the LS value from all the direct predecessors.

3. LS = LF - Duration.


CRITICAL PATH

1. Total slack of all activities should be 0.

2. The total duration of all the activities should be the highest.

3. Slack = LF - EF or LS - ES

CRITICAL PATH & DURATION

A + C + F + G + I = 24

Add a comment
Know the answer?
Add Answer to:
In the following table the activities with their precedence sequence and expected time (days) are listed...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT